- This event has passed.
December 7, 2023 Commission Meeting
This Commission meeting will be conducted in a hybrid format in accordance with SB 143 (2023). To maximize public safety while maintaining transparency and public access, members of the public can choose to participate either virtually via Zoom, by phone, or in person at the location listed below. Physical attendance at Metro Center requires that all individuals adhere to the site’s health guidelines including, if required, wearing masks, health screening, and social distancing.
Note: Agenda Item 8 and 11 have been postponed.
Metro Center
375 Beale Street
San Francisco, 415-352-3600
If you have issues joining the meeting using the link, please enter the Meeting ID and Password listed below into the ZOOM app to join the meeting.
Join the meeting via ZOOM
Live Webcast
See information on public participation
Teleconference numbers
1 (866) 590-5055
Conference Code 374334
Meeting ID
825 5739 1023
Passcode
407711
If you call in by telephone:
Press *6 to unmute or mute yourself
Press *9 to raise your hand or lower your hand to speak
Tentative Agenda
- Call to Order
- Roll Call
- Public Comment Period (Each speaker is limited to three minutes) A maximum of 15 minutes is available for the public to address the Commission on any matter on which the Commission either has not held a public hearing or is not scheduled for a public hearing later in the meeting. Speakers will be heard in the order of sign-up, and each speaker is generally limited to a maximum of three minutes. It is strongly recommended that public comments be submitted in writing so they can be distributed to all Commission members for review. The Commission may provide more time to each speaker and can extend the public comment period beyond the normal 15-minute maximum if the Commission believes that it is necessary to allow a reasonable opportunity to hear from all members of the public who want to testify. No Commission action can be taken on any matter raised during the public comment period other than to schedule the matter for a future agenda or refer the matter to the staff for investigation, unless the matter is scheduled for action by the Commission later in the meeting.
(Steve Goldbeck) [415/352-3611; steve.goldbeck@bcdc.ca.gov] - Approval of Minutes for November 16, 2023 Meeting (PDF)
(Reylina Ruiz) [415/352-3638; reylina.ruiz@bcdc.ca.gov] - Report of the Chair
- Report of the Executive Director
- Commission Consideration of Administrative Matters
There is no administrative listing
(Harriet Ross) [415/352-3615; harriet.ross@bcdc.ca.gov] - Commission Consideration of a Contract with the Port of San Francisco to Fund Planning Activities
POSTPONED
The Commission will consider authorizing the Executive Director to enter into a contract with the Port of San Francisco to fund a planning position that will lead several activities, including amending the San Francisco Waterfront Special Area Plan (Bay Plan Amendment No. 3-17) and coordinating between Port of San Francisco and BCDC on regulatory and planning issues.
(Erik Buehmann) [415/352-3645; erik.buehmann@bcdc.ca.gov] - Public Hearing and Possible Vote to Approve Stipulated Orders CCD2023.002.00 and CCD2023.003.00
The Commission will hold a public hearing and possibly vote to approve two stipulated orders as recommended by the Enforcement Committee to resolve BCDC Enforcement Case No. ER2019.063.00 against Seaplane Investments LLC alleging unauthorized development activities and violations of BCDC permits 1973.014.04 and M1985.030.01 in Sausalito, Marin County.
(Greg Scharff) [650/868-9303; greg.scharff@bcdc.ca.gov]
Executive Director’s Recommended Enforcement Decision with Exhibits - Public Hearing on the US Army Corps of Engineers, San Francisco District’s Proposed Phased Consistency Determination for the Oakland Turning Basins Widening Project.
The Commission will hold a public hearing to receive comment on the US Army Corps of Engineers, San Francisco District’s proposed Port of Oakland Outer and Inner Harbor Turning Basins Widening Project, Alameda County. In order to improve the ability of large ships calling at the Port of Oakland to turn around, the USACE proposes to widen the Outer Harbor Turning Basin from 49 acres to 70 acres, and the Inner Harbor Turning Basin from 41 acres to 61 acres. At the Inner Harbor Turning Basin portions of Howard Terminal and Alameda former Naval Annex wharves, land beneath the wharves, infrastructure, and portions of buildings would be removed. Both turning basins would require dredging of the new areas to minus 50 feet Mean Lower Low Water (MLLW). In addition, sheet and batter piles, and rip rap would create new bulkheads in Oakland and Alameda. Adjacent to Schnitzer Steel, a subtidal retaining wall with rip rap would stabilize the slope from the shore to subtidal bottom. The disposal of construction debris and dredged sediment is targeted for an appropriately classed landfill, and beneficial reuse at a wetlands restoration site when the materials are of suitable quality. The disposal and reuse site locations are not fully defined, but could occur in Marin and/or Solano County, and a landfill(s) outside of the Commission’s jurisdiction, respectively.
(Brenda Goeden) [415/352-3623; brenda.goeden@bcdc.ca.gov
Presentation (PDF) // Public Comment (PDF) // Application Summary Addendum (PDF) // Staff Presentation (PDF) - Briefing on Updates to the California Sea-Level Rise Guidance
POSTPONED
Representatives of the California Natural Resources Agency Ocean Protection Council (OPC) will brief the Commission on updates to the California Sea-Level Rise Guidance, last issued in 2018. This update aims to incorporate the most current scientific knowledge and improved planning and decision-making guidance to support preparedness for rising sea levels, and is used by BCDC to determine how best to ensure that projects and plans are resilient to rising sea levels.
(Jessica Fain) [415/352-3642; jessica.fain@bcdc.ca.gov] - Adjournment
Supplemental Materials
Commission Mailing November 17, 2023
Commission Mailing December 1, 2023
- Revised December 7, 2023 Commission Meeting – Agenda Item 8 has been postponed
- Draft Minutes of November 16, 2023 Hybrid Commission Meeting (PDF)
Articles about the Bay and BCDC
- When sea levels rise, so does your rent
- There’s a big new sea wall in the Bay Area, is this the future?
- No water, power, Wi-Fi or parking – but for $25 million, this island on S.F. Bay can be yours
- Bay Area Housing Project Raises Concerns About Sea-Level Rise
- MLB owners approve Athletics’ planned move to Las Vegas, sources say
- Bay Area Housing Project Raises Concerns About Sea-Level Rise
Meeting Minutes
Audio Recording & Transcript
Audio Recording
CHAIR, ZACHARY WASSERMAN:
GOOD AFTERNOON, ALL, AND
WELCOME. TO OUR, ONCE AGAIN,
HYBRID BCDC COMMISSION MEETING.
MY NAME IS ZACK WASSERMAN, AND I
AM THE CHAIR OF BCDC.
BEFORE WE GET STARTED, I WANT TO
INFORM THAT YOU BOTH ITEMS EIGHT
REGARDING A CONTRACT WITH THE
PORT OF SAN FRANCISCO AND ITEM
11 REGARDING THE UPDATE OF SEA
LEVEL RISE GUIDANCE HAVE BEEN
POSTPONED, HOPEFULLY TO OUR NEXT
MEETING.
OUR FIRST ORDER OF BUSINESS IS
TO CALL THE ROLL. COMMISSIONERS
IF YOU ARE PARTICIPATING
VIRTUALLY, PLEASE UNMUTE
YOURSELVES WHEN YOU ANSWER, AND
THEN MUTE YOURSELVES AGAIN
AFTERWARDS. RAY LYNN A WILL YOU
PLEASE CALL THE ROLL?
>>CLERK, REYLINA RUIZ: CHAIR
WASSERMAN?
>>CHAIR, ZACHARY WASSERMAN:
HERE.
>>CLERK, REYLINA RUIZ: VICE
CHAIR EISEN?
>>V. CHAIR, REBECCA EISEN:
HERE.
>>CLERK, REYLINA RUIZ:
COMMISSIONER ADDIEGO?
>>ANDREW FREMIER: HERE.
>>CLERK, REYLINA RUIZ: AHN?
>>EDDIE AHN: HERE.
>>CLERK, REYLINA RUIZ: AMBUEHL?
>>DAVID AMBUEHL: HERE.
>>CLERK, REYLINA RUIZ: BURT?
>>ANDREW FREMIER: HERE.
>>CLERK, REYLINA RUIZ: ECKERLY?
>>JENN ECKERLE: HERE.
>>CLERK, REYLINA RUIZ: ECKLUND?
>>PATRICIA SHOWALTER: PRESENT.
>>CLERK, REYLINA RUIZ:
COMMISSIONER GILMORE?
>>MARIE GILMORE: HERE.
>>CLERK, REYLINA RUIZ: GIOIA?
>>JOHN GIOIA: HERE.
>>CLERK, REYLINA RUIZ: GORIN?
>>SUSAN GORIN: HERE.
>>CLERK, REYLINA RUIZ: GUNTHER?
>>ANDREW GUNTHER: HERE.
>>CLERK, REYLINA RUIZ: HASZ?
>>V. CHAIR, KARL HASZ: HERE.
>>CLERK, REYLINA RUIZ:
JOHN-BAPTISTE?
>>ALICIA JOHN BAPTISTE: HERE.
>>CLERK, REYLINA RUIZ:
KISHIMOTO?
>>YORIKO KISHIMOTO: HERE.
>>CLERK, REYLINA RUIZ: NELSON?
>>BARRY NELSON: HERE.
>>CLERK, REYLINA RUIZ:
PEMBERTON?
COMMISSIONER PESKIN?
>>AARON PESKIN: PRESENT.
>>CLERK, REYLINA RUIZ:
COMMISSIONER PINE?
>>DAVE PINE: HERE.
>>CLERK, REYLINA RUIZ:
COMMISSIONER RAMOS?
>>BELIA RAMOS: HERE.
>>CLERK, REYLINA RUIZ:
COMMISSIONER WILLIAMS?
>>SPEAKER: HERE.
>>CLERK, REYLINA RUIZ:
COMMISSIONER ZAPEDA?
>>CESAR ZEPEDA: HERE.
>>CLERK, REYLINA RUIZ: DID I
FORGET ANYONE?
>>STEPHANIE MOULTON-PETERS:
MOULTON-PETERS?
>>CLERK, REYLINA RUIZ: SORRY.
THANK YOU.
>>SPEAKER: AND PEMBERTON.
HERE.
>>CLERK, REYLINA RUIZ: 23
COMMISSIONERS PRESENT.
>>CHAIR, ZACHARY WASSERMAN: WE
HAVE A QUORUM AND SO WE CAN
PROCEED. IT’S A LITTLE A BIT
LIKE A QUAKER QUILT, IF YOU
DON’T LEAVE SOMEBODY OUT, THEN
IT’S TOO PERFECT.
[LAUGHTER]
ITEM THREE IS PUBLIC COMMENT.
YOU HAVE THREE MINUTES TO
ADDRESS THE COMMISSION ON ANY
ITEM NOT ON OUR AGENDA, OR NOT
WHERE WE HAVE NOT — WHERE WE
HAVE NOT HELD A PUBLIC HEARING,
OR ARE NOT SCHEDULED TO.
I DO WANT TO REMIND YOU, ALL, OF
THE UNFORTUNATE INCREASE IN THIS
TERRIBLE WORD ZOOM BOMBING OF
BOTH LOCAL AND REGIONAL
AGENCIES, AND THEIR MEETINGS.
EVERYONE PLEASE DO NOTE, AS WAS
SAID IN THE INTRODUCTORY VIDEO,
THAT BCDC WILL NOT TOLERATE ANY
FORM OF HATE SPEECH OR THREATS
OF ANY GROUPS, AGAINST ANY
GROUPS OR INDIVIDUALS. AND AS
CHAIR, I WANT YOU TO KNOW THAT I
WE WOULD A VERY HEAVY HAMMER ON
THOSE ISSUES.
WITH THAT, DO WE HAVE ANY
MEMBERS IN THE ROOM WHO HAVE
SUBMITTED CARDS?
>>CLERK, REYLINA RUIZ: I HAVE
NO CARDS.
>>CHAIR, ZACHARY WASSERMAN: AND
DO WE HAVE ANYBODY ON ZOOM WHO
WISHES TO SPEAK.
>>CLERK, REYLINA RUIZ: NO
PUBLIC COMMENT.
>>CHAIR, ZACHARY WASSERMAN: NO
PUBLIC COMMENT. THIS IS GOING
TO BE A VERY QUICK MEETING,
EVERYBODY.
THAT BRINGS US TO APPROVAL OF
OUR MINUTES OF NOVEMBER 16TH.
WE HAVE ALL RECEIVED COPIES. I
WOULD ENTERTAIN A MOTION TO
APPROVE, AND A SECOND.
COMMISSIONER MOULTON-PETERS
MOVED. I SAW IT.
COMMISSIONER BAPTIST SECONDED.
I SAW HER MOVING HER HAND.
[LAUGHTER]
ANY CORRECTIONS OR ADDITIONS TO
THE MINUTES?
SEEING NONE.
DOES ANYBODY WISH TO OPPOSE OR
ABSTAIN?
I DON’T SEE ANY. THE MINUTES
ARE APPROVED UNANIMOUSLY.
THAT BRINGS US TO MY REPORT.
OUR NEXT MEETING WILL BE HELD ON
A.M. AT THAT MEETING WE MAY
TAKE UP THE FOLLOWING MATTERS
CONSIDERATION OF A CONTRACT WITH
THE PORT OF SAN FRANCISCO
REGARDING SAN FRANCISCO
WATERFRONT SPECIAL AREA PLAN
THAT WE POSTPONED TODAY. A
POTENTIAL COMMISSION VOTE ON THE
PROPOSED OAKLAND TURNING BASIN
EXPANSION ON WHICH WE ARE
HOLDING A PUBLIC HEARING TODAY.
A BRIEFING ON THE UPDATE OF SEA
LEVEL RISE GUIDANCE FROM THE
STATE, ALSO POSTPONED FROM
TODAY. A BRIEFING ON THE SUISUN
MARSH IN SOLANO COUNTY, AND A
BRIEFING ON BAY ADAPT.
JUST A COUPLE OF BRIEF COMMENTS.
AS I NOTED EARLIER, SLIGHTLY
JOKING, THIS IS GOING TO BE A
BRIEF MEETING. ENJOY THE GIFT
OF TIME. I THINK NEXT MEETING
WILL BE A BIT LONGER. AND AS WE
MOVE INTO THE NEW YEAR, I THINK
THEY WILL BE LONGER. I THINK
WE’LL START TAKING ON MORE
IN-DEPTH SOME OF THE POLICIES WE
HAVE BEEN DISCUSSING AND I AM
CERTAIN THERE WILL BE SOME
INTERESTING HEARINGS ALONG THE
WAY. THERE WAS AN INTERNATIONAL
SCIENTIFIC REPORT THAT NOTED
OVER THE LAST TEN YEARS GIVE OR
TAKE OR MAYBE EVEN ARE LONGER,
THE RATE OF SEA LEVEL RISE HAS
DOUBLED OVER THE LONG-TERM
TREND. IT’S STILL SMALL, BUT
THAT IS SIGNIFICANT AND
INDICATES THE WATER THAT WE KNOW
IS COMING, WELCOME OR NOT, IS
COMING, AND WE NEED TO KEEP
DOING OUR WORK, AS WE ARE, AND
WE NEED TO KEEP PUSHING OUR
COLLABORATORS AND PARTNERS ON
MOVING EVER FASTER. BECAUSE THE
SEA AIN’T WAITING FOR US.
WITH THAT, THIS IS A MOMENT TO
PUT ON THE RECORD ANY EX PARTE
COMMUNICATIONS YOU MAY HAVE HAD
THAT YOU HAVE NOT PUT IN WRITING
THROUGH OUR WEB SITE. YOU DO
NEED TO DO THAT, IN ANY END OF
THE EVENT, AND THESE ARE ON
ADJUDICATORIAL MATTERS NOT ON
POLICY MATTERS. ANYBODY HAVE
ANY EX PARTE COMMUNICATION TO
REPORT? SEEING NONE. THAT
BRINGS US TO THE REPORT OF OUR
EXECUTIVE DIRECTOR. EXECUTIVE
DIRECTOR GOLDZBAND IS ON
VACATION, AND EXECUTIVE DIRECTOR
SCHARFF IS ACTING TO PROVIDE THE
REPORT.
>>GREG SCHARFF: I’M GREG
SCHARFF IT’S BEEN A PLEASURE
SERVING AS YOUR ACTING EXECUTIVE
DIRECTOR FOR THE LAST FEW WEEKS
WHILE LARRY HAS BEEN OUT. I
WANT TO NOTE TODAY IS PERIL
HARBOR DAY AND I CAN ONLY
IMAGINE HOW LARRY WOULD HAVE
WEAVED THAT INTO THE REPORT.
UNFORTUNATELY YOU HAVE ME, NOT
LARRY. SO, YOU WILL JUST HAVE
TO IMAGINE.
NOW, FIRST OF ALL, I WANT TO
THANK EVERYONE WHO INDICATED
THEY WILL BE PRESENT FOR THE
DECEMBER 21ST COMMISSION
MEETING, AND STRESS THAT IT’S
CRITICAL THAT YOU DO SO, AS WE
WILL ALL BE TAKING A VOTE AT THE
MEETING ON TODAY’S ITEM 10,
WHICH IS THE THE PROPOSED PHASE
CONSISTS OF DETERMINATION FOR
THE PROPOSED BASIN-WIDENING
PROJECT AND WE WILL NEED A
QUORUM FOR THAT.
I WANT TO NOTE AS PART OF BCDC
SEDIMENT FOR WETLAND ADAPTATION
PROJECT, BCDC AND PARTNERS US
EPA COASTAL CONSERVANCY REGIONAL
WATER BOARD, SFEI AND SAN
FRANCISCO BAY JOINT VENTURE ARE
HOSTING A WORKSHOP IN-PERSON ON
JANUARY 23RD AND FEBRUARY 13TH,
2024 TO REVIEW AND DISCUSS
POTENTIAL CHANGES TO SEDIMENT
MANAGEMENT AND IMPLEMENTATION
ROADMAP OF ACTIONS TO INCREASE
BENEFICIAL USE OF SOIL AND
SEDIMENT IN THE BAY AREA. THE
WORKSHOP WILL WORK WITH A
VARIETY OF STAKEHOLDERS WHO ARE
INVOLVED IN AND IMPACTED BY
SEDIMENT IN THE BAY AREA. WE
WILL BE HOLDING OUR SECOND BAY
ADAPT COORDINATING MEETING ON
12/8 AND ELECTED OFFICIALS TASK
FORCE MEETING ON 12/19. FINALLY
NOVEMBER 27TH COASTAL MANAGEMENT
ISSUED TWO DECISION LETTERS
APPROVING CHANGES TO THE COASTAL
MANAGEMENT PROGRAM UNDER THE
COASTAL ZONE MANAGEMENT ACT NOAA
HAS APPROVED TWO SETS OF
AMENDMENT TO THE COMMISSION’S
REGULATION ADOPTED IN 2022
REGULATIONS CONCERNING
ENFORCEMENT PROCEDURES
ADMINISTRATIVE CIVIL PENALTY
POLICY AND THE IMPLEMENTATION OF
THE CALIFORNIA ENVIRONMENTAL
QUALITY ACT WITH NOAA PRIVATE
PRIOR APPROVAL OF THE ELEMENTS
COMMISSIONS REGULATIONS
CONCERNING ADMINISTRATIVE
PROCEDURAL PERMITTING AND
PLANNING MATTERS. ALL THREE
SETS OF AMENDMENTS TO THE
REGULATIONS ADOPTED BY THE
COMMISSION IN 2022 HAVE BEEN
APPROVED BY NOAA AS PART OF THE
COMMISSION’S COASTAL MANAGEMENT
PROGRAM. THANK YOU.
>>CHAIR, ZACHARY WASSERMAN: ANY
QUESTIONS FOR OUR ACTING
EXECUTIVE DIRECTOR? SEEING
NONE. WE MOVE TO ITEM SEVEN
WHICH WE’RE NOT TAKING UP
BECAUSE THERE ARE NO MATTERS TO
REPORT. THAT BRINGS US TO ITEM
EIGHT WHICH WE ARE ALSO NOT
TAKING UP THAT WILL BE POSTPONED
HOPEFULLY TO THE NEXT MEETING
AND THAT BRINGS US TO ITEM NINE
WHICH I CAN’T EVEN GET TO IN MY
PAGE.
THIS IS THE PUBLIC HEARING AND
POSSIBLE VOTE TO APPROVE
STIPULATED ORDERS,
CCD2023.002.00 AND
CCD2023.003.00 REGARDING THE SEA
PLANE INVESTMENTS LLC OF CORTE
MADERA AND THEIR DEVELOPMENT IN
MARIN COUNTY. AFTER BCDC HAS
GIVEN ITS OPENING REMARKS I’LL
ASK RESPONDENTS TO AFFIRM THE
STIPULATED AGREEMENT I’LL
COMMENT AFTER AND WE HOLD
DISCUSSION AND VOTE ON THE
COMMITTEE’S RECOMMENDATION. AT
THIS TIME WILL THE
REPRESENTATIVES FOR THE
RESPONDENT PLEASE IDENTIFY
THEMSELVES FOR THE RECORD.
PRESENT OR ON ZOOM.
>>SPEAKER: DO WE NEED TO
POSSIBLY ADMIT GILLIAN
BLANCHARD, COUNSEL FOR SEA PLANE
INVESTMENTS, LLC AND LOU
VASQUEZ?
>>LOU VASQUEZ: HI. THIS IS LOU
VASQUEZ. I’M PRESENT,
REPRESENTING SEA PLANE
INVESTMENTS.
>>CHAIR, ZACHARY WASSERMAN:
THANK YOU.
BEFORE STAFF GIVES ITS
PRESENTATION, I INVITE
COMMISSIONER GILMORE, THE CHAIR
OF THE ENFORCEMENT COMMITTEE TO
GIVE A BRIEF SUMMARY OF THE
COMMITTEE’S HEARING ON THIS
MATTER THAT TOOK PLACE ON
NOVEMBER 9TH OF THIS YEAR.
CHAIR GILMORE.
>>MARIE GILMORE: THANK YOU,
CHAIR WASSERMAN. BEFORE I
START, I WANT TO GIVE A REAL
VOTE OF THANKS TO BOTH THE
RESPONDENTS, STAFF, AND OUR
GENERAL COUNSEL GREG SCHARFF,
THE ENFORCEMENT COMMITTEE HEARD
THIS CASE SEVERAL TIMES AND IT
IS A COMPLICATED CASE AND IT’S
COMPLICATED BY THE NUMBER OF
VIOLATIONS, THE FACT THAT THE
PROPERTY CHANGED HANDS AND ALSO
THE LENGTH OF TIME INVOLVED IN
THIS AND SO KUDOS TO EVERYBODY
INVOLVED BRINGING THIS TOGETHER
AND GETTING AN ORDER THAT FIXES
THE VIOLATIONS AND ALLOWS
EVERYBODY TO MOVE FORWARD. SO
THANKS AGAIN TO THE RESPONDENTS,
TO STAFF, AND TO OUR GENERAL
COUNSEL.
CHAIR WASSERMAN?
>>CHAIR, ZACHARY WASSERMAN: WE
WILL NOW HAVE STAFF’S
PRESENTATION BY PRINCIPLE
ENFORCEMENT ANALYST ADRIENNE
KLEIN. GO FOR.
>>ANDREW FREMIER: THANK YOU
CHAIR GILMORE. IN JULY 2024
STAFF ISSUED A VIOLATION TO
REPORT COMPLAINT TO RESOLVE SIX
UNRESOLVED VIOLATIONS IN OCTOBER
OF THE SAME YEAR WE ISSUED A
SECOND COMPLAINT FOR
ADMINISTRATIVE CIVIL PENALTIES
TO RESOLVE THE PENALTY PORTION
OF THREE RESOLVED VIOLATIONS
DURING THE PUBLIC HEARING ON
MAY 30TH, 2023 THE ENFORCEMENT
COMMITTEE DIRECTED STAFF TO
ENTER INTO A SETTLEMENT
NEGOTIATIONS WHICH RESULTED IN
TWO PROPOSED STIPULATED ORDERS
TO RESOLVE ALL NINE VIOLATIONS
DURING THE PUBLIC HEARING ON
NOVEMBER 3RD OF THIS YEAR THE
ENFORCEMENT COMMITTEE HAS
JANUARY MENTIONED BY CHAIR
GILMORE COMMISSIONER GILMORE
ADOPTED BOTH PROPOSED STIPULATED
ORDERS WHICH ARE BEFORE YOU
TODAY. NEXT SLIDE PLEASE.
THE PRESENTATION WILL COVER THE
SITE LOCATION, NINE VIOLATIONS
AND THE TWO STAFF
RECOMMENDATIONS. NEXT SLIDE
PLEASE.
THE RED PIN ON THIS VICINITY MAP
SHOWS THE LOCATION WHERE THE
VIOLATIONS ARE OCCURRING AND ARE
OCCURRING KNOWN AS 240242
REDWOOD HIGHWAY FRONTAGE ROAD IN
AN UNINCORPORATED AREA OF MARIN
COUNTY. JUST TO BE CLEAR,
APOLOGIES CHAIR WASSERMAN, IT’S
NOT IN CORTE MADERA. IMAGE ON
THE LEFT SHOWS THE SITE LOOKING
TO THE NORTHEAST THE SITE
CONTAINS A NUMBER OF BUSINESSES
AND OPERATIONS WHILE SOME OF THE
GROUND LEVEL USES AND ASSOCIATED
FILL APPEAR TO HAVE BEEN ONGOING
SINCE 1965 CHANGES TO THE
ONGOING USES AND ASSOCIATED
THROUGH WITHIN BCDC JURISDICTION
INCLUDING MAINTENANCE THAT
OCCURRED AFTER ENACTMENT OF THE
MCATEER-PETRIS ACT REQUIRING
BCDC PERMIT OR PERMIT AMENDMENT.
PERMITS RUN WITH THE LAND AND
NEW OWNERS ARE RESPONSIBLE FOR
RESOLVING INHERITED VIOLATIONS
AND VIOLATIONS THEY UNDERTAKE.
AS NEW OWNERS RESPONDENTS HAVE
DID NOT CONTACT THE BCDC AS PART
OF THE DUE DILIGENCE REVIEW TO
INQUIRE ABOUT THE SITE STATUS IN
RELATION TO THE LAW AND THE
EXISTING PERMITS THAT GOVERN THE
SITE THE IMAGE ON THE RIGHT IS
AN OVERLAY OF THE PROXIMATE
LOCATIONS IN THE TWO PRIVATELY
OWNED PARCELS NUMBERED 164, ON
THE RIGHT 167 ON THE LEFT WITH
THE THREE STREET RIGHTS OF WAY
WHICH YOU CAN SEE THE LEFT SIDE
PARAPPA STREET, MOLENA STREET,
AND YELLOW STREETS THAT SURROUND
OR STRADDLE THEM AND THE DOCKING
FACILITY PICTURES IN THE WATER
IS LOCATED ON MARIN COUNTY
PROPERTY. NEXT SLIDE. I’LL
DESCRIBE THE SIX VIOLATIONS
UNRESOLVED VIOLATION FIRST BEING
THAT RESPONDENT VIOLATING
SPECIAL CONDITION TO SEE PUBLIC
ACCESS OF ITS 1973 PERMIT BY
FAILING TO PROVIDE THE PUBLIC
SHORE SIGNAGE PUBLIC ACCESS
CONNECTION FROM THE SITE TO
MARIN COUNTY PUBLIC ACCESS WEST
OF THE SITE VIOLATION TWO IS OF
SPECIAL CONDITION 2C TWO
MAINTENANCE OF THE PERMIT BY
FAILING TO MAINTAIN THE EXISTING
REQUIRED PUBLIC SHORT PATHWAY
AND LANDSCAPING. THE BULK HEAD
AT PARAPPA STREET IS SEVERELY
ERODED IN THE ADJACENT PUBLIC
SHORELINE PATHWAYS FREQUENTLY
INUNDATED BY TIDES AND THE
NORTHWESTERN TIP IS ERODED TO
THE POINT OF BEING GONE AND THE
WERE REMAINDER IS COLLAPSING
INTO THE BAY. VIOLATION THREE
IS MCATEER PETRIS ACT SECTION
66632A BY PLACING UNAUTHORIZED
FILL IN THE BAY AND SHORELINE
BAND IN YOLO STREET.
UNAUTHORIZED FILL INCLUDES
VEHICLE PARKING AND OR EQUIPMENT
STORAGE, SEA PLANE STORAGE
REPAIR AND SEA PLANE STORAGE
REPAIR MAINTENANCE FUELING TANK
ELEVATED ASPHALT PATHWAY ACROSS
YELLOW STREET TO ALLOW
PEDESTRIAN ACCESS DURING HIGH
TIDES. BY USING FILLED AREAS
DESIGNATED TO BE USED ONLY FOR
LANDSCAPING PUBLIC ACCESS AND
PEDESTRIAN BICYCLE PATHWAYS FOR
PRIVATE USE.
VIOLATION FOUR IS MCATEER-PETRIS
ACT INVOLVING PLACING
UNAUTHORIZED FILL IN BCDC’S
JURISDICTION CONSISTING OF THE
UNAUTHORIZED HELICOPTER LANDING
PAD AND FOUR PAVED WALKWAYS ON
BLOCK 164 VIOLATION FIVE
MCATEER-PETRIS ACT VIOLATION
PLACING UNAUTHORIZED FILL IN THE
BAY ON MARIN COUNTY PROPERTY BY
EXPANDING EXISTING U SHAPED
FLOATING SEPARATE EPISODES WITH
NEW FLOATING FILL TWO PILINGS
RELOCATING ON WATER FILLING
STATION.
AND THE SIXTH UNRESOLVED
VIOLATION IS ALSO A MCATEER
PETRIS ACT VIOLATION INVOLVES
EXCAVATION TO FILL AND CONSTRUCT
A NEW CONCRETE REBAR WATER
ACCESS RAMP IN THE YELLOW STREET
RIGHT OF WAY. THIS MOST
RECENTLY MARCH 20, 2022. THIS
COMPLETES THE SUMMARY OF THE SIX
UNRESOLVED VIOLATIONS. NEXT
SLIDE PLEASE WHERE I WILL
DESCRIBE THE THREE RESOLVED
VIOLATIONS.
TWO ARE THE SAME, WHICH ARE
RESPONDENTS FAILURE TO TAKE
ASSIGNMENT OF BOTH THE 1973 AND
THE SECOND 1985 PERMITS THAT
GOVERN THE SITE AND THE THIRD
RESPONDENT’S FAILURE TO COMPLETE
A PROJECT PRIOR TO PERMIT
EXPIRATION DATE AND CONTINUE
WORK WITH AN EXPIRED PERMIT
THOSE ISSUES HAVE BEEN RESOLVED
BUT THERE WERE ADMINISTRATIVE
CIVIL PENALTIES. NEXT SLIDE. I
WILL NOW READ THE ENFORCEMENT
COMMITTEE’S RECOMMENDED
ENFORCEMENT DECISION TO RESOLVE
THE SIX UNRESOLVED VIOLATIONS.
THE RESPONDENT HAS AGREED TO
STIPULATE TO THE FOLLOWING
TERMS. SO, TO CEASE AND DESIST
FROM VIOLATING THE
MCATEER-PETRIS ACT AND BOTH
PERMITS BY JUNE 30TH, 2024 TO
COMPLY WITH THE EXISTING PERMITS
BY MAINTAINING THE PERMIT
REQUIRED PUBLIC ACCESS ALONG THE
EXISTING SHORELINE PATHWAY
WITHIN RESPONDENTS CURRENT
PROPERTY OWNERSHIP ON YOLO
STREET FROM THE TERMINATION OF
THE SHORELINE PATHWAY LOCATED
WITHIN THE DEDICATED PUBLIC
ACCESS AREA TO STRIPE AND
MAINTAIN A CONNECTION FOR AN
EIGHT FOOT WIDE ACCESS PATH OF
TRAVEL. AND THAT IS OUTLINED IN
ONE OF THE ORDER EXHIBITS.
RESPONDENT AGREES TO INSTALL
EIGHT PUBLIC SHORE SIGNS AS
OUTLINED ON THE SLIDE AND IN
ORDER TO RELOCATE ACCESSIBLE
PARKING ALSO SHOWN IN THE ORDER
EXHIBIT ON YOLO STREET TO REMOVE
UNAUTHORIZED ELEVATED ASPHALT
PATH THAT WAS CONSTRUCTED TO
ALLOW FOR ACCESS AND HIGH TIDES
AND TO CONFIRM WITH STAFF WHICH
HELICOPTER LANDING PADS AND
WALKWAYS ARE AUTHORIZED OR NOT.
NEXT SLIDE PLEASE.
WITHIN 12 MONTHS OF THE DATE OF
THE ORDER RESPONDENT AGREES TO
FILE A PERMIT APPLICATION FOR
THE UNAUTHORIZED FILL IN USES AS
FOLLOWS THEY’LL SUBMIT A REVISED
LANDSCAPING PLAN FOR AREAS
ADJACENT TO THE PUBLIC PERMIT
REQUIRED PUBLIC ACCESS THAT WILL
BE REVIEWED BY STAFF AND IT WILL
INCLUDE INSTALLATION AND
MAINTENANCE OF SOME PICNIC
TABLES THAT WILL BE ADA
ACCESSIBLE. AND IF THERE IS ANY
NEW ACCESS REQUIRED UNDER A
FOLLOWING SECTION, THAT WILL BE
INCLUDED ON THESE PLANS.
RESPONDENT AGREES TO REQUEST
AFTER THE FACT AUTHORIZATION FOR
ANY HELICOPTER LANDING PADS,
FUEL TANKS, AND WALKWAYS THAT
ARE NOT PERMITTED BY THE ’85
PERMIT. THE THREE FINGERS THAT
ARE PART OF THE DOCKINGS IS THAT
ARE NOT CURRENTLY AUTHORIZED,
AND THE LAUNCHING RAMP
CONSTRUCTED IN MARCH 2022. NEXT
SLIDE PLEASE.
RESPONDENT AGREES TO PROVIDE
SOME ADDITIONAL PUBLIC ACCESS,
EITHER THAT CURRENTLY REQUIRED
BY THE PERMIT, WHICH IS A
CONNECTION BETWEEN THE SITE AND
THE ADJACENT COUNTY PUBLIC
WALKWAY, AND BICYCLE PATH, OR
ALTERNATIVE ON-SITE ACCESS IF
LOCAL APPROVAL CANNOT BE
OBTAINED. AND FINALLY TO
PREPARE A SEA LEVEL RISE RISK
ASSESSMENT TO ADDRESS SEA LEVEL
RISE IN THE PERMIT RELATED
PUBLIC ACCESS — THE PERMIT
REQUIRED PUBLIC ACCESS AREAS.
AND TO IMPLEMENT THAT SEA LEVEL
— TO IMPLEMENT THE SEA LEVEL
RISE PLAN IN THE TIMELINE
OUTLINED IN IT.
AND IT WILL INCLUDE THE
MAINTENANCE OF THE PUBLIC ACCESS
ON PARAPPA STREET THAT’S FLOODED
AND ERODED, FREQUENTLY FLOODED
AND QUITE ERODED AND ALSO
ADAPTIVE MEASURES TO MAINTAIN
PUBLIC ACCESS FOR THE LIFE OF
THE PROJECT OR UNTIL 2050. NEXT
SLIDE.
SO, THAT COMPLETES THE
REQUIREMENTS FOR THE UNRESOLVED
VIOLATIONS.
THERE WILL BE, FOR THE THREE
RESOLVED VIOLATIONS, A
RESPONDENT AGREES TO A $5,000
ADMINISTRATIVE CIVIL PENALTY DUE
WITHIN 12 AND 24 MONTHS OF THE
ORDER IN TWO EQUAL INSTALLMENTS.
NEXT SLIDE, PLEASE.
AND THE PENALTY BE ASSOCIATED
WITH THE SIX UNRESOLVED
VIOLATIONS IS 43,800 DUE IN
THREE DIFFERENT INCREMENTS,
FIRST 10,000 WITHIN 60 DAYS OF
ORDER ISSUANCE THEN TWO PAYMENTS
OF 16,900 DUE WITHIN 12 AND 24
MONTHS OF ORDER ISSUANCE.
I THINK THAT’S MY LAST SLIDE.
MAYBE NEXT SLIDE.
SO, TOGETHER, THE TWO
RECOMMENDATIONS WOULD RESULT IN
A TOTAL PENALTY OF $48,800, AND
THAT CONCLUDES THE STAFF
PRESENTATION.
>>CHAIR, ZACHARY WASSERMAN:
THANK YOU VERY MUCH.
I WOULD ASK RESPONDENTS
REPRESENTATIVE WHETHER THEY
CONCUR WITH STAFF
RECOMMENDATIONS IN THE
STIPULATED ORDER?
>>SPEAKER: YES. GOOD AFTERNOON
COMMISSIONERS. APOLOGIES FOR
JOINING LATE. I’M GILLIAN
BLANCHARD WITH LAW GROUP AND I
REPRESENT SEA PLANE INVESTMENTS,
LLC.
GOOD TO SEE YOU ALL.
I, ON BEHALF OF RESPONDENTS, CAN
CONCUR THAT WE DO SUPPORT THE
STAFF’S RECOMMENDATION AND
STIPULATED ORDER. THANK YOU.
>>CHAIR, ZACHARY WASSERMAN:
THANK YOU VERY MUCH.
ARE THERE ANY QUESTIONS FROM
COMMISSIONERS BEFORE WE OPEN FOR
PUBLIC COMMENT? I THOUGHT WE
HAD A QUIET GROUP? VICE CHAIR
EISEN
>>V. CHAIR, REBECCA EISEN: I
WANT TO POINT OUT THAT THIS
MATTER IS, SORT OF, A REALLY
GOOD EXAMPLE OF THE WORKINGS OF
THE ENFORCEMENT COMMITTEE.
STAFF AND RESPONDENTS ARE
WORKING HARD TO RESOLVE THIS
MATTER BUT SOMETIMES THEY CAN’T
QUITE PULL IT ACROSS THE FINISH
LINE, AND THE ENFORCEMENT
COMMITTEE SERVES AS WHAT I WOULD
CALL THE COURTHOUSE STEPS. AND
AS CHAIR WASSERMAN AND ADRIENNE
KLEIN MENTIONED THIS WAS A
COMPLICATED MATTER AND WHEN IT
CAME TO US, WE THE EFFORT THAT
HAD BEEN MADE ALREADY, AND WE
SAW THAT WITH A LITTLE MORE
EFFORT AND PUSH FROM OUR
COMMITTEE THEY COULD RESOLVE
THIS MATTER AND THEY DID. SO,
IT’S REALLY A TESTAMENT TO HOW
WELL THAT COMMITTEE WORKS AS AN
ARM OF THIS COMMISSION. SO I
JUST WANTED TO MAKE THAT POINT.
>>CHAIR, ZACHARY WASSERMAN:
THANK YOU. AND I WOULD ADD MY
THANKS TO STAFF, AND TO CHAIR
GILMORE.
ANY OTHER COMMISSIONERS? DO WE
HAVE ANY PUBLIC COMMENT?
>>CLERK, REYLINA RUIZ: NO
PUBLIC COMMENT.
>>CHAIR, ZACHARY WASSERMAN: I
ASSUME THERE ARE NO FINAL
COMMENTS FROM COMMISSIONERS.
AND I NOW INVITE CHAIR GILMORE
OF THE ENFORCEMENT COMMITTEE TO
PRESENT THE COMMITTEE’S
ENFORCEMENT RECOMMENDATIONS.
>>MARIE GILMORE: THANK YOU
CHAIR WASSERMAN. BEFORE I PUT
FORTH THE ENFORCEMENT
COMMITTEE’S RECOMMENDATIONS I’M
GOING TO BRIEFLY REVIEW THE
COMMISSION’S OPTIONS TO PROCEED.
PURSUANT TO BCDC REGULATIONS
SECTION 11332 ENTITLED
COMMISSION ACTION ON RECOMMENDED
ENFORCEMENT DECISION. WHEN THE
COMMISSION ACTS ON A RECOMMENDED
ENFORCEMENT DECISION THE
COMMISSION’S ACTION SHALL BE ONE
OF THE FOLLOWING. ONE, THE
COMMISSION MAY ADOPTED
RECOMMENDED ENFORCEMENT DECISION
WITHOUT ANY CHANGES TO THE
PROPOSED STIPULATED ORDERS AND
THIS IS YOUR ENFORCEMENT
COMMITTEE’S RECOMMENDATION.
TWO, THE COMMISSION MAY DISMISS
THE ENTIRETY OR EITHER PART OF
THE MATTER BY VOTING NOT TO
ISSUE ONE OR BOTH OF THE
STIPULATED — OF THE PROPOSED
ORDERS.
THREE, THE COMMISSION MAY REMAND
THE ENTIRE MATTER BACK TO THE
ENFORCEMENT COMMITTEE OR STAFF
FOR FURTHER ACTION AS THE
COMMISSION DIRECTS, OR, FOUR,
THE COMMISSION MAY REJECTED
RECOMMENDED ENFORCEMENT DECISION
AND DECIDE TO CONSIDER THE
ENTIRE MATTER DE NOVO. IN THIS
EVENT THE COMMISSION SHALL
CONTINUE THE PUBLIC HEARING TO
THE NEXT AVAILABLE COMMISSION
MEETING WHERE IT SHALL PROCEED
IN ACCORDANCE WITH THE SAME
PROCEDURAL REQUIREMENTS AS THE
COMMISSION MUST FOLLOW UNDER
REGULATION SECTION 11327.
I WILL NOW PRESENT THE
ENFORCEMENT COMMITTEE’S
RECOMMENDATION.
THE ENFORCEMENT COMMITTEE
RECOMMENDS THAT THE COMMISSION
VOTE IN FAVOR OF THE ADOPTION OF
THE PROPOSED ENFORCEMENT
DECISION AND CEASE AND DESIST
CIVIL PENALTY ORDERS CCD
2023.002 AND CCD2023.003 TO
RESOLVE BCDC ENFORCEMENT CASE
NUMBER ER2019.063.00.
I’M GOING TO MOVE THAT THIS
COMMISSION ADOPTED RECOMMENDED
ENFORCEMENT DECISION WITHOUT ANY
CHANGES.
>>CHAIR, ZACHARY WASSERMAN: DO
I HAVE A SECOND FOR THE MOTION?
>>SPEAKER: I’LL SECOND THAT.
>>CHAIR, ZACHARY WASSERMAN:
COMMISSIONER MOULTON-PETERS FROM
THE GREAT COUNTY OF MARIN
SECONDS THE MOTION.
[LAUGHTER]
PLEASE CALL THE ROLL REYLINA.
>>CLERK, REYLINA RUIZ:
COMMISSIONER ADDIEGO?
>>ANDREW FREMIER: YES.
>>CLERK, REYLINA RUIZ:
COMMISSIONER AHN?
>>EDDIE AHN: YES.
>>CLERK, REYLINA RUIZ: AMBUEHL?
>>DAVID AMBUEHL: YES.
>>CLERK, REYLINA RUIZ:
COMMISSIONER BURT?
>>PAT BURT: YES.
>>CLERK, REYLINA RUIZ:
COMMISSIONER ECKERLY?
>>JENN ECKERLE: YES.
>>CLERK, REYLINA RUIZ:
COMMISSIONER ECKLUND? PAT.
>>SPEAKER: YES.
>>CLERK, REYLINA RUIZ:
COMMISSIONER GILMORE?
COMMISSIONER GUNTHER?
>>SPEAKER: YES.
>>CLERK, REYLINA RUIZ: HASZ?
>>V. CHAIR, KARL HASZ: YES.
>>CLERK, REYLINA RUIZ:
KISHIMOTO?
>>YORIKO KISHIMOTO: YES.
>>CLERK, REYLINA RUIZ:
MOULTON-PETERS?
>>STEPHANIE MOULTON-PETERS:
YES.
>>CLERK, REYLINA RUIZ:
PEMBERTON?
>>SHERI PEMBERTON: YES.
>>CLERK, REYLINA RUIZ: PESKIN?
>>AARON PESKIN: YES.
>>CLERK, REYLINA RUIZ: PINE?
RAMOS? COMMISSIONER WILLIAMS?
>>ANDREW FREMIER: ABSTAIN.
>>CLERK, REYLINA RUIZ:
COMMISSIONER ZEPEDA?
>>CESAR ZEPEDA: YES.
>>CLERK, REYLINA RUIZ: EISEN?
>>V. CHAIR, REBECCA EISEN: YES.
>>CLERK, REYLINA RUIZ:
WASSERMAN?
>>CHAIR, ZACHARY WASSERMAN:
YES.
>>CLERK, REYLINA RUIZ: 20
YESES. NO NOS, AND ONE
ABSTENTION.
>>CHAIR, ZACHARY WASSERMAN: THE
MOTION PASSES. THANK YOU FOR
ALL OF YOUR WORK.
CONTINUE AND LET THIS NOT COME
BACK TO US. THAT BRINGS US TO
ITEM TEN, PUBLIC HEARING ON THE
U.S. ARMY CORP OF ENGINEERS
PROPOSED PHASE CONSISTENCY
DETERMINATION OF THE OAKLAND
TURNING BASIN’S WIDENING
PROJECT.
THE PRESENTATION WILL BE MADE BY
OUR SEDIMENT PROGRAM MANAGER
BRENDA GADEN, OR AT LEAST SHE’LL
INTRODUCE AND KICK IT OFF.
>>ANDREW FREMIER: THANK YOU
CHAIR WASSERMAN AND
COMMISSIONERS. WE APPRECIATE
YOU ALL BEING HERE TODAY FOR THE
ARMY CORP’S OAKLAND TURNING
BASIN-WIDENING PROJECT. WE HAVE
A BIT OF A PRESENTATION FOR YOU
TODAY. PLEASE HANG ON. WE
RECOGNIZE THAT THIS PROJECT IS
BOTH COMPLEX IN ITS CONSTRUCTION
AND TIMING, BUT ALSO WE NOTE
THAT THE COMMISSION DOESN’T
OFTEN HEAR PHASED CONSISTENCY
DETERMINATION. SO WITH THAT, WE
WOULD TAKE THE OPPORTUNITY TO
JUST USE OUR LEGAL EAGLE,
MICHAEL NG TO WALK YOU THROUGH
THE FEDERAL LAW AND POLICIES
AROUND THIS TYPE OF PROJECT
PRIOR TO GETTING THE — PRIOR TO
GETTING THE OVERVIEW OF THE
PROJECT FROM THE COMMISSION
STAFF, WHICH WILL BE MYSELF.
THEN FOLLOWING ME, PHOENIX
ARMENTA WILL BE PRESENTING ON
THE EJ POLICIES BECAUSE THERE
ARE SOME COMPLEX EJ ISSUES HERE.
FOLLOWING PHOENIX I’LL STEP BACK
IN FOR A MINUTE THEN WE’LL BE
TURNING THE PROJECT OVER TO THE
ARMY CORP OF ENGINEERS TO GIVE
YOU A DETAILED DESCRIPTION.
WITH THAT, I APPRECIATE YOUR
ATTENTION TODAY. MICHAEL WILL
GO AHEAD AND TAKE THE MIC.
>>MICHAEL NG: HELLO
COMMISSIONERS MICHAEL, SENIOR
STAFF ATTORNEY AT BCDC.
AS BRENDA MENTIONED I’M GOING TO
BE COVERING TWO TOPICS TODAY
COASTAL ZONE MANAGEMENT ACT CMA
AND FEDERAL CONSISTENCY, THEN
THE SECOND TOPIC IS THE
COMMISSION’S AUTHORITY AND
JURISDICTION. I’M GOING TO KEEP
THIS BRISK. THE COMMISSION’S
CURRENT CONSIDERATION IS A BIT
OUT OF ITS USUAL CONSIDERATION
OF PROJECTS. THROUGH THE MY
PRESENTATION YOU MAY SEE
ASTERISKS ON CERTAIN SLIDES AND
WONDER WHAT THAT’S ALL ABOUT.
THOSE HAVE NO PARTICULAR
SIGNIFICANCE OTHER THAN TO SERVE
AS CUES FOR MYSELF TO PROVIDE
FOR SPEAKER NOTES WHICH I
WOULDN’T FIT ON TO MY SLIDES.
NEXT SLIDE.
THANK YOU. SO, FIRST I’LL TALK
ABOUT THE PURPOSE OF THE CZMA.
IT IS A FEDERAL LAW, AGAIN, THE
COASTAL ZONE MANAGEMENT ACT.
ITS BASIC PURPOSE IS TO
PRESERVE, PROTECT, DEVELOP, AND
WHERE POSSIBLE TO RESTORE OR
ENHANCE THE NATION’S RESOURCES
OF THE COASTAL ZONE AND THE CZMA
ENCOURAGES THIS AND ACCOMPLISHES
THIS BY ENCOURAGING STATES TO
DEVELOP WHAT’S CALLED COASTAL
ZONE MANAGEMENT PROGRAMS OR
CZMP’S AND THIS GOAL IS FURTHER
INCENTIVIZED BY FEDERAL
GOVERNMENT PROVIDING MATCHING
GRANTS TO ADMINISTER CZMP’S FOR
COASTAL STATES THAT HAVE
CERTIFIED CZMP’S AND ADMINISTER
PER CMA STATUTE CZMP SHOULD
INCLUDE OBJECTIVE POLICIES AND
STANDARDS TO GUIDE PUBLIC AND
PRIVATE USES OF LANDS AND WATERS
IN THE COASTAL ZONE AND ONCE
APPROVED BY NOAA CMP STANDARD
FOR FEDERAL AGENCY ACTIVITY THAT
COASTAL ZONE. NEXT SLIDE.
BCDC AUTHORITY RESPONSIBILITY
UNDERTAKING A STEP BACK THERE’S
ACTUALLY TWO COASTAL ZONE
SEGMENTS IN CALIFORNIA FOR CZMA
PURPOSES BCDC ADMINISTERS THE
SAN FRANCISCO BAY AREA AND
COASTAL ZONE SEGMENT AND THE
COASTAL COMMISSION ADMINISTERS
THE REST OF THE COASTAL ZONE BUT
IT’S WORTH POINTING OUT THAT
BOTH THE MCATEER-PETRIS ACT
FOUNDING LAW AND THE BAY PLAN
PREDATE THE CZMA AND THE MAC ACT
WAS ADOPTED AND ENACTED BY
LEGISLATURE IN 1965 AND THE BAY
PLAN APPROVED IN 1968, CZMA
ENACTED BY CONGRESS IN 1972. IN
1977 WHEN NOAA APPROVED THE BCDC
CZMP IT VIRTUALLY AND WHOLLY
INCORPORATED THE MAC ACT AND THE
BAY PLAN INTO OUR CCP. BACK.
>>CLERK, REYLINA RUIZ: SORRY
MICHAEL.
>>SPEAKER: UPDATES TO OUR CZMP
MUST BE ACCOMPLISHED THROUGH OUR
CZMA PROGRAM CHANGES AND MOST
COMMONLY OCCURS WHEN THE
COMMISSION ADOPTS A BAY PLAN
ELEMENT SO IT’S WORTH POINTING
OUT THAT BCDC CZMP HAS UPON BEEN
UPDATED 121 TIMES SINCE 1982 AND
REFLECT AMENDMENTS AND UPDATES
TO BCDC’S LAWS AND POLICIES.
NOW WE GET INTO THE NITTY-GRITTY
BEFORE US TODAY A SUBMITTED
CONSISTENCY DETERMINATION SO THE
CONSISTENCY DETERMINATION
PROCESS OR CD INVOLVES BOTH
FEDERAL AND STATE AGENCIES.
I’LL TALK ABOUT THE FEDERAL
AGENCY ROLE SUBMITTING TO BCDC
PRIOR TO UNDERTAKING ANY
ACTIVITY THAT AFFECTS ANY LAND
OR WATER USE OR NATURAL RESOURCE
OF THE COASTAL ZONE ACTIVITY
MUST BE CARRIED OUT IN A MANNER
WHICH IS CONSISTENT TO THE
MAXIMUM EXTENT PRACTICABLE WITH
THE ENFORCEABLE POLICIES OF THE
APPROVED STATE MANAGEMENT PLAN
PROGRAM. TWO NOTES FIRST I’LL
ADDRESS THE LEGAL CHARACTER OF
PHASE LATER IN THIS PRESENTATION
SECOND NOAA’S REGULATIONS DEFINE
MAXIMUM EXTENT PRACTICABLE TO
MEAN FULLY CONSISTENT WITH THE
ENFORCEABLE POLICIES OF
MANAGEMENT PROGRAMS UNLESS FULL
CONSISTENCY IS PROHIBITED BY
EXISTING LAW APPLICABLE TO THE
FEDERAL AGENCY AND NOAA
REGULATIONS FURTHER DEFINE
ENFORCEABLE POLICY AS STATE
POLICIES WHICH ARE LEGALLY
BINDING THROUGH CONSTITUTIONAL
PROVISIONS LAWS REGULATIONS LAND
USE PLANS ORDINANCES OR JUDICIAL
ADMINISTRATIVE DECISIONS BY
WHICH A STATE EXPERTS CONTROL
OVER A PRIVATE AND PUBLIC LAND
AND WATER USES AND NATURAL
RESOURCES IN THE COASTAL ZONE SO
THE FEDERAL AGENCY SHALL NOT
PROCEED WITH ACTIVITY OVER BCDC
OBJECTION UNLESS FEDERAL AGENCY
HAS CONCLUDED ONE OF THE
FOLLOWING EITHER THAT ACTIVITY
IS CONSISTENT WITH BCDC
ENFORCEABLE POLICIES IS
ENFORCEABLE ARE POLICIES IS
PROHIBITED BY LAW OR THAT
PROPOSED ACTION IS CONSISTENT
WITH BCDC ENFORCEABLE POLICIES.
THE NEXT PART OF THE CD PROCESS
IS THE STATE AGENCY ROLE. BCDC
RESPONDS TO A CD SUBMITTED TO
THE FEDERAL AGENCY BY ONE OF THE
FOLLOWING EITHER CONCURRING
CONDITIONALLY CONCURRING OR
OBJECTING TO THE CD CONDITIONAL
CONCURRENCE MEANS THAT THE
FEDERAL AGENCY MUST MEET
SPECIFIED CONDITIONS TO BE
DEEMED CONSISTENT WITH THE
POLICIES AND BCDC MUST IDENTIFY
SPECIFIC ENFORCEABLE POLICIES OF
ITS CMP EXPLAINING WHY
CONDITIONS ARE NECESSARY TO
ENSURE CONSISTENCY WITH THOSE
SPECIFIC ENFORCEABLE POLICIES
AGAIN BCDC CZMP INCLUDES
ENFORCEABLE POLICIES OF BOTH
MCATEER-PETRIS ACT AND THE BAY
PLAN IF THE FEDERAL AGENCY
REJECTS CONDITIONS IN THE
STATE’S CONDITIONAL CONCURRENCE
IS EFFECTIVELY DEEMED AN
OBJECTION. NEXT SLIDE. NOW WE
KNOW THE FEDERAL AGENCY AND
STATE AGENCY ROLES IN THE
PROCESS, WHAT HAPPENS WHEN
THERE’S A CONFLICT IN THE TWO
SIDES. FIRST NOTING OBJECTION
TO A CD IS NOT A DENIAL IN THE
WAY WE MAY BE ABLE TO DENY AN
APPLICATION UNDER OUR STATE LAW
AUTHORITY UNDER FEDERAL AGENCY
DECIDES TO PROCEED WITH ACTIVITY
THAT IS OBJECTED TO BY BCDC THE
FEDERAL AGENCY MUST NOTIFY BCDC
OF ITS DECISION TO PROCEED
BEFORE COMMENCEMENT. SO IF
THERE IS A SERIOUS DISAGREEMENT
BETWEEN THE FEDERAL AGENCY AND
BCDC, EITHER PARTY MAY REQUEST
MEDIATION BY NOAA’S OFFICE OF
COASTAL MANAGEMENT, OCM OR THE
SECRETARY OF COMMERCE. IF
MEDIATION IS NOT SUCCESSFUL OR
UTILIZED, EITHER PARTY MAY SEEK
REVIEW. NEXT SLIDE.
SO, THAT WAS A LOT OF
INFORMATION. BUT TO SUMMARIZE,
BCDC’S CZMP INCLUDES ENFORCEABLE
POLICIES OF MCATEER-PETRIS ACT
AND THE BAY PLAN AND FEDERAL
AGENCIES MUST UNDERTAKE
ACTIVITIES CONSISTENT WITH THE
MAXIMUM EXTENT PRACTICABLE WITH
ENFORCEABLE POLICIES OF OUR
CZMP. FEDERAL AGENCY SUBMITS A
CONSISTENCY DETERMINATION FOR
ITS PROPOSED ACTIVITIES TO WHICH
BCDC CAN CONCUR CONDITIONALLY
CONCUR OR OBJECT, AND FOR
SERIOUS DISAGREEMENTS BETWEEN A
FEDERAL AGENCY AND BCDC, BCDC
MAY REQUEST MEDIATION FROM
NOAA’S OFFICE OF COASTAL
MANAGEMENT OR THE SECRETARY OF
COMMERCE AND/OR SEEK JUDICIAL
REVIEW IN A COURT OF LAW. NEXT
SLIDE. NOW TO THE SECOND PART
TALKING ABOUT THE COMMISSION’S
AUTHORITY AND JURISDICTION.
NEXT SLIDE.
BEFORE I ADDRESS THE SPECIFIC
TOPIC OF THE COMMISSIONS
JURISDICTION AND AUTHORITY OVER
THIS PROJECT IT WILL BE HELPFUL
TO TAKE A STEP BACK AND
UNDERSTAND HOW VARIOUS LEGAL
REGIMES SHOULD INFORM AND GUIDE
THE COMMISSION’S DECISION-MAKING
PROS. I HAVE SET FORTH TWO
BROAD CATEGORIES FOR DISCUSSING
RELEVANT LEGAL REGIMES FIRST
CATEGORY SHOULD GUIDE THE
PROCESS AND PROVIDE SUBSTANTIVE
POLICY STANDARDS BY WHICH THE
COMMISSION SHOULD MAKE A
DECISION ON THE PROJECT AT THE
NEXT MEETING ON DECEMBER 21ST.
THE SECOND CATEGORY
ENVIRONMENTAL DOCUMENTATION
IDENTIFIES TWO LAWS, ONE FEDERAL
AND ONE STATE WHICH REQUIRES
PREPARATION OF ENVIRONMENTAL
DOCUMENTATION WHICH SHOULD ALSO
INFORM THE COMMISSIONS POLICY
DETERMINATIONS WITHIN ITS
DECISIONAL FRAMEWORK. YOU MAY
HEAR COMMENTERS MAKE REFERENCE
TO THE ENVIRONMENTAL
DOCUMENTATION REQUIRED FOR THE
PROPOSED PROJECT UNDER THESE
LAWS. HOWEVER IT’S WORTH
POINTING OUT THAT THE
ENVIRONMENTAL DOCUMENTATION LAWS
THEMSELVES DO NOT DIRECTLY
CONTROL THE COMMISSIONS
DECISION-MAKING FRAMEWORK HERE.
NEXT SLIDE.
FIRST WE’LL TALK ABOUT THE CZMA
WHICH WE JUST TALKED ABOUT. AS
PREVIOUSLY EXPLAINED UNDER CZMA,
A FEDERAL AGENCY UNDERTAKING ITS
OWN ACTIVITY WITHIN OR OUTSIDE
OF THE SAN FRANCISCO BAY COASTAL
ZONE WHICH MAY AFFECT COASTAL
RESOURCES WITHIN OUR SEGMENT OF
THE COASTAL ZONE MUST SUBMIT A
CONSISTENCY DETERMINATION TO
BCDC JUSTIFYING THAT THE FEDERAL
AGENCY’S PROPOSED ACTIONS ARE
CONSISTENT TO THE MAXIMUM
COMMENT PRACTICABLE WITH THE
ENFORCEABLE POLICIES OF BCDC
CZMP. ARMY CORP ENGINEERS
SUBMITTED A FIRST PHASE CD THAT
IS PROPOSED ACTIONS CONSISTENT
TO THE MAXIMUM EXTENT
PRACTICABLE WITH THE ENFORCE
POLICIES OF OUR CZMP AND AGAIN
BCDC CZMP INCLUDES ENFORCEABLE
POLICIES OF THE MAC ACT AND THE
BAY PLAN AND BCDC CAN CONCUR
CONDITIONALLY OR OBJECT. THESE
ARE BASED ON DEVELOPING
INFORMATION NOT AVAILABLE AT THE
TIME OF THE CD WITH EACH PHASE
SUBJECT TO FEDERAL AGENCY
DISCRETION TO IMPLEMENT
ALTERNATIVE DECISIONS BASED UPON
THE INFORMATION AVAILABLE AT
THAT TIME. FOR EXAMPLE,
PLANNING CITING DESIGNING DESIGN
PHASES AND CD IS REQUIRED FOR
EACH MAJOR DECISION. NEXT
SLIDE.
NEXT WE’LL TALK ABOUT THE
MCATEER-PETRIS ACT AS PART OF
THE DECISIONAL FRAMEWORK. THE
PROJECT WOULD OCCUR OUTSIDE OF
THE BAY AND SHORELINE BAN
JURISDICTIONS BUT THE PROJECT
MAY AFFECT RESOURCES WITHIN BOTH
OF THESE JURISDICTIONS WITHIN
BCDC COASTAL ZONE SEGMENT
IDENTIFIED IN THE APPLICATION
SUMMARY OF LISTED I’M NOT GOING
TO GO OVER ALL OF THESE BUT YOU
CAN SEE STAFF IDENTIFIED AS THE
RELEVANT POLICIES FOR THE
COMMISSION TO CONSIDER IN
RELATION TO THIS PROJECT. NEXT
SLIDE.
SO, NEXT WE’LL TALK ABOUT THE
BAY PLAN AS PART OF THE
DECISIONAL FRAMEWORK. AND ON
THIS SLIDE, AGAIN, I’M NOT GOING
TO READ ALL OF THESE CATEGORIES,
BUT THESE ARE ENFORCEABLE
POLICIES AND THE CZMP THAT WERE
IDENTIFIED IN THE BAY PLAN. THE
FOLLOWING BAY PLAN POLICY
CATEGORIES ARE RELEVANT IN
ENFORCING POLICIES FOR THE
COMMISSION TO CONSIDER
DETERMINING WHETHER IT CONCURS
CONDITIONALLY OR OBJECTS TO THE
ARMY CORP SUBMITTED CD. THE
COMMISSION’S RECENT UPDATE TO
THE SEAPORT PLAN VIS-À-VIS
ADOPTED PLAN IS NOT YET PART OF
THE BCDC APPROVED CERTIFIED
CZMP. FOR PURPOSES OF THE
COMMISSION’S CONSIDERATION OF
THE CD THE COMMISSION SHOULD
RELY ON POLICIES OF THE SEAPORT
PLAN PRIOR TO ADOPTION OF BPA
119 TO THE EXTENT THEY INFORM
THE COMMISSION DETERMINATION
WHETHER IT CONDITIONALLY CONCURS
OR OBJECTS TO THE ARMY CORP’S
SUBMITTED CD. NEXT SLIDE.
NEXT I’LL TALK ABOUT
ENVIRONMENTAL DOCUMENTATION AS
PART OF THE RELEVANT LEGAL
REGIME HERE. SO, NEPA STANDS
FOR THE NATIONAL ENVIRONMENTAL
POLICY ACT, WHICH WAS ENACTED BY
CONGRESS IN 1969. IT REQUIRES
THAT ALL FEDERAL AGENCIES ARE TO
PREPARE DETAILED STATEMENTS
ASSESSING THE ENVIRONMENTAL
IMPACT AND ALTERNATIVES TO MAJOR
FEDERAL ACTIONS SIGNIFICANTLY
AFFECTING THE ENVIRONMENT. SO,
HERE, FOR THIS PROJECT, THE ARMY
CORP PREPARED AN INTEGRATED
FEASIBILITY REPORT AND
ENVIRONMENTAL ASSESSMENT AS THE
NEPA LEAD AGENCY. AND AS PART
OF ITS EA, IT MADE A DRAFT
FINDING OF NO SIGNIFICANT IMPACT
OR [INDISCERNIBLE] UNDER CZMA
STATE AGENCIES CANNOT REQUIRE
SUBMITTAL OF NEPA DOCUMENTATION
AS PART OF A CD BUT HERE THE
ARMY CORP DID PROVIDE AN EA FOR
STAFF CONSIDERATION IN
EVALUATING THE SUBMITTED CD IT’S
WORTH POINTING OUT FEDERAL
AGENCIES CD OBLIGATIONS UNDER
CZMP ARE INDEPENDENT OF THOSE
REQUIRED UNDER NEPA AND ARE NOT
NECESSARILY FULFILLED BY THE
SUBMISSION OF NEPA. THE EA IS
NOT NECESSARILY DETERMINATIVE OF
THE COMMISSION’S REVIEW OF THE
ARMY CORP’S SUBMITTED CD THOUGH
ANALYSIS IN MAY ASSIST THE
COMMISSION IN DETERMINING
WHETHER IT CONCURS CONDITIONALLY
CONCURS OR OBJECTS TO THE
SUBMITTED CD. SIMILAR TO NEPA
CEQA REQUIRES STATE AND LOCAL
GOVERNMENT AGENCIES TO INFORM
DECISION MAKERS AND THE PUBLIC
ABOUT THE POTENTIAL
ENVIRONMENTAL IMPACTS OF
PROPOSED PROJECTS AND REDUCE
ENVIRONMENTAL IMPACTS TO THE
EXTENT FEASIBLE THE. THE EIR IS
NOT DIRECTLY BEFORE US TODAY
BECAUSE CEQA IS NOT A
REQUIREMENT UNDER CZMA. UNDER
THE DOCUMENT THEY HAVE
IDENTIFIED FOUR SIGNIFICANT AND
UNAVOIDABLE IMPACTS THREE
RELATING TO AIR QUALITY AND ONE
RELATING TO NOISE AND THEY ALSO
IDENTIFIED CERTAIN MITIGATION
MEASURES TO MITIGATE THE
SIGNIFICANCE OF THOSE IMPACTS
ALTHOUGH THEY STILL CONCLUDED
THEY WERE SIGNIFICANT AND
UNAVOIDABLE. SO BCDC STAFF IS
CURRENTLY REVIEWING AND
COMMENTING ON THE DRAFT EIR AS A
RESPONSIBLE AGENCY AND WILL
CONSIDER IT WHEN THE PORT
APPLIES FOR A BCDC PERMIT. THIS
IS TYPICALLY HOW BCDC HANDLES
ITS CEQA COMPLIANCE BECAUSE
PERMIT APPLICANTS MUST OBTAIN
ALL DISCRETIONARY APPROVALS
BEFORE SEEKING A BCDC PERMIT AND
TYPICALLY THE LOCAL GOVERNMENT
PROVIDING ANY LOCAL
DISCRETIONARY APPROVAL SERVES AS
A CEQA LEAD AGENCY. BCDC RELIES
ON THE CEQA DOCUMENTATION
PREPARED BY THE LEAD AGENCY WHEN
ACTING ON A PERMIT APPLICATION
FOR A PROJECT AS A CEQA AGENCY
RESPONSIBLE AGENCY IF A PROJECT
REQUIRES APPROVAL FROM A
CALIFORNIA PUBLIC AGENCY OR
FEDERAL AGENCY THE CEQA
GUIDELINES GENERALLY REQUIRE
PREPARATION OF A JOINT CEQA
DOCUMENT GUIDELINES ACKNOWLEDGE
THAT A FEDERAL AGENCY MAY NOT
COOPERATE IN THE PREPARATION OF
A JOINT DOCUMENT AND MAY REQUIRE
A SEPARATE NEPA DOCUMENTATION.
HERE THE ARMY CORP AND PORT OF
OAKLAND DID NOT PREPARE A JOINT
NEPA CEQA DOCUMENT INSTEAD THE
ARMY CORP PREPARED AN EA PORT
PREPARED AN EIR UNDER ITS CEQA
REQUIREMENTS. THERE IS NO
REQUIREMENT THAT THE
ENVIRONMENTAL REVIEW OF A
PROJECT UNDER NEPA COME TO THE
CONCLUSIONS AS THE ENVIRONMENTAL
REVIEW OF THE SAME PROJECT UNDER
CEQA BECAUSE CEQA AND NEPA ARE
DIFFERENT STATUS WITH DIFFERENT
REQUIREMENTS. AGAIN THAT WAS A
LOT OF INFORMATION. JUST TO
SUMMARIZE HERE THE ARMY CORP
SUBMITTED A PHASED CONSISTENCY
DETERMINATION AS REQUIRED AND
ALLOWED BY THE CMA. BCDC MUST
CONCUR INITIALLY CONCUR OR
OBJECT TO THE SUBMITTED CD THAT
THE ARMY CORP’S PROPOSED ACTIONS
ARE CONSISTENT TO THE MAXIMUM
EXTENT PRACTICABLE WITHIN THE
ENFORCEABLE POLICIES OF BCDC,
CZMP. AND AGAIN BCDC CZMP
INCLUDES ENFORCEABLE OF POLICIES
OF MACATEER PETRIS AND THE BAY
PLAN. OBJECTION IS NOT A
DENIAL. THOUGH BCDC MAY SEEK
MEDIATION FOR JUDICIAL REVIEW.
ARMY CORP PREPARED AN EA UNDER
ITS NEPA AUTHORITY, ALTHOUGH
THIS IS NOT A CZMA REQUIREMENT.
AND THE PORT PREPARED AN EIR
UNDER ITS CEQA AUTHORITY WHICH
IS ALSO NOT A CZMA REQUIREMENT
BUT WILL BE CONSIDERED BY BCDC
WHEN THE PORT NEEDS A BCDC
PERMIT. AND THAT’S THE END OF
MY PRESENTATION.
>>SPEAKER: THANK YOU MICHAEL.
SO, COMMISSIONERS, I HOPE YOU
APPRECIATE THAT MINI CONCISE
TRAINING ON CZMA, CEQA AND NEPA.
IT’S VERY MUCH TO INFORM THE
PROJECT AND HOW THE COMMISSION
STAFF HAS BEEN APPROACHING THE
OAKLAND TURNING BASIN’S WIDENING
PROJECT.
I’M GOING TO GIVE A BRIEF
OVERVIEW OF THE PROJECT BECAUSE
THE ARMY CORP IS GOING TO GIVE A
LONGER AND THOROUGH REVIEW OF
THE ARMY CORP PROJECT. IT’S
IMPORTANT TO NOTE THAT THIS IS A
JOINT PROJECT OF THE PORT OF
OAKLAND AND THE U.S. ARMY CORP
OF ENGINEERS AS MICHAEL
MENTIONED OR ALLUDED TO, THE
PORT OF OAKLAND WILL BE
REQUESTING A BCDC PERMIT LIKELY
IN 2025, 2026. SO, WE LOOK
FORWARD TO SEEING THIS PROJECT
AGAIN AROUND THE MCATEER-PETRIS
ACT STATUS AND BAY PLAN
POLICIES.
SO, JUST A QUICK NOTE. AGAIN,
THIS IS A FIRST PHASE
CONSISTENCY DETERMINATION. THE
ARMY CORP WILL DESCRIBE FURTHER.
BUT IN THE FIRST PHASE, AT THIS
LEVEL WE’RE LOOKING AT THE
FEASIBILITY STUDY AND THE
ENVIRONMENTAL ASSESSMENT FOR THE
PROJECT. THAT MEANS THAT MANY
OF THE DETAILS THAT WE WOULD
NORMALLY RECEIVE IN A PERMIT
APPLICATION HAVE NOT YET BEEN
PROVIDED ALTHOUGH WE HAVE
SEVERAL DETAILS IN HAND. THE
PROJECT IS NOT YET AUTHORIZED OR
FUNDED. SO, WE ANTICIPATE A
SECOND PHASE — WE ANTICIPATE A
SECOND PHASE CONSISTENCY
DETERMINATION IN 2025 OR 2026.
THAT WILL BE AT THE PLANNING
ENGINEERING AND DESIGN PHASE
WHERE MORE DETAILS WILL BE
PROVIDED BY THE ARMY CORP. ONE
OF THE REASONS WE’RE HERE TODAY
IS BECAUSE IN ORDER FOR THE ARMY
CORP OF ENGINEERS TO HAVE THEIR
HEADQUARTERS SIGN WHAT IS KNOWN
AS THEIR CHIEF’S REPORT, THE
COASTAL MANAGEMENT ACT
CONSISTENCY DETERMINATION LETTER
OF AGREEMENT NEEDS TO BE
APPENDED TO THAT REPORT. THEN
LASTLY THIS ACTION HELPS THE
ARMY CORP OF ENGINEERS REQUEST
AUTHORIZATION FOR THIS PROJECT
IN THE WATER RESOURCES AND
DEVELOPMENT ACT, 2024, OR LATER,
SHOULD THAT NEED TO HAPPEN AT A
LATER TIME AND FUTURE
APPROPRIATIONS OF THE PROJECT BY
CONGRESS.
THIS IS THE PORT OF OAKLAND.
I’M HOPING MANY OF YOU ARE
FAMILIAR WITH IT. THIS IS A
GRAPHIC FROM THE PORT’S FILES.
BUT IT SHOWS THE OUTER HARBOR TO
THE NORTHERN PART OF MY SCREEN,
THE TOP OF MY SCREEN, WITH THE
OUTER HARBOR TURNING BASINS,
SORT OF IN THE CRUX OF THE OUTER
HARBOR AND THE INNER HARBOR
TRAVELING BETWEEN THE PORT OF
OAKLAND AND THE ISLAND OF
ALAMEDA WITH THE INNER HARBOR
DOWN IN THE LOWER RIGHT HAND
CORNER OF THE SCREEN. THESE TWO
TURNING BASINS ARE THE MAIN
SUBJECT OF THIS CONSISTENCY
DETERMINATION, BECAUSE AT THIS
TIME, LARGE VESSELS THAT ENTER
THE PORT FACE RESTRICTIONS NOT
ALL OF THEM BUT SOME FACE
RESTRICTIONS WHEN THEY’RE
TRAVELING IN AND OUT OF THE PORT
FACILITIES TO BERTH AND OFFLOAD
THEIR CARGO. THIS IS A SHORT
VERSION OF THE PORT OF OAKLAND’S
PROJECT DESCRIPTION FOR THE
PROJECT. BUT BASICALLY THEY’RE
LOOKING TO IMPROVE EFFICIENCIES
FOR LONGER VESSELS FOR BOTH THE
CURRENT VESSELS THAT ARE
ENTERING AND LEAVING THE HARBORS
TODAY AND ALSO FOR THE FUTURE
DEEP DRAFT VESSELS THAT MAY CALL
AT THE PORT IN THE FUTURE, AND
ARE ANTICIPATED TO CALL IT THE
PORT. THEY ALSO MAINTAIN WANT
TO MAINTAIN THE COMPETITIVENESS
FOR THE PORT INTERNATIONAL CARGO
SHIPMENTS THEY WANT TO MAKE SURE
THAT VESSELS HAVE FLEXIBILITY
FOR CONNECTING TO SHORE POWER
WHILE THEY’RE AT BERTH
APPARENTLY SOME OF THE SHIPS
ONLY HAVE THE ABILITY TO CONNECT
TO SHORE POWER ON THE INSIDE SO
THEY NEED TO BE ABLE TO TURN AND
MAKE SURE THEY CAN CONNECT TO
SHORE POWER. THIS HELPS SUPPORT
A MOVE TOWARDS ZERO-EMISSIONS IN
THE FUTURE AND THEY WILL ALSO
IMPROVE VESSEL MANUFACTURING AND
SAFETY AND REDUCE ENVIRONMENTAL
RISKS SUCH AS OIL SPILLS THAT
CURRENTLY EXIST IN THE TURNING
BASINS WHEN THEY’RE UNDERSIZED
FOR THE VESSELS THAT ARE
TRANSITING THEM AND ALSO
MEASURES TO MODERNIZE ESSENTIAL
WATERWAY PORT OF OAKLAND FOR THE
NATION AND WITH THE FLEET COMING
AND GOING AND THE GRAPHIC ON THE
RIGHT SHOWS SOME OF THE
DIFFERENCES THAT THE PORT IS
FACING NOW BOTH IN THE FUTURE
VESSELS GET LONGER AND WIDER
WITH THE ABILITY OF VESSELS TO
TRY TO CARRY MORE CARGO.
LOOKING AT THE TWO AREAS OF
ACTION FOR THIS PROJECT SO THE
OUTER HARBOR TURNING BASIN CLOSE
UP OF EARLY DESIGN PHASE BUT THE
TURNING BASIN AS IT EXISTS TODAY
IN THE LIGHT GRAY. THE PROPOSED
TURNING BASIN IN THE DARKER OR
CHARCOAL GRAY TO BLACK.
BASICALLY, THIS REPRESENTS AN
EXPANSION OF THE EXISTING
TURNING BASIN BY 21 ACRES. IT
WOULD BE ACCOMPLISHED BY
DREDGING APPROXIMATELY
1.34 MILLION CUBIC YARDS OF
SHALLOW SUBTIDAL HABITAT THAT’S
CURRENTLY AT 4 TO 5 FEET MEAN
LOW WATER. THAT AREA WILL BE
TAKEN DOWN TO MINUS 50 FEET TO
MATCH THE EXISTING TURNING BASIN
STEPS. AND THE PORT AND CORP
HAVE COMMITTED TO BEN OFFICIALLY
REUSING ALL THE DREDGE SEDIMENT
THAT’S CLEAN AND SUITABLE FOR
REUSE FROM THIS PROJECT AND
PARTICULARLY THE OUTER HARBOR
BECAUSE IT’S ANTICIPATED TO HAVE
FEWER CONTAMINANTS IN THE INNER
HARBOR JUST DUE TO THE NATURE
WAS THE UNDISTURBED SITE. AND
AS PART OF THIS, THEY WILL BE
UPGRADING EXISTING ELECTRICAL
INFRASTRUCTURE NEAR 26, WHICH IS
ADJACENT TO THE SITE.
THE INNER HARBOR TURNING BASIN
FAR MORE COMPLEX THAN THE OUTER
HARBOR TURNING THE BASIN
EXPANSION. SIMILARLY THE
GRAPHIC YOU SEE HERE EXISTING
INNER HARBOR TURNING BASIN IN
LIGHT GRAY. THE PROPOSED
WIDENING EXPANSION OF THE
TURNING BASIN IN BLACK WITH THE
DASHED LINES BEING IN AREAS THAT
ARE WITHIN THE EXISTING 50 FOOT
FEDERAL NAVIGATION CHANNEL AND
THE AREAS THAT ARE YELLOW AND
SOLID BLACK ARE AREAS NEED TO BE
EXCAVATED OR DREDGED AS PART OF
THE PROJECT. IN ORDER TO EXPAND
THE TURNING BASIN AS THE CORP
DID IN THE 50-FOOT DEEPENING
PROJECT — THIS HAS BEEN DONE AT
LEAST ONCE BEFORE — PORTIONS
OF HOWARD TERMINAL WHICH WERE
PUT INTO PLACE IN THE 1980’S
WOULD NEED TO BE REMOVED, 3.9
ACRES. ALAMEDA LAND SITE
OPPOSITE THE CHANNEL WOULD HAVE
6.5 ACRES REMOVED. THERE ARE
TWO WAREHOUSES ON THAT SITE;
YOU CAN SEE THEM THERE IN WHITE.
ON THE LOWER PART OF THE SCREEN
ONE OF THEM SAYS ALAMEDA
PROPERTY THOSE WAREHOUSES WOULD
BE PARTIALLY DEMOLISHED TO
ACCOMMODATE THE WIDER TURNING
BASIN. IN THE WHARFS ON BOTH
SIDES THERE IS A COMBINATION OF
A ROCK DIKE, THOSE AREAS THAT
NEED TO BE REMOVED AS PART OF
THIS PROJECT AND TWO BULK HEADS
WOULD BE INSTALLED ONE ON THE
HOWARD TERMINAL SIDE ONE ON THE
ALAMEDA SIDE TO HOLD THE NEW
SHORELINE. IN ADDITION — AND
IT’S NOT ON THIS SLIDE — IN
ADDITION THERE IS A SMALL NARROW
AREA IN FRONT OF SCHNITZER STEEL
ON THE LEFT UPPER PART OF THE
SLIDE WHERE THE CORP WOULD PLACE
IN WATER RETAINING WALL TO HOLD
BACK THE SLOPE OF THE SHORELINE
SO WHEN THE AREA IS DEEPENED TO
MINUS 50 FEET THE SLOPE WOULDN’T
SLUMP AND CAUSE SLOPE FAILURE.
ONCE THE NEW BULK HEADS ARE IN
PLACE THE PROJECT WOULD DREDGE
APPROXIMATELY 825 CUBIC YARDS OF
SEDIMENT ALSO TARGETED FOR
BENEFICIAL REUSE WHENEVER
SUITABLE AND IT WILL BE DEEPENED
TO MINUS 50 FEET TO MATCH THE
CHANNEL AND EXISTING TURNING
BASIN CONSTRUCTION DEBRIS WOULD
BE DISPOSED OR RECYCLED,
DEPENDING ON ITS TYPE, AND THEY
WOULD NEED TO INSTALL ADDITIONAL
INFRASTRUCTURE AT HOWARD
TERMINAL TO SUPPORT THE PROJECT.
OOPS. WE WENT THE WRONG WAY.
SORRY.
>>STEVEN GOLDBECK: BRENDA, I
THINK YOU MISSPOKE. IT’S
825,000.
>>SPEAKER: DID I SAY MILLION?
>>STEVEN GOLDBECK: —
[INDISCERNIBLE] DREDGING.
I THINK YOU SAID 825.
>>SPEAKER: OH. YEAH, I ALWAYS
DROP OFF THREE ZEROES. MY
APOLOGIES. THAT’S WHAT HAPPENS
WHEN YOU WORK IN THE WORLD OF A
LOT OF ZEROS.
THANK YOU FOR THAT, STEVE.
ONE OF THE BIG QUESTIONS OF THE
PROJECT IS MACING FILLS TAKING
AWAY OF FILL, OVERALL IT’S
REDUCTION OF BAY FILL INCREASE
OF SURFACE AREA VOLUME IN THE
BAY. YOU CAN SEE THE TOP FOUR
LINES LOOKING AT FILL REMOVAL
10.4 ACRES OF THE AREA WOULD BE
REMOVED OVERALL THEN 418,400
CUBIC YARDS OF SOLID FILL WOULD
BE REMOVED. THE FILL PLACED, OR
THE NEXT SET OF NUMBERS
TOTALLING 2.81 ACRES OF FILL
PLACED AND 23,000 ACRE YARDS OF
FILL PLACED THAT RESULTS IN
TOTAL NET OF REDUCTION OF 7.6
ACRES AND NET SOLID FILL
REDUCTION OF 395,400 CUBIC YARDS
REPRESENTING INCREASE IN SURFACE
AREA AND VOLUME OF THE BAY WHICH
IS HELPFUL. I’M GOING TO TOUCH
ON ISSUES THAT THE COMMISSION
WILL NEED TO CONSIDER WHEN IT’S
VOTING TO HELP FRAME ANY PUBLIC
COMMENTS THAT MAY ARISE AND ALSO
FOR YOU TO THINK ABOUT THIS
PROJECT AS YOU’RE HEARING THE
ARMY CORP PRESENTATION. SO THE
PRIMARY ISSUES THE PROJECT IS
CONSISTENT WITH THE LAWS AND
POLICIES, WHETHER THE PROJECT IS
CONSISTENT WITH THE SEAPORT PLAN
WHETHER THE ARMY CORP HAS
CONDUCTED EQUITABLE AND
CULTURALLY RELATIVE OUTREACH TO
THE PUBLIC PARTICULARLY THE
ENVIRONMENTAL JUSTICE COMMUNITY
THAT MAY BE DISPROPORTIONATELY
IMPACTED BY THIS PROJECT AND
WHETHER IT’S CONSISTENT WITH OUR
ENVIRONMENTAL SOCIAL JUSTICE
POLICIES AND THERE IS MITIGATION
FOR THOSE IMPACTS WHERE WE HAVE
AUTHORITY. AND LASTLY, WHETHER
THE PROPOSED DELAY ON ADDRESSING
PUBLIC ACCESS AND SCENIC VIEWS
TO THE NEXT PHASE CONSISTENCY
DETERMINATION IS APPROPRIATE.
A COUPLE MORE SLIDES THEN I’LL
TURN IT OVER TO PHOENIX.
MICHAEL TOUCHED ON THIS I’M NOT
GOING TO BELABOR THE POINT BUT A
QUICK REMINDER THAT WE’RE USING
THE 1996 SEAPORT PLAN FOR THIS
PROJECT AS AMENDED IN 2012. HE
MENTIONED THE CURRENT ONE
REQUIRES COASTAL ZONE MANAGEMENT
REVIEW BEFORE WE CAN USE IT.
SO, JUST A QUICK NOTE THAT THE
SEAPORT PLAN AS IT CURRENTLY
EXISTS SUPPORTS REDEVELOPMENT OF
THE PORT TO IMPROVE WATER BORNE
COMMERCE AND COMMERCE AND
SUPPORT ECONOMY OF THE BAY AREA
ALSO INCLUDES DREDGING TO DEEPEN
AND MAINTAIN NAVIGATION
CHANNELS.
AND THEN IN JUST A MINUTE ON
PUBLIC ACCESS. SO THERE HAS
BEEN CONCERNS AND COMMENTS MADE
ABOUT PUBLIC ACCESS AND WHETHER
OR NOT THE PROJECT SHOULD
PROVIDE PUBLIC ACCESS. AND AT
THIS POINT IN TIME, IN THE
FEASIBILITY STAGE, THE CORP AND
THE PORT HAVE NOT PROVIDED OR
PROPOSED ANY PUBLIC ACCESS.
IT’S IMPORTANT TO NOTE DIFFERENT
POLICIES THAT SUPPORT THE
COMMISSION STAFF’S VIEW THAT
PUBLIC ACCESS IS AND SHOULD BE
REQUIRED BY THIS PROJECT. SO,
MCATEER-PETRIS ACT SECTION 66602
SPEAKS TO REQUIRING THE MAXIMUM
FEASIBLE PUBLIC ACCESS
CONSISTENT WITH A PROJECT AND IT
SPECIFICALLY CALLS OUT PORTS AS
ONE AREA WHERE PUBLIC ACCESS
SHOULD BE REQUIRED WHERE
FEASIBLE AND SAFE TO DO SO.
WHEN THE STAFF LOOKS AT PROJECTS
FOR PUBLIC ACCESS THEY LOOK AT
THE POTENTIAL TO AFFECT BOTH
CURRENT AND FUTURE PUBLIC ACCESS
IN THE AREA.
IN LIEU, PUBLIC ACCESS FOR PORT
PROPERTIES IS LIKELY AN OUTCOME
DUE TO THE SAFETY CONCERNS
THAT’S PART OF THE PUBLIC ACCESS
POLICIES AND PUBLIC ACCESS
POLICY 1 AND 2 IT SEEKS IF YOU
CAN’T PROVIDE IT IN PORT
PROPERTIES THAT NEARBY PUBLIC
ACCESS PROJECTS COULD BE
PROVIDED AND IF YOU CAN’T DO IT
NEARBY, THEN PUBLIC ACCESS
SHOULD BE PROVIDED FOR
VULNERABLE OR DISADVANTAGED
COMMUNITIES.
I ALSO WANT TO NOTE THAT THIS
STAFF MET WITH THE CITY OF
ALAMEDA, WHO RAISED SPECIFIC
CONCERNS ABOUT THE STAFF
SUMMARY. AND FRANKLY, THE
TERMINOLOGY USED, WE CALLED IT
ALAMEDA TERMINAL, THE TRUE NAME
IS ALAMEDA LANDING. THE MASTER
LAN FOR THE ALAMEDA LANDING FOR
THE CITY OF ALAMEDA ANTICIPATES
AND ENCOURAGES PUBLIC ACCESS AND
RECREATIONAL OPPORTUNITIES AS
PART OF THAT SITE AND IN FACT
MENTIONED THAT IT’S PART OF THE
BAY TRAIL, IN THE FUTURE.
AND THEN LASTLY, THE PORT’S
POLICIES AND THE SEAPORT PLAN
SAY THAT PORT SHOULD BE DESIGNED
WHENEVER FEASIBLE TO PERMIT
PUBLIC ACCESS AND VIEWING
ACTIVITIES THROUGH VIEWING
OPPORTUNITIES FOR PORT
ACTIVITIES THROUGH VIEWPOINTS
AND OPENINGS BETWEEN BUILDINGS
AND OTHER SITE DESIGNS THAT
PERMIT VIEW OF THE MARITIME
ACTIVITIES. JUST WANTED TO CALL
THOSE TO YOUR ATTENTION AS WE
THINK ABOUT THIS PROJECT WITH
THE PROPOSED PUBLIC ACCESS. AND
I’M GOING TO TURN IT OVER TO
PHOENIX ARMENTA TO TALK ABOUT
THE ENVIRONMENTAL JUSTICE
POLICIES.
>>SPEAKER: WEST OAKLAND IS AN
ENVIRONMENTAL COMMUNITY AS
DEMONSTRATED BY CALENVIROSCREEN,
EJ COMMUNITY SCREENING TOOL AND
BCDC COMMUNITIES VULNERABLE MAP
CLOSEST TO THE OAKLAND HARBOR
TURNING BASIN ARE WITHIN THE
70th, 8TH, 90th PERCENTILE IN
TERMS OF THE ENVIRONMENTAL
BURDEN IN THE STATE OF
CALIFORNIA BCDC SOCIAL
VULNERABILITY MAP SHOWS
COMMUNITIES AROUND THE TURNING
BASIN RANGE FROM MODERATE TO
HIGH SOCIAL VULNERABILITY.
OAKLAND HAS A LONG HISTORY OF
INDUSTRIAL USES PORT EXPANSION
AND IS SURROUNDED BY TWO
FREEWAYS LEADING TO THE HIGHEST
EXPOSURES TO PARTICULATE MATTER
IN THE NATION. NEXT SLIDE.
BCDC ENVIRONMENTAL JUSTICE AND
SOCIAL EQUITY POLICIES ADOPTED
IN 2019 OUTLINE REQUIREMENTS FOR
WORKING IN SOCIALLY VULNERABLE
COMMUNITIES FIRST POLICY DIRECTS
COMMISSION TO INCLUDE PRINCIPLES
ENVIRONMENTAL JUSTICE AND SOCIAL
EQUITY IN ALL ACTIONS AND
ACTIVITIES RELATED TO
ENVIRONMENTAL JUSTICE AND SOCIAL
EQUITY THAT MAY AFFECT THE
COMMISSION’S AUTHORITY OR
JURISDICTION.
THE THIRD POLICY REQUIRES
MEANINGFUL COMMUNITY ENGAGEMENT
BY LOCAL GOVERNMENTS AND PROJECT
APPLICANTS WORKING IN SOCIALLY
VULNERABLE COMMUNITIES FOURTH
POLICY REQUIRES THAT LOCAL
GOVERNMENTS AND THE COMMISSION
SHOULD MAKE MEASURES THROUGH
ENVIRONMENTAL REVIEW OF THE
PERMITTING PROCESS WITHIN THE
SCOPE OF THEIR RESPECTED
AUTHORITY TO REQUIRE MITIGATION
FOR DISPROPORTIONATE ADVERSE
PROJECT IMPACT ON THE IDENTIFIED
VULNERABLE COMMUNITIES IN WHICH
THE PROJECT IS PROPOSED. IT’S
IMPORTANT TO NOTE THAT POLICY
FOUR IS APPLIED ONLY WITHIN THE
SCOPE OF THE COMMISSION’S
RESPECTIVE AUTHORITY WHEN
CONSIDERING ITS APPLICATION TO
THE OAKLAND HARBOR TURNING
BASIN. NEXT SLIDE PLEASE.
WITH REGARDS TO MEANINGFUL
COMMUNITY ENGAGEMENT THE PORT
AND THE U.S. ARMY CORP OF
ENGINEERS HELD A TOTALLY OF NINE
MEETINGS AS PART OF THE NEPA AND
CEQA PROCESSES THEY MET WITH
LOCAL GROUPS SUCH AS THE OAKLAND
ENVIRONMENTAL INDICATOR’S
PROJECT JACK LONDON IMPROVEMENT
DISTRICT AND ACORN PRESCOTT
NEIGHBORHOOD COUNCIL TO DISCUSS
THE PROJECT THEY ALSO WORKED
CLOSELY WITH ME TO DEVELOP AND
HELP WITH THE OUTREACH
STRATEGIES. NEXT SLIDE.
ENVIRONMENTAL JUSTICE CONCERNS
STILL REMAIN AROUND THE PROJECT
INCLUDING CONCERNS AROUND
SIGNIFICANT UNAVOIDABLE EFFECTS
OF AIR QUALITY FROM CONSTRUCTION
AND DREDGING EQUIPMENT CONCERNS
OF WIDENING COULD INDUCE GROWTH
OVER TIME AND CONTRIBUTING TO
WORSENING AIR QUALITY RESIDENTS
DON’T WANT CONTAMINATED SOIL TO
BE PASS ODDS TO OTHER EJ
COMMUNITIES LIKE KETTLE MAN
CITY. IT’S IMPORTANT TO NOTE
THESE CONCERNS ALTHOUGH
IMPORTANT TO ADDRESS DO NOT FALL
UNDER THE SCOPE OF BCDC’S
AUTHORITY. NEXT SLIDE. BCDC
HAS BEEN COORDINATING WITH
AGENCIES TO HAVE SOME AUTHORITY
ON THESE ENVIRONMENTAL JUSTICE
CONCERNS TO HELP ADDRESS THEM
OUR STAFF HAS BEEN WORKING WITH
BAY AREA AIR QUALITY MANAGEMENT
DISTRICT, CALIFORNIA AIR
RESOURCES BOARD, CALIFORNIA
DEPARTMENT OF FISH AND WILDLIFE
AND CALIFORNIA WATER BOARDS
CALIFORNIA SUBSTANCES CONTROL
AND US EPA TO WORK ON FINDING
SOLUTIONS TO THE ENVIRONMENTAL
JUSTICE CONCERNS ON THIS
PROJECT. I’LL SEND IT BACK TO
BRENDA TO TALK MORE ABOUT THE
PROJECT.
>>SPEAKER: THANK YOU. SO THE
COMMISSION UNFORTUNATELY DOES
NOT HAVE THE ABILITY TO ADDRESS
AIR QUALITY ISSUES ASSOCIATED
WITH THIS PROJECT IT’S OUTSIDE
OF OUR SCOPE AND AUTHORITY
HOWEVER BECAUSE WE REALIZED THE
COMMISSION MAY BE CONCERNED
ABOUT THE AIR QUALITY IMPACTS OF
THE PROPOSED PROJECT WE THOUGHT
WE WOULD BRIEFLY LIST OUT SOME
OF THE AGENCIES THAT HAVE THE
ABILITY TO REGULATE THESE ISSUES
IN CALIFORNIA. WE ARE TRYING TO
LAY OUT AREAS WHERE THIS ISSUE
CAN BE ADDRESSED. SO, THE BAY
AREA AIR QUALITY MANAGEMENT
DISTRICT REGULATES STATIONARY
EQUIPMENT AND COMMENTS ON
ENVIRONMENTAL DOCUMENTS. THE
CALIFORNIA AIR RESOURCES BOARD
REGULATES MOBILE EQUIPMENTS,
VEHICLES AND SHIPS IN STATE
WATERS. SO, FOR EXAMPLE, THEY
HAVE REGULATIONS RELATING TO
TRUCKING AND THIS IS THE CARB
REGULATION. SO, ALL OF THESE
LISTED BELOW ARE PRIMARILY
RELATED TO CARB, BECAUSE THEY
ARE ENACTING NEW LAWS AND
POLICIES AND REGULATIONS TO
IMPROVE AIR QUALITY THROUGHOUT
THE STATE OF CALIFORNIA. SO,
YOU CAN SEE THAT THEY’RE WORKING
TO REDUCE SULFUR OXIDES, NITROUS
OXIDES, REDUCING EMISSIONS FROM
TRUCKS THROUGH INCREASING
IMPROVEMENTS FOR THEIR ENGINES,
FOR LES EMISSIONS. OVER TIME.
AND SO SOME OF THOSE ARE ALREADY
IN PLACE. SOME ARE COMING
ONLINE NOW. VESSEL REGULATIONS
THAT THEY HAVE ENACTED ARE
LOOKING AT RENEWABLE DIESEL
FUEL, AND, AGAIN, IMPLEMENTING
PHASED-IN BETTER ENGINES WITH
LESS EMISSIONS. SIMILARLY FOR
CARGO EQUIPMENT, THEY’RE
DEVELOPING CARGO HANDLING AND
REGULATIONS TO TRANSITION TO
ZERO-EMISSIONS FOR THOSE TYPES
OF EQUIPMENT, AND THEN FINALLY
WITH RAIL, THEY’RE LOOKING AT
IMPROVING LOCATION MOTION SO IT
HAS LESS EMISSIONS AND THEN
ZERO-EMISSIONS OVER TIME. SOME
OF THAT IS BY PHASING OUT OLDER
EQUIPMENT.
LASTLY, BECAUSE CALIFORNIA’S LAW
AND AUTHORITY ONLY GOES TO THE
EXTENT OF THE STATE OF
CALIFORNIA’S JURISDICTION, I
ALSO LOOKED INTO WHAT KIND OF
REGULATIONS APPLY TO OVER —
EXCUSE ME — TO OCEAN GOING
VESSELS THAT MAY COME TO THE
PORT OF OAKLAND WHEN THEY’RE
CALLING ON THE PORT.
SO, THERE ARE CONTROLS WENT 200
MILES OF THE COAST THROUGH THE
INTERNATIONAL MARITIME
ORGANIZATION, THEY’RE LOOKING,
AGAIN, TO REDUCE — EXCUSE ME —
SULFUR OXIDES, AND — [ AUDIO
DISTORTION ] GREENHOUSE GASSES,
U.S. MARINE VESSELS. THE JONES
ACT WHILE NOT SPECIFICALLY
LOOKING AT EMISSIONS IT GOVERNS
DOMESTIC SHIPPING IN THE UNITED
STATES, THERE IS A FEDERAL
MARITIME COMMISSION WHICH
GOVERNS OTHER ASPECTS OF
SHIPPING BUT NOT NECESSARILY
MISSIONS. AND THEN LASTLY,
CALIFORNIA AIR BOARD, JUST A
LITTLE BIT MORE, WITHIN 24
NAUTICAL MILES FROM BASELINE OF
THE STATE, THEY HAVE OCEAN-GOING
VESSEL FUEL REDUCTION
REGULATIONS AND OCEAN GOING
VESSELS AT BERTH REGULATIONS.
SO I WANTED TO BRING THIS TO
YOUR ATTENTION SO THE COMMISSION
DOES HAVE AN AWARENESS OF THE
DIFFERENCE LAWS AND ORGANIZATION
THAT IS WORKING TO REDUCE AIR
QUALITY IMPACTS AT THE PORTS AND
FOR THE COMMUNITIES THAT ARE
AROUND THEM. NEXT STEPS SO YOU
KNOW WHERE WE’RE GOING. NEXT
STEPS ARMY CORP IS GOING TO GIVE
A PRESENTATION ON THE PROJECT IN
MORE DETAIL THAN I HAVE PROVIDED
HERE TODAY THEN WE’LL HAVE
OPPORTUNITY TO HEAR FROM THE
PUBLIC ON THIS PROJECT.
DECEMBER 15TH IS THE DATE WE
ANTICIPATE SENDING OUT THE STAFF
RECOMMENDATION. IT WILL BE
RELEASED BOTH TO THE PUBLIC AND
THE COMMISSION. A.M. IS THE DAY
THAT WE ARE PLANNING TO VOTE ON
THIS PROJECT AND THIS IS A VERY
IMPORTANT DAY, BECAUSE IT’S THE
LAST OPPORTUNITY FOR THE
COMMISSION TO VOTE IN 2023.
AND THEN, LASTLY, SHOULD THE
COMMISSION CHOOSE TO CONCUR WITH
THIS PROJECT, WE WOULD ISSUE THE
LETTER OF AGREEMENT NOT LATER
THAN DECEMBER 31ST, 2023.
SO, THIS IS A PLEA FROM OUR
FRIENDS THE HARBOR SEALS,
COMMISSIONERS PLEASE COME TO THE
MEETING ON A.M. BECAUSE WE NEED
THE 84 TOWEL HAVE A VOTE OR THE
PROJECT WILL BE DELAYED AND
POTENTIALLY NOT MAKE IT INTO THE
REPORT. SO THAT’S A CUTE LITTLE
FACE SAYING PLEASE COME. WE
WOULD LIKE TO SEE YOU AGAIN IN A
COUPLE OF WEEKS. THAT IS IT
FROM ME AND NEXT UP IS THE ARMY
CORP. AND I THINK I’M SHARING
MY SCREEN FOR THEM, AS WELL.
JUST ONE MINUTE. WITH THAT, I
WOULD LIKE TO INTRODUCE ERIKA
POWELL, FROM THE ARMY CORP OF
ENGINEERS. SHE ALSO HAS MEMBERS
FROM THE PORT OF OAKLAND AND THE
ARMY CORP STAFF WITH HER TODAY
TO ASSIST IN THE PRESENTATION OR
QUESTIONS SHOULD THEY ARISE.
ERIKA?
>>ERIKA POWELL: THANK YOU
BRENDA HELLO EVERYONE MY NAME IS
ERIKA POWELL. THANK YOU
COMMISSIONERS AND BCDC STAFF FOR
ALL YOUR SUPPORT AND OPPORTUNITY
TO PRESENT TODAY ON THE OAKLAND
HARBOR TURNING BASINS WIDENING
FEASIBILITY REPORT AND
ENVIRONMENTAL ASSESSMENT. THIS
STUDY WAS AUTHORIZE WAS FUNDED
BY CONGRESS WHICH ALLOWED THE
ARMY CORE OF ENGINEERS TO ENTER
INTO AN AGREEMENT WITH THE PORT
OF OAKLAND IN JULY OF 2020 TO
DETERMINE IF THERE WAS A
TECHNICALLY FEASIBLE
ECONOMICALLY JUSTIFIED
ENVIRONMENTALLY ACCEPTABLE
PROJECT THAT WOULD DECREASE
VESSEL TRANSIT INEFFICIENCIES AT
THE OAKLAND HARBOR. SO THAT WAS
THE PURPOSE OF THE STUDY. I AM
JOINED HERE BY — NEXT SLIDE —
>>SPEAKER: IT’S NOT
TRANSITIONING.
>>ERIKA POWELL: I WAS GOING TO
TAKE THAT OPPORTUNITY TO SAY I’M
SO HAPPY TO SEE SO MANY FAMILIAR
FACES. SO, I’M JOINED HERE BY
THE CORP OF ENGINEERS TEAM
MEMBERS. WE HAVE A VERY LARGE
TEAM BUT WE DO HAVE FOLKS HERE
IN PERSON. BARNEY WAIR, WHO IS
OUR TECHNICAL LEAD, ALSO OUR
GEOTECHNICAL EXPERT, ERIK
JOLIFFE, OUR ENVIRONMENTAL LEAD,
AND VIRTUALLY, WE HAVE ELIZABETH
DIONNE. OUR LEAD PLAN
FORMULATOR, AND ELLIE C, WHO IS
OUR ENVIRONMENTAL COLEAD AND
ENVIRONMENTAL JUSTICE
SPECIALIST. I’M ALSO JOINED
HERE BY THE PROJECT DELIVERY
TEAM ON THE PORT SIDE. JUSTIN
TASCHEK. I BELIEVE THE PORT
WOULD LIKE TO MAKE A FEW
COMMENTS. IF THAT’S OKAY?
>>CHAIR, ZACHARY WASSERMAN:
YES.
>>JUSTIN TASCHEK: GREAT.
APPRECIATE THAT. GOOD AFTERNOON
HONORABLE MEMBERS OF THE BCDC
COMMISSION. BCDC STAFF, AND THE
PUBLIC.
MY NAME IS JUSTIN TASCHEK, AND I
AM THE PORT OF OAKLAND PROJECT
ADMINISTRATOR FOR THE PROPOSED
PROJECT TO WIDEN THE OAKLAND
HARBOR TURNING BASINS. WITH ME
MY ESTEEMED COLLEAGUES, EDWIN
DRAPER, LEAD ENVIRONMENTAL
SCIENTIST, CAMERON CHUOP, AND I
WOULD LIKE TO SAY THANK YOU TO
BCDC STAFF FOR THEIR COMMITMENT
AND SUPPORT FOR BRINGING THIS
ITEM BEFORE THE COMMISSION TODAY
AND SECONDLY, I WOULD LIKE TO
TAKE THE OPPORTUNITY TO THANK
THE U.S. ARMY CORP OF ENGINEERS
FOR DETERMINATION AND LEADERSHIP
IN ENSURING THE PORT CONTINUES
TO DELIVER ECONOMIC PROSPERITY
TO THE REGION. THE PORT, IN
COLLABORATION WITH COMMUNITY
MEMBERS, ENVIRONMENTAL
ORGANIZATIONS, INDUSTRY, AND
LOCAL AGENCIES, INCLUDING BCDC,
IS COMMITTED TO A DECARBONIZED
FUTURE AND PROUDLY ALIGNS ITSELF
WITH THE MUTUAL GOAL OF
DELIVERING SUSTAINABLE
TRANSPORTATION INITIATIVES.
WIDENING THE TURNING BASINS IS
ONE SUCH PROJECT THAT HELPS
DELIVER ON THIS COMMITMENT.
WITH WIDENED TURNING BASINS, THE
PORT CAN ACCOMMODATE SAFE
EFFICIENT ACCESS FOR A
TRANSITIONING GLOBAL FLEET THAT
INCLUDES NEWER, LONGER, AND MORE
ENVIRONMENTALLY FRIENDLY SHIPS
WHICH ARE SHORE POWER READY.
THAT IS THE SHIPS CAN PLUG IN
AND TURN THEIR ENGINES OFF WHILE
AT BERTH. THANK YOU FOR BCDC’S
ONGOING SUPPORT. OUR SHARED
PURSUIT OF REGIONAL PROSPERITY
AND BAY RESILIENCE UNDERSCORES
THE IMPORTANCE OF THIS AGENDA
ITEM AND WHY WE’RE HERE TODAY.
THE PORT LOOKS FORWARD TO OUR
COLLECTIVE ENDEAVORINGS AS WE
NAVIGATE A COURSE TOWARDS A
THRIVING, SUSTAINABLE, AND
DECARBONIZED FUTURE. AS A
REMINDER, THE PORT, AS LEAD
AGENCY UNDER THE CALIFORNIA
ENVIRONMENTAL QUALITY ACT, AS
MENTIONED PRIOR, RELEASED A
DRAFT ENVIRONMENTAL IMPACT
REPORT FOR THE PROPOSED PROJECT
ON OCTOBER 3RD. COMMENTS ARE
DUE DECEMBER 18TH.
RESPECTFULLY, WE ARE IN THE OPEN
PUBLIC COMMENT PERIOD FOR THE
CEQA DOCUMENT, AND ALL QUESTIONS
DIRECTED TO THE PORT HERE TODAY
WILL BE INCLUDED AND RESPONDED
TO IN THE FINAL ENVIRONMENTAL
IMPACT REPORT.
AND I WOULD LIKE TO NOTE FOR THE
PUBLIC RECORD, LAST FRIDAY,
DECEMBER 1ST, THE PORT SUBMITTED
A COMMENT LETTER FOR STAFF’S
CONSIDERATION, AS WELL AS THE
COMMISSION’S CONSIDERATION,
FURTHER EXPANDING ON INFORMATION
RELATED TO THIS PROPOSED
PROJECT. WITH THAT I’LL HAND IT
BACK TO ERICA. THANK YOU.
>>ERIKA POWELL: ALL RIGHT.
THANK YOU TO THE PORT FOR BEING
HERE TODAY. I AM EXCITED ABOUT
GIVING CREDIT TO BCDC STAFF.
THAT WAS A FANTASTIC
PRESENTATION. THANK YOU SO MUCH
YOU’RE GOING TO MAKE MY JOB SO
MUCH EASIER.
SO, NEXT SLIDE, PLEASE.
SO, JUST TO KIND OF WALK THROUGH
THIS SLIDE A LITTLE BIT. ON THE
FAR LEFT, FOR THOSE OF YOU NOT
ENTIRELY FAMILIAR WITH THE MAKE
UP OF THE SEAPORT AREA. ON THE
FAR LEFT IS AN ARROW THAT POINTS
TO THE ENTRANCE TO THE
NAVIGATION CHANNEL. ON THE
UPPER PART OF THAT — THE SLIDE,
IS AN ARROW THAT POINTS TO THE
OUTER BASIN AND THEN THE FAR
BOTTOM RIGHT IS AN ARROW THAT
POINTS TO THE INNER BASIN. THE
BLUE DASH LINE SHOWS THE FEDERAL
CHANNEL LIMITS OF THE OAKLAND
HARBOR WHICH INCLUDES DEEP
NAVIGATION CHANNELS AND TWO
TURNING BASINS. A TURNING BASIN
IS VERY SIMILAR TO A CUL-DE-SAC
ON A STREET. RIGHT? SO THE
WHOLE POINT OF A TURNING BASIN
IS TO ALLOW VESSELS ENTERING OR
DEPARTING OR EXITING THE PORT TO
TURN AROUND. SO THAT’S JUST TO
KIND OF GIVE YOU A BIRDS EYE
VIEW OF THE PORT. NEXT SLIDE,
PLEASE.
WE HAD ANOTHER SLIDE SIMILAR TO
THIS ONE, JUST TO KIND OF SPEAK
TO THE PROBLEM. THE EXISTING
TURNING BASINS WERE DESIGNED FOR
CONTAINER VESSEL OF
APPROXIMATELY 1139 FEET.
VESSELS LARGER THAN THAT HAVE
RESTRICTIONS SO THE EXPERIENCED
RESTRICTIONS FOR TODAY WHEN
USING THE EXISTING TURNING
BASINS. THESE RESTRICTIONS
INCLUDE SCHEDULING TRANSITS
AROUND SPECIFIC TIDE, CURRENT,
AND WIND CONDITIONS. LIMITING
TO DAYLIGHT TIMES. USES OF
ADDITIONAL PILOT AND REQUIRED
NUMBER OF VESSEL —
[INDISCERNIBLE] ARE NEEDED,
THAT’S HOW THEY MITIGATE THESE
RESTRICTIONS. THESE CAN DELAY
VESSELS FROM ARRIVING OR
DEPARTING A BERTH. IN ADDITION
VESSELS LONGER THAN 1200 FEET IN
LENGTH ARE USED IN THE HARBOR
TURNING BASIN AND ARE RESTRICTED
TO DOCKING PORT SIDE ONLY
POINTED EAST. THAT CAN IMPACT
THE ABILITY FOR THE VESSEL TO
USE SHORE POWER, AND IF NEEDED,
IT PREVENTS — IT PREVENTS THE
ABILITY TO DEPART IN AN
EMERGENCY. SO, ONE THING THAT’S
KIND OF IMPORTANT HERE TOO THAT
I WOULD LIKE TO POINT OUT IS
THAT IN THE FUTURE, EXISTING
FLEETS OF SMALLER VESSELS WILL
BE REPLACED BY LARGER VESSELS,
AND WE DO HAVE A SLIDE THAT
SHOWS THAT TREND. WE HAVE DATA
THAT SHOWS THAT TREND. NEXT
SLIDE PLEASE.
SO, THIS IS JUST ANOTHER WAY,
ANOTHER ILLUSTRATION OF THE
VESSELS THAT ARE — OR THE CLASS
OF THAT — THE VESSEL CLASSES
THAT ARE VISITING OR CALLING ON
THE PORT TODAY. SO, ANY VESSEL
ABOVE A THOUSAND FORTY-FIVE
FEET, AS YOU CAN SEE IN THE TOP
BLUE TABLE DOESN’T EXPERIENCE
THE RESTRICTIONS THAT WE HAVE
MENTIONED EARLIER. HOWEVER, IF
YOU LOOK AT THE BOTTOM TABLE,
THERE ARE ALL SORTS OF
RESTRICTIONS FOR ANY VESSEL
THAT’S OVER 1200 FEET. AND AS
YOU HEARD MY SAY, THERE IS TIDE,
CURRENT, AND WIND CONDITIONS
THAT IMPEDE THE PROPER
NAVIGATION OF THESE VESSELS.
THEY NEED ADDITIONAL PILOT, THEY
NEED ADDITIONAL TUGBOATS TO HELP
THEM NAVIGATE SAFELY IN AND OUT
OF THE PORT.
NEXT SLIDE, PLEASE.
AND I SHOULD HAVE MENTIONED,
TOO, ON THAT LAST SLIDE, THAT
ALL OF THOSE VESSELS ARE COMING
INTO THE PORT TODAY. A BRIEF
DESCRIPTION OF THE PROJECT AND I
THOUGHT BRENDA DID A GREAT JOB
IN DETAILING IT PART OF THE U.S.
ARMY CORP OF ENGINEERS PLAN
FORMULATION PROCESS IT WAS
DETERMINED THAT THE INNER HARBOR
TURNING BASIN SHOULD BE WIDENED
BY AN ADDITIONAL 334 FEET AND TO
A DEPTH OF 50 FEET WHICH IS
CONSISTENT WITH THE CURRENT
DEPTH OF THE TURNING BASIN AND
THE INNER HARBOR CHANNEL. THE
PURPLE AREAS WHERE THE LAND
EXCAVATION AND DREDGING OCCUR
BOTH IN THE OAKLAND SIDE AND THE
ALAMEDA SIDE. THE TWO
WAREHOUSES ON THE BOTTOM WHERE
IT SAYS ALAMEDA THEY ACTUALLY,
DEMOLITION WE SAY PARTIAL
DEMOLITION, I DON’T KNOW IF
YOU’RE FAMILIAR WITH THESE
WAREHOUSES, WE HAVE TWO BAYS
THAT WOULD BE IMPACTED IN THE
FRONT AND THREE BAYS IN THE
BACK. THE DARK ORANGE DASH
LINES REPRESENT THE NEW BULK
HEAD AND YOU CAN SEE BOTH ON THE
OUTER EDGE OF THE GREEN CIRCLE
ON THE HOWARD SIDE AND THEN ON
THE ALAMEDA SIDE. THE NEW BULK
HEAD SERVES AS SEPARATION OF
LAND AND WATER. ON THE RIGHT IS
THE SCHNITZER STEEL NOW WHAT IS
CALLED RADIUS RECYCLING THAT IS
AN INWATER STRUCTURE AND THE
POINT OF THAT LITTLE WALL IS TO
PREVENT SLOPE FROM — TO PREVENT
SLOPE FROM SLIPPING THERE. THE
TILL OF THE SLOPE. IT IS
PROPOSED THAT INFRASTRUCTURE
WOULD BE INSTALLED AT THE
SOUTHEAST CORNER OF HOWARD
TERMINAL TO FACILITATE ELECTRIC
DREDGING TO REDUCE CONSTRUCTION
AND EMISSIONS FOR THE PROSED
PROJECT. OKAY. THE LAST THING
I WOULD LIKE TO SHARE WITH YOU
AS A TAKE AWAY FOR THIS IS A
TOTAL OF 2.4 MILLION CUBIC YARDS
OF DREDGE MATERIAL IS EXPECTED,
AND DIRT WILL BE TAKEN FROM THE
INNER AND OUTER BASIN SO THE
TOTAL IS 2.4 MILLION. A LITTLE
MORE THAN 2 MILLION WOULD
ACTUALLY BE TAKEN BY BARGE TO
NEARBY WETLANDS RESTORATION SITE
FOR BENEFICIAL USE AND
APPROXIMATELY 400,000 CUBIC
YARDS WHICH ARE NOT, RIGHT NOW,
ESTIMATED NOT SUITABLE FOR
BENEFICIAL USE, IS PROPOSED TO
BE TAKEN TO A LANDFILL AND/OR
RECYCLED.
NEXT SLIDE, PLEASE.
THE OUTER HARBOR TURNING BASIN
WOULD BE WIDEN TO APPROXIMATELY
315 FEET AND AGAIN TO THE SAME
DEPTH AS THE EXISTING CHANNEL
WHEN WHICH IS MINUS 50, THIS
WOULD BE ACCOMPLISHED BY
DREDGING SHOWN IN THE PURPLE
HATCH AND DOES NOT REQUIRE ANY
REMOVAL OF ANY LAND. IN
ADDITION, AND BASED ON PUBLIC
FEEDBACK SPECIFICALLY FROM THE
BAR PILOTS, THE BASIN WOULD BE
SHIFTED AWAY FROM THE BERTH AREA
TO ALLOW THEM TO HAVE ACCESS.
BERTH 26 IS WHERE WE WOULD
PROPOSE ELECTRICAL
INFRASTRUCTURE FOR ELECTRIC
DREDGING AND BERTH TEN WOULD BE
USED FOR CONSTRUCTION STAGING
AND REHANDLING OF NON-HAZARDOUS
DREDGE MATERIAL THAT REQUIRES
LANDFILL DISPOSAL. NEXT SLIDE
PLEASE.
SO, ACTUALLY BEFORE I TALK ABOUT
THIS SLIDE, I DID WANT TO SAY A
SPECIAL THANKS TO BCDC EPA
REGION NINE AND THE PORT OF
OAKLAND FOR THEIR COLLABORATION
WITH OUR DISTRICT TO ENSURE
MEANINGFUL PUBLIC ENGAGEMENT,
AND EFFECTIVE PUBLIC ENGAGEMENT.
WE STARTED MEETING ON A WEEKLY
BASIS. IT’S BEEN A YEAR SINCE
WE STARTED MEETING ON A WEEKLY
BASIS WELL IN ADVANCE OF THE
RELEASE OF THE SECOND DRAFT IFR
EPA INTEGRATED FEASIBILITY
REPORT ENVIRONMENTAL ASSESSMENT
AND TO HIGHLIGHT THE FACT THAT I
BELIEVE IT WAS AROUND THE END OF
2022, THAT WE HAD POLICY
GUIDANCE FOR ENVIRONMENTAL
JUSTICE. SO THAT ALLOWED US TO
STEP UP OUR ENVIRONMENTAL — I’M
SORRY — OUR PUBLIC ENGAGEMENT.
SO, WE, THE CORP, ARE TRYING TO
DO MORE THAN THE BEAR MINIMUM
NOW, AS MUCH AS WE POSSIBLY CAN.
SO, WITH THIS NEW GUIDANCE WE
WERE ABLE TO CONSIDER
COMPREHENSIVE BENEFITS. AND
THAT’S AN INTERESTING TERM BUT
WHAT IT SAYS IS WE WERE ABLE TO
LOOK AT ELECTRIC DREDGING DURING
CONSTRUCTION AND BENEFICIAL USE
OF DREDGE MATERIAL, EVEN THOUGH,
FOR EXAMPLE, FOR DREDGE
MATERIAL, WE’RE NOT REQUIRED TO
DO IT AS MITIGATION, BUT THIS IS
SOMETHING THAT WE ACTUALLY HAVE
TO GO TO THE ASSISTANT SECRETARY
OF THE ARMY AND ASK FOR
PERMISSION TO BE ABLE TO COST
SHARE THAT WITH THE LOCAL
SPONSOR. THEY APPROVED THAT, SO
THAT’S A RECOMMENDATION THAT’S
BEING MADE BY THIS REPORT. IN
ADDITION, THE PORT OF OAKLAND IS
ACTUALLY GOING TO BE FULLY
PAYING ENTIRETY FOR THE ELECTRIC
DREDGES. SO THAT’S SOMETHING
THAT THE PORT IS DOING, AS WELL.
AND THAT’S JUST TO POINT OUT
THAT WE HAD AS MANY MEETINGS AS
POSSIBLE. WE HAD SOME
NEIGHBORHOOD COUNCIL MEETINGS,
WHICH WERE — IT’S NOT SOMETHING
THAT WE TYPICALLY DO BUT WE WERE
ASKED TO BE INVITED TO THEIR
MONTHLY MEETINGS, AND THAT’S ONE
WAY THAT WE WERE TRYING TO REACH
OUT. WE ALSO MET WITH THE WEST
OAKLAND ENVIRONMENTAL
INDICATOR’S PROJECT TWICE, ONCE
IN ’22, AND ONCE IN ’23. NEXT
SLIDE, PLEASE.
SO, ONE OF THE COMMENTS THAT WE
RECEIVED MULTIPLE TIMES, AND
WE’RE TRYING TO ADDRESS THAT,
WAS RELATED TO INDUCED GROWTH.
AND SO ONE OF THE THINGS THAT WE
WOULD LIKE TO CLARIFY IS THAT
THE RECOMMENDED PLAN DOES NOT
CHANGE HOW MANY VESSELS CAN BE
ADOPTED AT ANY TIME. SO
INCREASING THE DIAMETER OF THE
TURNING BASINS DOES NOT ADD
BERTHING SPACE.
THE RECOMMENDED PLAN ALSO DOES
NOT CHANGE THE CONTAINER
HANDLING FACILITIES. SO, THE
PORT’S LAND SIDE CONTAINER
HANDLING CAPACITY REMAINS
CONSTANT, REMAINS THE SAME.
THIRDLY, THE RECOMMENDED PLAN
DOES NOT AFFECT CONSUMER
ECONOMIC ACTIVITY IN THE BAY
AREA, OR IN THE CENTRAL AND
NORTHERN CALIFORNIA MARKET.
ECONOMIC FACTORS SUCH AS
RECESSIONS, TRADE AGREEMENTS,
MICRO ECONOMIC DEMANDS,
ECONOMIES OF SCALE AFFECT GLOBAL
SHIPPING SUPPLY AND DEMAND.
WHAT THE RECOMMENDED PLAN DOES
IS IT ALLOWS FOR SHIPS TO TURN
MORE SAFELY, AND FOR SMALLER
SHIPS TO BE PHASED OUT FOR
BIGGER MORE EFFICIENT FLEETS.
THE RECOMMENDED PLAN ALSO ALLOWS
FOR EFFICIENCY IN DEPARTING AND
ARRIVING AT THE PORT WITH FEWER
IDLING SHIPS, FEWER RESTRICTIONS
ON SHIPS ALREADY IN THE HARBOR.
NEXT SLIDE, PLEASE.
AND THEN, AS I INDICATED
EARLIER, I WAS GOING TO PROVIDE
YOU WITH A SLIDE THAT
ILLUSTRATES THE TRENDS OF
SHORTER AND LONGER VESSEL CALLS
TO THE PORT OF OAKLAND. IN THIS
GRAPH, IF YOU LOOK ON THE FAR
LEFT, YOU HAVE THE NUMBER OF
CALLS. ON THE BOTTOM, YOU HAVE
THE YEAR STARTING IN 2014 TO
TODAY, AND ON THE FAR RIGHT YOU
HAVE THE TEUS OR THE THROUGHPUT
PER YEAR. SO THE VESSELS ARE
GROUPED INTO TWO CATEGORIES
HERE. IF YOU LOOK AT THE SOLID
NAVY BLUE LINE, THAT IS THE
LONGER VESSELS. THE DASHED LINE
IS THE SHORTER VESSELS, AND
THERE IS A VERTICAL LINE THAT
SHOWS THAT PRIOR TO THE
PANDEMIC, THE TOTAL NUMBER OF
SHORTER UNRESTRICTED VESSELS
CONTINUED ITS DOWNWARD TREND.
AND THEN THROUGH SEPTEMBER OF
THIS YEAR, THE PORT HAS SEEN 406
LONG VESSELS CALL THE PORT,
COMPARED TO 319 SHORTER VESSELS
— OR SHORT VESSELS, I SHOULD
SAY.
THEN THE — OKAY, THE BIG TAKE
AWAY HERE IS THE GRAY SHADED
AREA DEPICTS TOTAL CARGO HANDLE
FOR THE LAST TEN YEARS DURING
WHICH TIME CARGO VOLUME HAS
REMAINED RELATIVELY CONSTANT.
THOUGH THE NUMBER OF VESSELS HAS
CONTINUED TO DECREASE. SO,
THANK YOU FOR ALLOWING ME TO
PRESENT THOSE SLIDES. ALLOWING
ME TO PRESENT THOSE SLIDES. I’M
GOING TO HAND IT OFF TO ERIK
JOLIFFE.
>>ERIC JOLIFFE: THANKS ERICA.
THANK YOU FOR THE OPPORTUNITY TO
SPEAK TO YOU. WHAT I’M GOING TO
TALK ABOUT HERE HAS ALREADY BEEN
DISCUSSED IN BRENDA’S
PRESENTATION BUT LET’S GO OVER
IT. WHERE WE’RE AT IN OUR NEPA
COMPLIANCE, A LONG TIME AGO IN
SEPTEMBER 2020 WE SENT OUT
REQUESTS FOR COOPERATING
AGENCIES, THE ONLY AGENCY THAT
ACCEPTED WAS EPA SO THEY ARE
CONTRIBUTING AS A COOPERATING
AGENCY IN THIS STUDY. BETWEEN
DECEMBER 17TH AND FEBRUARY 14TH
WAS OUR COMMENT PERIOD FOR OUR
INITIAL DOCUMENT THAT WE
RELEASED, AND BASED ON COMMENT
THAT WE RECEIVED FROM THAT
DOCUMENT, WE CHANGED THE DESIGN
A LITTLE BIT THAT REQUIRED US TO
RERELEASE, AGAIN, IN APRIL 26,
2023 TO JUNE 16TH, 2023 WE HAD
THE COMMENT PERIOD ON OUR SECOND
DOCUMENT THAT WE SENT OUT TO THE
PUBLIC THAT ADDRESSED THE SHIFT
IN ALIGNMENT THAT WE SHOWED YOU,
AND IT ADDRESSED SOME NEW
REQUIREMENTS THAT WE HAD TO DO,
WE HAD TO — THE 50 DOCUMENT
DIDN’T REQUIRE GUIDANCE DURING
THE FIRST DOCUMENT DIDN’T
REQUIRE US TO ANALYZE GREENHOUSE
GAS IMPACTS AND THE DOCUMENT NOW
CONTAINS ANALYSIS OF THAT.
AND THAT BRINGS US TO WHERE WE
ARE AT NOW. AND THEN WE ARE IN
THE FINAL PROCESSES OF
ADDRESSING COMMENTS, PUBLIC
COMMENT AND AGENCY COMMENTS, AND
FINALIZING THE DOCUMENT. AND IN
JANUARY, HOPEFULLY ON THE 17th,
WE’LL TRANSMIT THAT TO OUR SOUTH
PACIFIC DIVISION, WHICH IS THE
NEXT LEVEL ABOVE US, AS A FINAL
REPORT. AND SOMETIME AFTER —
THAT’S — AND IN THE PROCESS
THAT THEY TALKED ABOUT GETTING
AWARDED AUTHORIZATION, HOPEFULLY
IN 2024, AND AFTER THAT TIME,
WE’LL BE COMING BACK FOR A PHASE
TWO CONSISTENCY DETERMINATION
ONCE WE HAVE ADDITIONAL
INFORMATION WE’LL HAVE MORE
DETAILED SEDIMENT
CHARACTERIZATION, WE’LL HAVE
MORE DETAILED ENGINEERING
INFORMATION, AND WE’LL HAVE DONE
SOME FURTHER COORDINATION WITH
SOME OF THE AGENCIES. OKAY.
GO AHEAD BRENDA.
SO, THE COMMENTS WE RECEIVED
THROUGH THE BOTH OF THESE
COMMENT PERIODS, SOME OF THEM
WERE FAIRLY CONSISTENT AND FROM
NUMEROUS GROUPS, ESPECIALLY WITH
RELATION TO THE NOTION OF DOING
AN EA, INSTEAD OF AN EIS. AND
IN CONCERT WITH THAT, THE
DECISION NOT TO COMBINE THE
DOCUMENTS IN AN EA EIR.
AND WE DECIDE THAT WE WERE ON
THE RIGHT PATH, THAT THE
DOCUMENT, WE DIDN’T HAVE ANY
SIGNIFICANT IMPACTS THAT WEREN’T
MITIGABLE. SIMILAR IMPACTS TO
AIR QUALITY SIMILAR TO TRUCK
TRAFFIC AND THE PERCEPTION THAT
THIS PROJECT IS GOING TO INDUCE
GROWTH AND INCREASE THE TRUCKS
GOING THROUGH THEIR
NEIGHBORHOODS, THAT WAS STILL
WHAT WE’RE WORKING THROUGH WITH
THE OAKLAND NEIGHBORHOOD GROUPS,
ESPECIALLY THE INDICATOR
PROJECT.
THERE WERE CONCERNS ABOUT
IMPACTS TO WATER QUALITY.
TIMING, WE GOT SOME COMMENTS.
BECAUSE THE PORT IS STILL
ELECTRIFYING THINGS, MOST FAST
AS THEY CAN, AND THEY’RE ASKING
US TO DELAY THE PROJECT INTO THE
FUTURE ONCE EVERYTHING’S
ELECTRIC. THERE WERE COMPLAINTS
THAT WE WEREN’T ENGAGING WITH
THE PUBLIC SUFFICIENTLY. SOME
PEOPLE ASKED US ONLY DO THE
OUTER HARBOR TURNING BASIN.
THERE WAS SUPPORT FOR THE
PROJECT FROM A NUMBER OF GROUPS
AND PEOPLE WERE VERY HAPPY THAT
WE WERE COMMITTING TO BENEFICIAL
USE OF EVERYTHING THAT WE COULD.
AND THE SUPPORT FOR THE USE OF
ELECTRIC DREDGING WHICH REDUCES
THE AIR QUALITY IMPACTS OF
CONSTRUCTION OF THE PROJECT.
RESPONSES WILL BE INCLUDED IN
THE DOCUMENTS THAT WE’RE
FINALIZING NOW, AND WE’LL HAVE
ADDITIONAL COORDINATION THAT
I’LL TALK ABOUT IN A LITTLE BIT
THAT WILL BE CONDUCTED IN THE
FUTURE. GO AHEAD, BRENDA.
SO THESE AREN’T REALLY
MITIGATION MEASURES, BUT
AVOIDANCE AND MINIMIZATION
MEASURES THAT WE WILL BE USING.
IF YOU LOOK AT THE APPENDIX,
THIS IS A LONG LIST BUT BRIEF
VERSION OF THAT. RELATED TO
PILE DRIVING, PLACING BULK HEADS
IS GOING TO REQUIRE SHEET PILE
DRIVING, AND WE’RE COMMITTED TO
USING VIBE TORE METHODS FOR THAT
WHICH PRODUCES LESS NOISE AS
MUCH AS POSSIBLE. IT WON’T BE
POSSIBLE FOR EVERYTHING BUT
WE’LL TRY TO MINIMIZE THE
IMPACT. WE’LL BE USING NOISE
ATTENUATION MEASURES FOR IN
WATER NOISE, SO THE BIOLOGICAL
ACOUSTICAL MONITORING AND NOTION
OF USING SOME NOISE — I’M
TRYING TO REMEMBER THE TERM —
>>SPEAKER: DAMPENING.
>>SPEAKER: THANK YOU BRENDA
WE’LL BE COORDINATING WITH THE
PHASE 2C D FOR MARINE MAMMAL
IMPACTS, AND THERE WILL BE HOW
MANY PILES AND LOCATIONS AND
WE’LL GET INTO THAT WITH NOAA
AND WE’LL DEVELOP SOME
REQUIREMENT FOR THE PROJECT TO
PROTECT MARINE MAMMAL
POPULATIONS. WE’LL BE DOING EEL
GRASS SURVEYS IN THE OUTER
HARBOR, THERE IS EEL GRASS
FAIRLY CLOSE TO BE DOING
DREDGING SOLELY PRE AND POST
SURVEY AND SOME LIGHT MONITORING
LIKE WE NORMALLY DO FOR O&M IN
THAT AREA WE’LL BE USING CLAM
SHELL BUCKETS WE WON’T BE DOING
HYDRAULIC DREDGING. THE TUG
MOVEMENT NIGHT TIME ISN’T
CORRECT. WE WERE CONSIDERING
THAT BUT IT TURNS OUT THAT’S NOT
NECESSARY. THAT HAD TO DO WITH
NOISE IN ALAMEDA DURING THE
NIGHT TIME, BUT IT TURNED OUT
THAT SLIPPED IN THERE IT’S NOT
SUPPOSED TO BE THERE. THERE
WERE VARIOUS VMTS FOR REDUCING
PARTICULATE EMISSIONS AND
FUGITIVE DUST. BUT KEEPING A
LOW SPEED LIMIT, LIMITING IDLING
TIME FOR TRUCKS, AS THEY’RE
WAITING FOR STUFF TO LOAD AND
UNLOAD. AND REQUIRING THAT ALL
THE CONTRACTORS USE EQUIPMENT
THAT MEET CARB’S CERTIFICATION
STANDARDS, THINGS LIKE TIER FOUR
ENGINES AND THINGS LIKE THAT.
BUT I SHOULD SAY HERE THERE ARE
SOME MITIGATION MEASURES THAT
ARE REDUCING IMPACTS TO LESS
THAN SIGNIFICANT, AND THOSE ARE
THE ONES THAT PEOPLE ARE
PROBABLY MOST INTERESTED IN, AND
THAT WOULD BE THE USE OF SILT
CURTAINS WHICH IS PROBABLY NOT
ON THIS SLIDE, BUT TO PREVENT
EXPOSURE TO MARINE FAUNA, TO
SUSPENDED SEDIMENTS AND TO
POTENTIAL CONTAMINANTS THAT MAY
BE CONTAINED IN THERE, IN THE
AREAS WHERE WE EXPECT
CONTAMINATED MATERIALS TO BE,
WE’LL BE DOING THE DREDGING
BEHIND A SILT CURTAIN. THE
OTHER ONE WOULD BE SIGNIFICANT
WITHOUT MITIGATION WOULD BE THE
PILE DRIVING, THE NOISE IMPACTS
FROM THAT, BUT WE’LL BE
DEVELOPING BUBBLE CURTAINS AND
APPROPRIATE DISTANCES WHEN WE
COORDINATE. AND THE OTHER ONE
IS AGREEING TO COMPLY WITH THE
LTMS WINDOW THAT IS ESTABLISHED
FOR AT LEAST IN WATER DREDGING
FOR PROTECTION OF AQUATIC
SPECIES. SO WE HAVE COMMITTED
TO CONFORMING WITH THAT, AS
WELL. OKAY. THAT’S IT.
BRENDA.
SO, THIS IS KIND OF A RECAP OF
WHAT WE ALREADY TALKED ABOUT.
WE’RE LOOKING TO GET OUR
CONGRESSIONAL APPROVAL IN
JANUARY OF 2024 AND
PRECONSTRUCTION, WE’RE GOING
INTO OUR PRECONSTRUCTION
ENGINEERING AND DESIGN, WHERE WE
FINALIZE THE TECHNICAL
INFORMATION AND DEVELOP A FULL
DESIGN, AND WE’LL COME BACK TO
BCDC FOR OUR PHASE TWO
DETERMINATION ONCE WE HAVE
ENOUGH INFORMATION ABOUT 35%.
WE ASSUME THAT WILL BE IN 2026
COULD BE AS EARLY AS 2025 WE
HOPE TO GO TO CONSTRUCTION IN
JULY OF 2027 THAT WOULD RUN INTO
OCTOBER OF 2029. THANK YOU,
BRENDA.
>>SPEAKER: THANK YOU ERIK AND
ERIKA.
>>SPEAKER: I WANT TO SAY FOR
THE RECORD, ON THAT SLIDE WHERE
WE SAY MITIGATION MEASURES, FOR
THE RECORD, IT’S MINIMIZATION.
SO WE’LL MAKE THAT CORRECTION ON
THE POWERPOINT BEFORE WE SUBMIT
IT, IF THAT’S OKAY.
>>BRENDA GOEDEN: ABSOLUTELY.
THANK YOU FOR YOUR PRESENTATION.
I WANT TO MENTION ONE THING I
ACCIDENTALLY OMITTED AT THE
OPENING OF MY STATEMENTS, THE
PORT AND CITY OF ALAMEDA, THE
STAFF MET WITH THE CITY OF
ALAMEDA AND PORT OF OAKLAND AND
ARMY CORP REGARDING SOME
CONCERNS AFTER THE STAFF SUMMARY
WAS SENT OUT, AND AS A RESULT
BOTH ENTITIES PROVIDED SOME
IMPROVED LANGUAGE FOR US. THE
PORT OF OAKLAND INCLUDED SOME
VERY EXTENSIVE LANGUAGE WHICH WE
SUMMARIZED IN AN ADDENDUM AND
ATTACHED ERRATA SHEET THAT WAS
SENT OUT TO THE COMMISSIONERS AT
10:00 A.M. THIS MORNING SO IT IS
IN YOUR COMMISSION PACKET. AND
THE CITY OF ALAMEDA INFORMATION
IS INCLUDED SPECIFICALLY
REGARDING THE ALAMEDA LANDING
AREA. I WANTED TO POINT OUT TO
THE COMMISSION THAT WE DO
APPRECIATE ALL THREE ENTITY COME
TOGETHER TO HELP US CLARIFY AND
IMPROVE THE STAFF SUMMARY WHERE
WE HAD SOME CLARITY NEEDS AND
MISUNDERSTANDINGS OF PARTS OF
THE PROJECT. SO I JUST WANT TO
THANK THEM FOR THAT. AND WITH
THAT, CHAIR WASSERMAN, I WILL
GIVE THE MEETING BACK TO YOU.
>>CHAIR, ZACHARY WASSERMAN:
THANK YOU FOR THE PRESENTATION.
I WILL NOW OPEN THE PUBLIC
HEARING. ANY MEMBERS OF THE
PUBLIC WHO WOULD LIKE TO MAKE A
PUBLIC COMMENT, PLEASE LINE UP
AT THE PODIUM OR RAISE YOUR HAND
IN ZOOM. WE WILL START WITH
THOSE IN THE ROOM. REYLINA, DO
WE HAVE ANY IN THE ROOM
>>CLERK, REYLINA RUIZ: NO
PUBLIC COMMENT IN THE ROOM.
>>CHAIR, ZACHARY WASSERMAN: HOW
ABOUT ON ZOOM?
>>CLERK, REYLINA RUIZ: YES.
ALAN TAI. PLEASE UNMUTE
YOURSELF.
>>SPEAKER: CAN YOU HEAR ME?
>>CHAIR, ZACHARY WASSERMAN:
YES.
>>SPEAKER: GOOD AFTERNOON,
CHAIR WASSERMAN AND MEMBERS OF
THE COMMISSION. MY NAME IS ALAN
TAI, I AM THE PLANNING BUILDING
AND TRANSPORTATION DIRECTOR OF
THE CITY OF ALAMEDA WHERE A
PORTION OF THIS PROJECT IS
LOCATED. THE CITY OF ALAMEDA
WANTS THE COMMISSION TO BE WAIR
THAT THE PROJECT IS SUBJECT TO
OUR LOCAL DISCRETIONARY
APPROVALS. THE PROPERTY THAT’S
AFFECTED BY THE PROJECT FALLS
WITHIN THE CITY OF ALAMEDA’S
ALAMEDA LANDING MASTER PLAN
AREA. THE PROPOSED PROJECT
WOULD REMOVE SIX ACRES OR A
THIRD OF THE 18 ACRES THAT THE
CITY HAS PLANNED FOR EMPLOYMENT
LANDS AND THAT’S PART OF THE
MASTER PLAN. SO WE BELIEVE THE
PROJECT IS INCONSISTENT WITH OUR
LOCAL MASTER PLAN AND WILL
REQUIRE A MASTER PLAN AMENDMENT.
AND THAT ACTION IS SUBJECT TO
APPROVAL BY OUR ALAMEDA CITY
COUNCIL. THE CITY ALSO HAS MANY
CONCERNS ABOUT THIS PROJECT ON
MATTERS NOT WITHIN THE BCDC
JURISDICTION, BUT THE PROPERTY
— I’M SORRY — THE PROJECT’S
LACK OF FLOOD AND SEA LEVEL RISE
PROTECTIONS AND WATERFRONT
PUBLIC ACCESS, WHICH ARE WITHIN
THE COMMISSIONS REGULATORY AND
POLICY SCOPE AND AUTHORITY, AND
THE CITY RESPECTFULLY ASKS THE
COMMISSION AND BCDC STAFF TO
TAKE THE CITY’S CONCERNS INTO
CONSIDERATION FOR YOUR UPCOMING
ACTIONS ON THIS PROJECT. THESE
COMMENTS ARE REFLECTED IN A
LETTER ADDRESSED TO YOU BY OUR
MAYOR AZZY ASH CONTRACT AND IS
INCLUDED IN YOUR MEETING
MATERIALS. THANK YOU FOR THE
OPPORTUNITY TO SPEAK ON THIS
ITEM.
>>CLERK, REYLINA RUIZ: MIKE
JACOB. PLEASE UNMUTE YOURSELF.
>>SPEAKER: HI I’M MIKE JACOB
WITH PACIFIC MERCHANT SHIPPING
ASSOCIATION WE REPRESENT
TERMINAL OPERATORS DOING
BUSINESS AT PORT OF OAKLAND AND
OBVIOUSLY WE SUPPORT THE
CONSISTENCY DETERMINATION
REQUEST FROM THE ARMY CORP AND
SUBMITTED COMMENTS IN WRITING.
AND JUST FOR THE PURPOSE OF THIS
AND TO EXPAND ON SOME OF THE
COMMENTS YOU HEARD FROM THE PORT
AND THE ARMY CORP WITH RESPECT
TO ISSUES REGARDING GROWTH AND
AIR QUALITY. I THINK IT’S WORTH
MENTIONING THAT THE ISSUES FOR
US ARE NOT THAT THE PORT WILL OR
WILL NOT GROW WITH RESPECT TO
THE PROJECT. THE QUESTION IS
WHETHER OR NOT THE PORT WILL
GROW SAFELY, AND WHETHER OR NOT
WILL GROW CONSISTENT WITH THE
TERMS OF OTHER PORTS THAT ARE ON
OUR SAME VESSEL STRINGS AND DO
SO IN A WAY WHICH REDUCES COST
AND INCREASES EFFICIENCY. MAYBE
THE ANALOGY BEST USE IS WHEN YOU
THINK OF A VESSEL STRING PER
CONTAINER LINES LIKE A BUS
SERVICE WE SET UP A ROUTE AND
SERVICE THAT ROUTE FOR OUR
CUSTOMERS AND CUSTOMERS THEN
WILL MAKE DECISIONS ABOUT
IMPORTS AND EXPORTS BASED ON
THOSE SERVICES. THE SIZE OF THE
BUS THAT SERVES THAT ROUTE,
WHETHER IT’S A SMALL BUS, A
LARGE BUS, DOUBLE DECKER BUS,
DOESN’T MATTER IF YOU HAVE TO
GET FROM PLACE A TO PLACE B.
AND IT’S SIMILAR FOR US. YOU
BOOK CARGO, BECAUSE YOU HAVE A
BUSINESS IMPERATIVE TO IMPORT OR
EXPORT CARGO. IT DOESN’T MATTER
TO THE IMPORTER OR EXPORTER THE
SIZE OF THE VESSEL THAT COMES
AND DOES THAT WORK. BUT IT DOES
MATTER TO US, AS THE OCEAN
CARRIER, WHEN YOU HAVE LARGER
VESSELS, YOU HAVE HIGHER
EFFICIENCY, LESS FUEL, AND
BECAUSE YOU’RE BURNING LESS FUEL
PER BOX, YOU’RE ACTUALLY
DECREASING EMISSIONS PER UNIT,
AND OVERALL. WE WANT TO BRING
IN THE LARGER VESSELS. WE WANT
TO BRING IN THE MOST EFFICIENT
VESSELS AND THE NEWEST VESSELS
AND HAVE THEM IN THOSE STRINGS.
AND THAT IS AT THE CORE OF WHY
THIS IS IMPORTANT FOR US, FROM A
COMMERCIAL POINT OF VIEW, IN
ADDITION TO THE REST OF THE
ISSUES WITH RESPECT TO SAFETY.
WE LOOK FORWARD TO PARTICIPATING
IN ADDITIONAL CONVERSATIONS ON
THIS PROJECT, BUT IT’S
IMPERATIVE THAT THIS MOVE
FORWARD. AND WE APPRECIATE YOUR
CONSIDERATION.
>>CLERK, REYLINA RUIZ: KATRINA
THOMAS. PLEASE UNMUTE YOURSELF.
>>SPEAKER: I’M KATRINA THOMAS
WITH EARTH JUSTICE ALONGSIDE
WITH WEST OAKLAND ENVIRONMENT AT
INDICATOR’S PROJECT HAS BEEN
ENGAGING ON THIS PROJECT,
COMMENTING TODAY TO URGE BCDC TO
REJECT THE CORP REQUEST FOR
CONSISTENCY DETERMINATION
BECAUSE THE CORP HAS NOT
CONDUCTED EQUITABLE OUTREACH AND
THE PUBLIC ENGAGEMENT ABOUT
IMPACTED COMMUNITY MEMBERS NOR
HAS THE COURT ADDRESSED
COMMUNITY CONCERNS CLEARLY
IDENTIFIED MITIGATION FOR
PROJECTS IMPACTS WHILE
ACKNOWLEDGING THE COURT HAS HELD
PUBLIC MEETINGS ON THIS PROJECT
NONE HAVE CONSISTED OF A
DIALOGUE AND THE COURT HAS NOT
ENGAGED IN COMMUNITY STAKEHOLDER
CONVERSATION ABOUT THE PROJECTS
DURING DRAFTING OF ITS ANALYSIS
TO IDENTIFY MITIGATION MEASURES.
THAT DOES NOT LIVE UP TO THE
COMMITMENTS IN THE WEST OAKLAND
COMMUNITY ACTION PLAN OR BIDEN
ADMINISTRATION’S RECENTLY
ADOPTED EXECUTIVE ORDERS
REQUIRING AGENCIES THAT INVEST
IN INFRASTRUCTURE DEVELOPMENT TO
ALSO IMPLEMENT STRATEGIES THAT
WILL YIELD EQUITABLE OUTCOMES
FOR UNDERSERVED COMMUNITIES.
THE COURT’S FAILURE TO
COORDINATE THE ENVIRONMENTAL
REVIEW WITH THE PORT HAS LEFT
COMMUNITY MEMBERS IN THE DARK
WITH INCOMPLETE INFORMATION AND
THE COMERY CORP DATA ANALYSIS
DIDN’T FIND SIGNIFICANT IMPACTS
BUT THE PORT OF OAKLAND AND CEQA
REVIEW CONCLUDES THE PROJECT
WOULD HAVE SIGNIFICANT
UNAVOIDABLE IMPACTS TO NEARBY
COMMUNITIES EVEN ARCH PROPOSED
MITIGATION. THE FAILURE TO
COORDINATE HAS LEFT QUESTIONS
ENTIRELY UNANSWERED. I ALSO
WANT TO NOTE THE ENVIRONMENTAL
ANALYSIS OF ALL IMPACT AREAS
INCLUDING WATER QUALITY AND
BIOLOGICAL RESOURCE IMPACT. WE
DON’T KNOW WHAT THE PROJECT
IMPACTS WILL BE AS MORE SHIPS
BEGIN TO VISIT. ALSO BECAUSE
CORE CONSTRAINTS SCOPE OF
ANALYSIS IS LIMED TO ONE MILE
RADIUS FROM PROJECT SITE IT
DOWNPLAYS BOTH CONSTRUCTION AND
OPERATION IMPACTS TO WATER
QUALITY AND WILDLIFE IN THE BAY.
BCDC SHOULD REJECT THE REQUEST
FOR CONSISTENCY DETERMINATION
BCDC IS NOT BEHOLDEN TO INDUSTRY
INTEREST AND WE ENCOURAGE THE
COMMISSION TO LISTEN TO THE
COMMUNITY CONCERNS AND USE YOUR
AUTHORITY ON THIS PROJECT TO
PREVENT A HOST OF ENVIRONMENTAL
IMPACTS. THANK YOU.
>>CLERK, REYLINA RUIZ: ROBERT
ROGERS. PLEASE UNMUTE YOURSELF.
>>SPEAKER: GOOD AFTERNOON CHAIR
WASSERMAN AND MEMBERS OF THE
COMMISSION. THANK YOU FOR THE
OPPORTUNITY TO COMMENT. MY NAME
IS ROGER, AND I AM HERE ON
BEHALF OF THE BAY PLANNING
COALITION ALIGNING WITH THE
ORGANIZATIONS MISSION OF
PROMOTING ENVIRONMENTAL
SUSTAINABILITY AND ECONOMIC
DEVELOPMENT OF THE REGION BCDC
WOULD LIKE TO EXPRESS OUR
SUPPORT FOR THE OAKLAND TURNING
BASIN-WIDENING PROJECT BY
INCREASING EFFICIENCY AND
ENHANCING CAPABILITIES AT THE
PORT OF OAKLAND. THE PORT OF
OAKLAND GENERATES 98,340 LOCAL
JOBS AND IS THE SECOND LARGEST
JOB GENERATOR IN THE CITY OF
OAKLAND AND FIFTH LARGEST IN THE
REGION IT REMAINS CRITICAL
SOURCE OF ECONOMIC OPPORTUNITY
AND JOBS IN THE NORTHERN
CALIFORNIA MOREOVER VALUE
HIGHLIGHTS FROM BUSINESS REVENUE
CONSUMER SPENDING AND TOTAL
VALUE OF GOODS SERVICES THE PORT
ADDS $174 BILLION IN ECONOMIC
VALUE. THE PROPOSED PROJECT
WOULD IMPROVE NAVIGATIONAL
ACCESS FOR LARGER VESSELS. BY
OPTIMIZING OPERATIONS THE
PROJECT WILL SUPPORT A GREENER
FUTURE FOR OUR COMMUNITIES BY
REDUCING CONGESTION AND
MINIMIZING STAGNANT VESSELS THE
PORT OF OAKLAND IS A VITAL
ECONOMIC HUB FOR THE REGION AND
THE NATION. ALLOWING FOR THE
WIDENING OF THE TURNING BASIN
ENSURES PROSPERING ECONOMIC
CONDITIONS CONTINUE TO THRIVE I
WOULD LIKE TO THANK YOU FOR THE
OPPORTUNITY TO COMMENT ON BEHALF
OF THE BAY PLANNING COALITION.
>>CLERK, REYLINA RUIZ: SEAN
SWENDSEN. PLEASE UNMUTE
YOURSELF.
>>SPEAKER: YES, CAN YOU HEAR ME
ALL RIGHT?
>>CLERK, REYLINA RUIZ: YES.
YES.
>>SPEAKER: YES, MY CONCERN IS
VERY BRIEF. WE HEARD FROM THE
CITY OF ALAMEDA TODAY. I
BELIEVE HAS NAME IS ALAN TAI,
AND I’M WONDERING, HE REFERENCED
A LETTER THAT WAS WRITTEN BY THE
CITY OF ALAMEDA TO BCDC FOR
CONSIDERATION AS PART OF THIS
APPROVAL PROCESS, AND I WAS
WONDERING IF YOU WOULD BE SO
KIND AS TO INCLUDE THAT LETTER
IN THE BCDC’S PORTAL OF OTHER
DOCUMENTS RELATED TO THIS
APPROVAL PROCESS SO THAT THOSE
IN THE PUBLIC THAT WOULD LIKE TO
READ THE LETTER CAN ACCESS IT.
THAT’S ALL. THANK YOU.
>>CLERK, REYLINA RUIZ: EVEY,
PLEASE UNMUTE YOURSELF.
>>SPEAKER: HELLO. MY NAME IS
EVEY FONG, A MEMBER OF THE
CUSTOMS BROKERS FORWARDERS
ASSOCIATION OF NORTHERN
CALIFORNIA. I WANT TO SPEAK UP
TODAY AND OFFER SUPPORT FOR THE
TURNING BASIN PROJECT. THE
TURNING BASIN IS NECESSARY AND
RESPONSIBLE PROJECT TO ENSURE
THE PORT OF OAKLAND CONTINUES AS
AN ESSENTIAL WEST COAST GATEWAY
TO U.S. COMMERCE. WE, AT THE
PORT OF OAKLAND, IT IS
NECESSARY, AS A REGIONAL PORT
AND WITH THE LARGER COMMERCIAL
SHIPS, THIS WILL ENSURE THE
PORT’S FUTURE AS THE NECESSARY
REGIONAL PORT. DECISIONS MADE
TODAY WILL ENSURE CURRENT
CONTRACTS TO ENDURE AND SUCCEED
INTO THE FUTURE. THIS TURNING
BASIN WILL TAKE ABOUT TEN YEARS.
IT IS NECESSARY THAT THE
DECISIONS MADE WILL GO FORWARD
WITH THE PROJECT. THE FACT THAT
THE EXISTING CHANNEL AND TURNING
BASINS WERE LAST UPDATED 25
YEARS AGO, I THINK IT’S TIME TO
REDESIGN THE PORT INTO THE NEXT
25 YEARS. AND THEN LASTLY,
INFRASTRUCTURE. AS SAID FOR
CARB CONCERNS, THE TURNING BASIN
ACCOMMODATES FOR SHORE POWER
INFRASTRUCTURE IMPROVEMENTS AND
OTHER INFRASTRUCTURE NEEDED THAT
THE — ANY ENVIRONMENTAL
CONCERNS AND ELECTRIFICATION CAN
BE ACCOMMODATED. THOSE ARE GOOD
THINGS. AND THAT IS THE AIR
QUALITY MEASURES THAT ARE NOW
REQUIRED BY THE STATE. THIS
WILL BE SUSTAINABLE, COMPATIBLE
GROWTH FOR THE PORT AND CITY OF
OAKLAND. THANK YOU SO MUCH FOR
ALLOWING ME TO SPEAK TODAY.
>>CLERK, REYLINA RUIZ: SUNG
LEE. PLEASE UNMUTE YOURSELF.
>>SPEAKER: HELLO. THIS IS SUNG
LEE. I AM THE VICE CHAIR OF
NORTHERN CALIFORNIA DISTRICT
EXPORT COUNCIL. A PRIVATE
INDUSTRY ADVISORY GROUP
APPOINTED BY THE SECRETARY OF
RAI MONDO OF DEPARTMENT OF
COMMERCE ALSO REPRESENTING HERE
AS PRESIDENT OF NORTHERN
CALIFORNIA CUSTOM BROKERS AND
FREIGHT FORWARDERS ASSOCIATION
THAT CLEARS CUSTOMS AT THE
PORTS. WE’RE SUPPORTING THE
TURNING BASIN AT THE PORT OF
OAKLAND THE PROJECT IS DESIGNED
TO IMPROVE VESSEL TRANSIT
EFFICIENCIES AND NAVIGATIONAL
SAFETY AND WE FULLY SUPPORT THAT
MORE ALSO ENVIRONMENTAL BENEFITS
INCLUDING REDUCTION OF EMISSIONS
AT THE RATE OF GROWTH OF
EMISSIONS PER CONTAINER AND
DECREASING GHG EMISSIONS BY
BOATING CARGO, THE DIVERSION IS
ONE OF OUR GOALS. I WORK IN THE
CONTAINER SHIPPING INDUSTRY THE
SHIPPING COMPANIES THAT ARE
CALLING PORT OF OAKLAND ARE
PURCHASING PLACING ORDERS ON
NEWER AND CLEANER VESSELS THAT
IS GOING TO TAKE ADVANTAGE OF
THE LARGER TURNING BASIN THEY
WILL BE COMPLETED ABOUT THE SAME
TIME AS WHEN THE TURNING BASIN
IS COMPLETED SO WE LOOK FORWARD
TO HAVING THE CLEANER SHIPS CALL
OAKLAND THANK YOU VERY MUCH.
>>CLERK, REYLINA RUIZ: SUSAN
RANSOM.
>>SPEAKER: HI EVERYBODY, WITH
SSA TERMINAL IN OAKLAND FIRST I
WOULD LIKE TO THANK ALL THE
PARTIES FOR CONTINUING TO WORK
TOWARDS THE TURNING BASIN THE
DISCUSSIONS ARE GOOD IT’S
ESSENTIAL TO THE FUTURE OF
OAKLAND ECONOMIC ENGINE THAT
SUPPORTS EVERYONE NEAR AND FAR I
HAVE ALL DREDGING EQUIPMENT
NEEDED TO WIDENING THE DURING
BASIN WOULD BE ELECTRIC AND SOIL
WOULD BE REPURPOSED. AS FAR AS
ADDITIONAL CONTAINER TRAFFIC
THAT WOULD BE DICTATED BY THE
MARKETPLACE. THE TURNING
PROJECT CHANGES THE NUMBER AND
TYPE OF SHIPS FACILITATING THAT
COMMERCE. THIS WON’T BE BRING
MASSIVE ADDITIONAL CONTAINERS IT
WILL CONSOLIDATE CARGO WITH
OLDER SMALLER SHIPS BEING
DEPLOYED ELSEWHERE AND THE NEWER
LARGER SHIPS WILL BE MORE
ENVIRONMENTALLY CLEAN COMING
INTO THE PORT ALL OF THE MARINE
TERMINALS IN THE PORT ITSELF ARE
COMMITTED TO DOING BUSINESS
ZERO-EMISSIONS. KEEP IN MIND
THE WIDER THE TURNING BASIN THE
SAFER AND FASTER SHIPS TURN IT’S
A WIN-WIN FOR THE ENVIRONMENT
AND ECONOMY. IN ADDITION TO
MANDATES AND REGULATIONS
CALIFORNIA IS PUTTING ON
TRUCKING COMPANIES TO BE RUNNING
0 EMISSIONS, IT’S LIKELY THAT
THE INDUSTRY WILL LOSE ABOUT 25%
OF TRUCK CAPACITY AS MANY WON’T
BE ABLE TO AFFORD THE NEW TRUCKS
SO THERE WILL BE LESS TRAFFIC
OVERALL AND LESS POLLUTION NOT
MORE. ALREADY INVESTING
MILLIONS OF DOLLARS GETTING TO
THE GOAL OF ZERO EMISSIONS AND
VESSELS ARE ALREADY PLUGGING
INTO SHORE POWER ELIMINATING
NEED FOR DIESEL GENERATORS AT
THE PORTS WE HAVE AN
ENVIRONMENTAL TEAM WITHIN OUR
COMPANY WORKING ENDLESSLY WITH
THE PORT AND ALL OTHERS TO MEET
CHALLENGES OF NEW CALIFORNIA
REGULATIONS WE ARE NOT DONE BY
FAR BUT ARE CONTINUING TO
ADVANCE THE GOAL. WE ARE
CRITICAL PARTNERS INCLUDING THE
PORT OF OAKLAND AND ASK THAT IT
BE ACKNOWLEDGED THAT BY THE TIME
THIS PROJECT BREAKS GROUND WE’LL
BE ONE OF THE CLEANEST PORTS IN
THE WORLD. THANK YOU VERY MUCH.
>>CLERK, REYLINA RUIZ: NO
FURTHER PUBLIC COMMENT.
>>CHAIR, ZACHARY WASSERMAN:
THANK YOU, ALL, FOR THAT.
I WOULD NOW ENTERTAIN A MOTION
TO CLOSE THE PUBLIC HEARING AND
A SECOND, PLEASE?
>>SPEAKER: SECOND.
>>CHAIR, ZACHARY WASSERMAN:
VICE CHAIR MOVES. AND I’M
SORRY. WHO SECONDED?
OH I SEE SEVERAL HERE. I’LL
TAKE COMMISSIONER GUNTHER’S
SECOND.
THANK YOU VERY MUCH.
PLEASE RAISE YOUR HAND IF YOU
AGREE TO CLOSE THE PUBLIC
HEARING. ANYBODY OPPOSED TO
CLOSING THE PUBLIC HEARING?
PUBLIC HEARING IS NOW CLOSED.
THANK YOU ALL VERY MUCH.
WE WILL NOW ENTERTAIN COMMISSION
QUESTIONS AND COMMENTS.
I’M GOING TO RECOGNIZE
COMMISSIONER EISEN FIRST, AND
THEN I’LL GO TO THE SCREEN.
>>V. CHAIR, REBECCA EISEN: I
HAVE A LOT OF QUESTIONS. I
DON’T KNOW EXACTLY WHO TO DIRECT
THEM TO. AND I DON’T KNOW IF
THEY’RE PREMATURE. BUT THERE
WAS A DISCUSSION ABOUT PUBLIC
ACCESS AND, OF COURSE, MIDDLE
HARBOR SITS BETWEEN THESE TWO
TURNING BASINS. AND MIDDLE
HARBOR IS THE BIGGEST AREA OF
PUBLIC ACCESS THAT OAKLAND HAS.
I WAS THERE A WEEK AGO, BECAUSE
IT’S A MASSIVE BIRDING
DESTINATION, AND THE — I DON’T
KNOW IF THIS IS RELATED IN ANY
WAY, SHAPE, OR FORM, BUT ALL OF
THE VEGETATION HAD BEEN REMOVED
FROM MIDDLE HARBOR. AND I DON’T
KNOW HOW THAT IS GOING TO BE
IMPACTED BY THIS — WHAT SOUNDS
LOOK A VERY LARGE PROJECT,
WHETHER IT’S GOING TO BE
EXPANDED IN TERMS OF PUBLIC
ACCESS ON OR WHETHER IT’S GOING
TO BE — WE HAVE TALK ABOUT IT
BEFORE ON THE COMMISSION, THAT
IT IS A SAD AND UNHAPPY PLACE,
AND THAT THERE WAS COMMITMENTS
BY THE PORT OF OAKLAND AND
OTHERS THAT THEY WOULD IMPROVE
IT. SO, I’M NOT — I REALLY
WOULD LIKE TO UNDERSTAND WHAT
HAPPENS TO MIDDLE HARBOR IN THE
MIDST OF THIS ENTIRE PROJECT.
THAT’S NUMBER ONE. AND, SORT
OF, RELATED, I HEARD FROM ONE OF
THE PRESENTERS THAT ONE OF THE
MITIGATION MEASURES IS TO AVOID
DOING CONSTRUCTION DURING BIRD
BREEDING SEASON. I WONDER WHO
IS GOING TO HELP DETERMINE WHEN
THAT IS AND WHAT KIND OF IMPACT
THAT HAS ON THE PROJECT.
BECAUSE JUST NOT CONSTRUCTING AT
ALL DURING BIRD BREEDING SEASON
IS GOING TO BE, YOU KNOW,
COSTLY, AND DIFFICULT TO
SCHEDULE. SO, I REALLY WANT TO
UNDERSTAND THAT.
BRENDA MENTION THAT WE NEED TO
DECIDE NEXT MEETING SO WE CAN
CONCUR AND THAT CAN BE ATTACHED
TO THE CHIEF’S STATEMENT, I
THINK WAS THE EXPRESSION. AND I
WONDER IF THE CHIEF’S STATEMENT
IS WHAT NEEDS TO BE SUBMITTED TO
CONGRESS, BECAUSE THE TIMELINE
SAYS THAT WE’RE GOING TO BE
ASKING — THE ARMY CORP IS GOING
TO BE ASKING CONGRESS FOR, I
GUESS, VOTE ON THIS IN JANUARY,
WHICH IS JUST TWO WEEKS AWAY.
SO, AND ONLY TEN DAYS AWAY FROM
OUR NEXT MEETING. I’M WONDERING
WHAT THE ANSWER IS TO THE
QUESTION ABOUT WHY WE NEED TO
EXPAND BOTH TURNING BASINS, WHY
IT ISN’T SUFFICIENT JUST TO
EXPAND THE ONE THAT’S IN THE
OUTER HARBOR AND NOT THE ONE
THAT’S IN THE INNER HARBOR. AND
MAYBE ALL OF THIS IS GOING TO BE
ANSWERED AT OUR NEXT MEETING?
OR MAYBE IT IS NOT NECESSARY FOR
US TO HAVE ANSWERS TO THESE
PRIOR TO OUR DECISION ON WHETHER
TO CONCUR. THERE IS A LOT OF
COMMENT ABOUT HOW THIS IS GOING
TO BE BENEFICIAL FOR SAFETY
REASONS AND FOR ENVIRONMENTAL
REASONS BUT IT’S NOT NECESSARILY
GOING TO CHANGE, SORT OF, THE
ECONOMICS. BUT I REALLY DON’T
UNDERSTAND SOME BASIC THINGS. I
MEAN, HOW MUCH GROWTH IN THESE
LARGER SHIPS ARE WE SEEING? IS
IT EXPECTED TO CONTINUE? AND
FOR HOW LONG? SO THAT THAT,
SORT OF, DATA, WHETHER THIS IS
REALLY A NECESSARY PROJECT, I
DON’T HAVE THAT. MAYBE IT’S IN
SOME DOCUMENTS, MAYBE SOMEONE
CAN POINT ME TO IT. WITH THAT I
HAVE EXHAUSTED MY TIME ASKING
QUESTIONS
>>CHAIR, ZACHARY WASSERMAN:
WE’LL WORK ON ANSWERS.
>>SPEAKER: I’LL TAKE THE EASY
ONE. THERE WAS A QUESTION ABOUT
WHEN IT’S GOING TO CONGRESS.
RIGHT NOW THE REPORT IS BEING
FINALIZED AND IT’S GOING TO
HEADQUARTERS IN JANUARY AND THEN
THE CHIEF’S REPORT IS COMPLETED
AND SUBMITTED IN MAY, END OF
MAY, 2024, TO CONGRESS. YEAH,
THE CHIEF’S REPORT THAT GOES TO
CONGRESS.
>>V. CHAIR, REBECCA EISEN: I’M
PRETTY SURE THAT I SAW THAT IT
WAS ON JANUARY ON THE SLIDE.
>>SPEAKER: I THINK IT WAS
INCORRECT, AS WELL. YEAH. SO
IT STARTS — ONCE WE SUBMIT IT
TO HEADQUARTERS IT, SORT OF,
STARTS THAT PROCESS OF GETTING
IT TO — GETTING THE CHIEF’S
REPORT PREPARED AND SUBMITTING
TO CONGRESS FOR CONGRESSIONAL
APPROVAL. WE’LL MAKE A
CORRECTION ON THAT POWERPOINT.
SO THAT WAS THE EASY ONE. ON
THE ENVIRONMENTAL ONE, REGARDING
THE BIRD NESTING SEASON, I’LL
LET ERIK THEN ON THE ECONOMICS
WE’LL BRING JUSTIN UP TO ANSWER
THAT QUESTION. AND ALL OF THIS
IS IN THE REPORT.
>>SPEAKER: YEAH, WE HAVE THE
RESTRICTION ON TIMING FOR BIRDS
WAS RELATED TO PILE DRIVING
ONLY. IT WAS ONLY IN THE
PILE-DRIVING MEASURES. WE’RE
GOING TO ATTEMPT TO STAY WITHIN
THAT WINDOW, THE ONLY BIRDS WE
WOULD BE COMING INTO CONTACT
WITH FROM A NESTING STANDPOINT
AT HOWARD TERMINAL WOULD BE
POTENTIAL PEREGRINE FALCONS THAT
WOULD BE IN THE CRANES BUT IT’S
HIGHLY INDUSTRIALIZED CONTAINERS
BEING MOVED AROUND BY TRUCKS ALL
OVER THE PLACE BUT IT’S IN
MOTION AND COMPLETELY PAVED AND
CONTAINED. WITH INTERRUPTING
FORGING OF SOME BIRDS, WE
BELIEVE IN OUR INNER AND OUTER
HARBOR BASINS ARE NOT PREFERRED
HABITAT FOR THE TURINS. THE
PROJECT SHOWED THAT THE MOST
OVERWHELMING LARGE AMOUNT OF
FORAGING HAPPENS SOUTH OF
ALAMEDA. THERE IS A BIG COLONY
IN ALAMEDA AT THE AIR FIELD
LARGEST COLONY IN NORTHERN
CALIFORNIA, LARGELY FORAGED
WITHIN THREE MILES SOUTH OF THE
ISLAND TOWARDS BAY FARM AND
THAT’S WHERE THE OVERWHELMING
AMOUNT OF THAT HAPPENS SINCE
IT’S NOW STARTING TO HAPPEN IN
THE MIDDLE ONCE WE CREATED THAT
HABITAT DURING THE 50 FOOTWORK.
WE’RE STILL WORKING ON MILL
HARBOR WE’RE DOING EEL GRASS
SURVEYS WE DID PLANTING LAST
YEAR AND ARE ANALYZING POTENTIAL
FOR ADDITIONAL PHASE TWO
PLANTING OF EEL GRASS. WE NEED
TO COMPLETE THE MARSH THAT’S IN
THAT CORNER THAT LOOKS
[INDISCERNIBLE] NOW, WE’RE
COMMITTED TO DOING SOME TIDAL
MARSH FOR INTERPRETATIVE
PURPOSES, AND WITH THE OAKLAND
COMMUNITY CAN COME AND SEE WHAT
THE MARSH IS SUPPOSED TO LOOK
LIKE. WHICH CROSSES BOTH
PROJECTS AT SHORELINE PARK AND
IT WILL ENHANCE THE AREA AND
WE’LL HAVE SOME OPTIONS TO FIX
THAT BEACH AND I CAN’T ANSWER
THE QUESTION ABOUT THE PLANTS IN
THE UPLAND AREAS SOMEBODY AT THE
PORT MIGHT KNOW THE ANSWER TO
THAT ONE.
>>JUSTIN TASCHEK: JUSTIN
TASCHEK, PORT OF OAKLAND I’LL
ADDRESS THE QUESTION RELATED TO
HASH BORE OUTER BASIN ONLY.
THERE ARE TWO TURNING BASINS AND
IT MIGHT HELPFUL TO PULL UP THE
PRESENTATION MATERIAL THAT DOES
HAVE THE SEAPORT OVERVIEW, IF
THAT COULD BE PULLED UP, FROM
BRENDA?
>>SPEAKER: WORKING ON IT. JUST
A SECOND.
>>SPEAKER: WHILE SHE’S DOING
THAT, I WANT TO MENTION HERE
EACH TURNING BASIN PROVIDES ITS
OWN UTILITY FOR TURNING BASINS
FOR THE OUTER HARBOR TURNING
BASIN AND PROPERTIES IN THE
INCARBON TURNING BASIN THESE
PROPERTIES ARE LEASED OUT THAT
OPERATES THE FACILITIES AND
THESE LEASES DO COMPETE FOR THE
BUSINESSES SO THE VESSELS WE
TALKED ABOUT THAT VISIT THE PORT
OF OAKLAND FULL-SIZED VESSELS,
GO TO BOTH THE OUTER AND INNER
HARBOR IT’S INTEGRAL AND
IMPORTANT TO REMAIN COMPETITIVE
THROUGHOUT THE ENTIRE PORT
COMPLEX TO ALLOW ALL VESSEL
SIZES TO VISIT ALL PROPERTIES
WITHIN THE PORT COMPLEX AS THOSE
ARE MARINE TERMINAL PROPERTIES.
BRENDA COULD YOU PULL UP THE ONE
BEFORE THAT?
>>SPEAKER: THAT ONE?
>>JUSTIN TASCHEK: THE SEAPORT
FIGURE THAT HAS ALL THE
DIFFERENT BOUNDARIES AND LIMITS,
I WOULD MENTION SUZANNE PROVIDED
PUBLIC COMMENT THEY DO OPERATE
THE LARGEST FACILITY IN THE PORT
OF OAKLAND KNOWN AS OAKLAND
INTERNATIONAL CONTAINER TERMINAL
IT IS RIGHT NOW MOVING GREATER
THAN HALF OF THE TOTAL VOLUMES
60% CATEGORY OF THE VOLUMES
THAT’S SERVED EXCLUSIVELY BY THE
INNER HARBOR TURNING BASIN IT’S
VERY IMPORTANT THAT WE DO
PROVIDE THAT COMPETITIVE
LANDSCAPE TO WIDEN BOTH THE
TURNING BASINS. THANK YOU.
BRENDA —
>>SPEAKER: I’M JUST
EMBARRASSING MYSELF AT THIS
POINT. THANK YOU.
>>JUSTIN TASCHEK: THANK YOU.
>>CHAIR, ZACHARY WASSERMAN:
COMMISSIONER ECKLUND?
>>PAT EKLUND: THANK YOU VERY
MUCH. FIRST OF ALL, FOR FULL
DISCLOSURE, I WANT TO MAKE SURE
THAT EVERYONE KNOWS THAT I DID
WORK FOR THE U.S. ARMY CORP OF
ENGINEERS FOR EIGHT YEARS, AND
AM VERY FAMILIAR WITH THE
DREDGING ISSUES. AND I ALSO
WORKED FOR THE U.S.
ENVIRONMENTAL PROTECTION AGENCY
FOR 35 YEARS WHERE AT ONE POINT
I WAS IN CHANGE OF THE NPDS
PERMITTING PROGRAM SECTION 404
WHICH DEALT WITH A LOT OF
DREDGING, AND A LOT OF OTHER
WATER RELATED ISSUES.
I HAVE A LOT OF QUESTIONS THAT
I’M GOING TO — WOULD LIKE TO
START OUT WITH A COUPLE OF THEM,
AND THEN ASK THAT WE HAVE AN
OPPORTUNITY TO SUBMIT WRITTEN
QUESTIONS — OR ASK WHEN WE CAN
ALSO SUBMIT WRITTEN QUESTIONS
AFTERWARD AND MAYBE GET SOME
ANSWERS BEFORE THE NEXT MEETING.
BUT WE CAN TALK ABOUT THAT
LATER. SO FIRST OF ALL, I AGREE
WITH THE SPEAKER REQUESTING A
COPY OF THAT LETTER OF THE
LETTER FROM THE CITY OF ALAMEDA.
I WOULD LIKE TO HAVE A BETTER
UNDERSTANDING ABOUT WHAT
ALAMEDA, CITY OF ALAMEDA’S
CONCERNS ARE. AND I’M NOT QUITE
SURE TO WHAT EXTENT, AND THIS IS
A QUESTION, DOES BCDC NEED TO
MAKE ANY TYPE OF A DECISION
WHERE THAT — THIS ACTION IS
ALSO GOING TO BE IN COMPLIANCE
WITH LOCAL — A NEARBY
JURISDICTION, OR A JURISDICTION
THAT’S GOING TO BE AFFECTED BY
THE ACTIVITY. SO, SHOULD WE —
IS IT REQUIRED THAT WE HAVE A
BETTER UNDERSTANDING OF WHAT THE
IMPACT IS GOING TO BE TO THE
CITY OF ALAMEDA? AND WHAT
REMEDIES ARE POSSIBLY AVAILABLE?
>>BRENDA GOEDEN: I CAN TAKE
THAT ITEM AS A STARTER AND
OTHERS CAN JOIN IN. THE LETTER
FROM THE CITY OF ALAMEDA IS
CURRENTLY POSTED ON OUR WEB SITE
UNDER THE SUPPLEMENTAL
INFORMATION IF YOU GO TO THE
AGENDA THAT’S THE SUPPLEMENTAL
INFORMATION THERE, WE RECEIVED
THREE PUBLIC COMMENTS WRITTEN
BEFORE THE COMMISSION MEETING.
SO THAT WAS ONE OF THEM. ALSO
THE ADDENDUM, WHERE I TRIED TO
EXPLAIN A LITTLE BIT BETTER SOME
OF THE INFORMATION WE DIDN’T GET
QUITE RIGHT IN THE STAFF SUMMARY
IS IN THERE. SO REGARDING THE
LOCAL DISCRETIONARY APPROVAL IN
THE CITY OF ALAMEDA. RIGHT NOW
WE’RE AT THE FEASIBILITY STAGE
SO THE CORP FINISHED THE STUDY
OF WHETHER OR NOT IT’S FEASIBLE
FOR THE FEDERAL GOVERNMENT TO
HAVE A PIECE IN THIS AND THEY
HAVE SAID YES FIRST PHASE
CONSISTENCY SO WE’RE LOOKING TO
FIND OUT NEXT MEETING AS THE
COMMISSION SEES THE PROJECT IS
GENERAL CONSISTENT WITH ITS LAWS
AND POLICIES NEPA — EXCUSE ME,
IT DOES REQUIRE THAT THE LAWS
AND POLICIES OF THE COMMISSIONER
MET AS PART OF THE FILL STILL
PART OF THE MCATEER-PETRIS ACT
THERE IS A REQUIREMENT FOR THE
FILL ON THE PROPERTY THAT THERE
IS PROPERTY INTEREST SO WE
CANNOT REQUIRE THE PORT OR CORP
— THE LOCAL SPONSOR THE CORP IS
REQUIRED TO GET THE LAND’S
EASEMENTS AND RIGHT OF WAY
BEFORE THE CORP CAN CONSTRUCT
THE PROJECT SO THAT MEANS THE
PORT OF OAKLAND HAS TO GET THOSE
PROPERTIES THEY WOULD GET THAT I
BELIEVE WORKING WITH THE CITY OF
ALAMEDA AND IN ORDER FOR US TO
ISSUE A PERMIT TO THE PORT OF
OAKLAND FOR THIS PROJECT OF
THEIR UPCOMING APPLICATION IN A
COUPLE OF YEARS, THEY WOULD HAVE
TO PROVIDE THE LOCAL
DISCRETIONARY APPROVAL AND THE
PROPERTY INTEREST BECAUSE THAT
PROJECT IS FULLY UNDER THE
MCATEER-PETRIS ACT AND THE BAY
PLAN AND OUR STATE AUTHORITY
VERSUS OUR FEDERAL AUTHORITY
UNDER CDMZMA. THAT WAS A LOT.
DOES IT MAKE SENSE?
>>PAT EKLUND: YEAH IT IF WE
TOOK ACTION AT THE NEXT MEETING
THAT WOULD STILL ALLOW US AS THE
TIME COMES BACK TO ADD SOME
ADDITIONAL CONDITIONS IF WE
WANTED TO HELP MITIGATE SOME OF.
>>ANDREW FREMIER: IMPACTS?
>>SPEAKER: YES AND WE WILL NOT
BE RECOMMENDING THAT WE ALLOW
THE PROJECT TO GO FORWARD WE
WILL NOT AUTHORIZE ANY WORK AT
THIS TIME SO IF WE DON’T HAVE
THOSE DETAILS.
>>PAT EKLUND: THAT HELPS ME A
LOT. THE OTHER ISSUE THAT IS
PROBABLY A LITTLE BIT LARGER AND
I’M ASSUMING THAT BCDC HAS AN
INTEREST IN IT I WORKED FOR U.S.
EPA, I PUSHED REALLY HARD, WE
TRIED TO SET UP A PROGRAM TO
REUSE THE DREDGE MATERIAL
BECAUSE AS YOU KNOW THERE’S NOT
ENOUGH DREDGE MATERIAL AVAILABLE
TO DO ALL THE WETLAND
INSPIRATION THAT’S NEEDED AROUND
SAN FRANCISCO BAY ESTUARY AREA,
AND SO I SAW IN THE REPORT
THEY’RE TALKING ABOUT NOT ONLINE
LOOKING TO REUSE THE MATERIAL
BUT I DIDN’T SEE SPECIFIC AREAS
OR WHETHER IT’S MARSH LANDS, I
SAW FILL, BUT I DIDN’T SEE ANY
WETLAND RESTORATION. YOU CAN
HELP ME TO UNDERSTAND WHERE THAT
MATERIAL MIGHT OR WHETHER IT HAS
BEEN DETERMINED BECAUSE I KNOW
THEY HAVE TO DO A LOT OF TESTING
FIRST.
>>SPEAKER: FOR BENEFICIAL REUSE
I THINK WE MENTIONED HERE
WETLAND RESTORATION, WE THINK
THEY MIGHT GO TO BENEFICIAL
DEEPER MATERIAL, IT HAS NOT BEEN
IMPACTED BY INDUSTRIAL ACTIVITY,
AND HAVE RECEIVED SUSTAINABILITY
DETERMINATION IN THE 1990S THAT
MATERIAL IS CLEAN ENOUGH TO GO
TO BENEFICIAL REUSE. I BELIEVE
THE PORT HAVE BEEN TALKING TO
MONTEZUMA WETLANDS BECAUSE THEY
CAN TAKE BOTH FOUNDATION AND
COVER QUALITY MATERIAL THAT IS
NOT DETERMINED YET BECAUSE WE’RE
NOT AT THAT LEVEL OF DESIGN, IF
BEL MARIN KEYS CAME ONLINE SOME
OF THE MATERIAL COULD GO THERE,
IF COLIN IS OPERATIONAL SOME OF
THE MATERIALS COULD GO THERE,
THERE IS SITES THAT MAY NOT HAVE
BEEN IDENTIFIED, BUT THERE IS
ANTICIPATION COMMITMENT FROM THE
CORP AND THE PORT THROUGH THEIR
BENEFICIAL — I’M NOT
REMEMBERING THE NAME — BUT THEY
DID APPROVAL TO TAKE MATERIAL TO
BENEFICIAL REUSE WE DO
ANTICIPATE THAT TO BE WETLANDS.
>>PAT EKLUND: IS IT GOING TO BE
100% I DON’T KNOW WHAT THE
PROPOSING REUSE FOR FILL VERSUS
WETLAND RESTORATION OR LEVELS OR
WHATEVER.
>>SPEAKER: SORRY THAT WAS NOT
CLEAR. FILL PROPOSED IS PILE
SHEET PILES RIP RAP, IT’S NOT
DREDGE MATERIAL. SORRY THAT WAS
NOT SUPER CLEAR.
>>PAT EKLUND: IS THERE ANY
DREDGE MATERIAL THAT’S BEING
PROPOSED FOR DUMPING IN THE BAY
OR IN THE OCEAN?
>>SPEAKER: NOT AT THIS TIME.
>>PAT EKLUND: DO WE HAVE A
REQUIREMENT THAT THEY HAVE TO
REUSE ALL OF THE DREDGE
MATERIAL?
>>SPEAKER: THAT WOULD COME IN
THE DESIGN PHASE WHEN WE HAVE
BETTER INFORMATION ABOUT THE
QUALITY OF THE MATERIAL, THAT
WOULD BE THE SECOND PHASE
CONSISTENCY DETERMINATION BUT I
BELIEVE THEY’RE COMMITTED IN THE
ROOM THERE, THEY CAN VOUCH
WHETHER OR NOT THIS MATERIAL IS
SUITABLE FOR BENEFICIAL REUSE.
THAT IS MINDING AT THIS TIME.
>>SPEAKER: THIS IS ERIK AGAIN
WE DO HAVE PERMISSION FROM
HEADQUARTERS THAT WE BENEFICIAL
REUSE ALL MATERIAL. THE BULK IS
WETLAND COVER AT THIS POINT
BASED ON ASSUMPTIONS WE HAVE
MADE WHICH TECHNICALLY MEANS
MONTEZUMA AT THIS POINT THEY’RE
THE ONLY ONES THAT CAN TAKE THAT
1.71 MILLION YARDS GOING THERE,
150,000 YARDS OF COVER THAT
COULD GO TO ANY WETLAND
RESTORATION SITE.
>>PAT EKLUND: OKAY GREAT.
THANK YOU. AND THEN, LET’S SEE,
WHAT WAS THE LAST QUESTION? YOU
CAN HELP ME UNDERSTAND AT WHAT
POINT THROUGH THE THIS WHOLE
PROCESS BEFORE FINAL APPROVAL,
IS IT GOING TO BE COMING BACK TO
THE COMMISSION SO THAT IF NEEDED
WE CAN ADD SOME ADDITIONAL
CONDITIONS BECAUSE IF THIS IS
THE ONLY TIME WHERE WE CAN ADD
SPECIFIC CONDITIONS, THEN I
PROBABLY GOING TO LOOK AT THIS
WITH A FINE TOOTH COMB BUT I WAS
HOPING WE GOING TO GET ANOTHER
BITE AT THE APPLE WHICH IS
TYPICALLY WHAT WE HAVE DONE IN
THE PAST BUT I DON’T KNOW IF THE
PROCESS HAS BEEN CHANGED SINCE I
LEFT OF THE FEDERAL GOVERNMENT.
>>SPEAKER: YES THIS IS A PHASE
CONSISTENCY. FIRST PHASE IS A
GENERAL AUTHORIZATION BUT AS
WRITTEN SO FAR IT’S IN REVIEW.
THE STAFF RECOMMENDATION DOES
INCLUDE SOME GENERAL CONDITIONS
BUT NOT THE FINAL SET. IT ALSO
LISTS OUT SOME POTENTIAL
ADDITIONAL ITEMS THAT ARE NOT
BEING REQUIRED AT THIS TIME BUT
WOULD LIKELY BE REQUIRED. AT
THE SECOND PHASE WHEN WE’RE IN
THE PRECONSTRUCTION ENGINEERING
AND DESIGN PHASE, THE CORP WILL
BE COMING BACK TO US ANTICIPATED
IN 2025, ’26, PROBABLY 2026, WE
WILL HAVE A MORE DEFINITIVE
COMPLETE PICTURE OF THE PROJECT
AND WILL LIKELY MAKE MORE
REQUIREMENTS AT THAT TIME.
>>PAT EKLUND: I DIDN’T SEE IT
IN THE CONDITIONS OR MAY HAVE
MISSED IT THAT THEY WILL REUSE
ALL OF THE DREDGE MATERIAL.
>>SPEAKER: YOU DON’T HAVE TO
YET THAT’S WHY YOU MISSED IT
IT’S COMING OUT IN REVIEW AND
I’M SHARING IT WITH THE CORP IN
THE REPORT THEN YOU WILL SEE IT.
>>PAT ECKLUND: GREAT. SO OVER
TIME IT WILL BE HERE IN 2026
IT’S GOING TO BE HARD TO KNOW
BUT ANYWAY, OKAY. THAT’S GREAT.
IS IT POSSIBLE TO SEND
ADDITIONAL QUESTIONS IN WRITING
BEFORE THE NEXT MEETING? OR IS
THAT SOMETHING YOU PREFER NOT TO
DO?
>>SPEAKER: I’M HAPPY TO RECEIVE
WRITTEN COMMENTS. WE’LL DO OUR
BEST TO GET ANSWERS FOR YOU
BEFORE THE NEXT MEETING. I’M
FINE WITH THAT, BUT TO THE CHAIR
AND EXECUTIVE DIRECTOR.
>>PAT ECKLUND: THAT WOULD BE
GREAT. IF I COULD GET FEEDBACK
THAT WOULD BE GREAT.
>>CHAIR, ZACHARY WASSERMAN: TWO
COMMENTS BEFORE I GO TO THE NEXT
COMMISSIONER.
YES, CERTAINLY QUESTIONS AND
COMMENTS CAN COME IN. THIS IS
AN ONGOING PROCESS IT MAY NOT
AFFECT THIS VOTE. BUT THIS IS
NOT THE LAST TIME THIS PROJECT
WILL COME BEFORE US, AND THE
SECOND POINT, UNLESS I’M WRONG,
IN ADDITION TO COMING BACK FOR
FURTHER CONCURRENCE ON
CONFORMANCY, OR CONFORMANCE,
IT’S GET TO COME TO US FOR A
PERMIT. SO, WE WILL HAVE MORE
THAN ONE ADDITIONAL BITE AT THIS
APPLE.
COMMISSIONER GUNTHER?
>>ANDREW GUNTHER: THANK YOU
MR. CHAIRMAN. THANK YOU FOR THE
REALLY DETAILED RICH
PRESENTATION. I REALLY
APPRECIATE IT. I JUST HAVE TWO
QUICK QUESTIONS. FIRST OF ALL,
THE ELECTRICAL WORK THAT’S GOING
TO BE DONE AS PART OF BUILDING
THE TURNING BASIN. I MEAN,
ELECTRIFICATION OF OPERATING
DIESEL MOTORS AT THE PORT IS A
VERY, VERY IMPORTANT PART OF
IMPROVING THE HEALTH OF THE
LOCAL COMMUNITIES IN REDUCING
EMISSIONS. SO, IT DOES — DOES
THAT WORK WHICH WAS DESCRIBED AS
FACILITATING THE USE OF
ELECTRICAL DREDGES, DOES THAT
ALSO CONTRIBUTE, SORT OF, AS THE
PORT AS A WHOLE, FOR
ELECTRIFICATION FOR OTHER
PROCESSES AT THE PORT OR FOR
CHARGING SOME OF THE BATTERY
OPERATED MACHINERY THEY HAVE
NOW? I HOPE THAT WE CAN MAKE —
THAT THIS WILL NOT ONLY REDUCE
MISSIONS DURING DREDGING, BUT
ALSO CONTRIBUTE TO REDUCING
EMISSIONS IN THE FUTURE. AND
THEN, SECONDLY, I DIDN’T SEE
MUCH DISCUSSION OF SEA LEVEL
RISE. NOW, I HAVE A FEELING
THAT’S BECAUSE OF THE NATURE —
THAT’S — MAYBE THAT’S IN PHASE
TWO, BRENDA? BUT I JUST WANTED
TO MAKE SURE THAT AS THIS
PROJECT GOES FORWARD AND SO MUCH
OF THE SHORELINE IN THAT REGION
IS ALTERED, BUT IT’S ALTERED IN
A WAY THAT IS CONSISTENT WITH
BUILDING RESILIENCY TO SEA LEVEL
RISE, WHICH I ASSUME IS KIND OF
INTEGRATED INTO OUR PERMIT
DECISION, IF I UNDERSTAND IT
RIGHT?
>>BRENDA GOEDEN: I WILL START
TO ADDRESS THAT. THE CORP AND
PORT CAN BACK ME UP — TRY TO
SAY THAT FIVE TIMES FAST — BUT
I WOULD ALSO ELECT THE PORT TO
ADDRESS THE ELECTRIFICATION
ISSUE BECAUSE I’M UNFAMILIAR
WITH THEIR PLANS. REGARDING SEA
LEVEL RISE, WHICH SAY CONCERN OF
THE CITY OF ALAMEDA AND OTHERS,
THE PORT AND THE CORP VIEW THIS
AS A NAVIGATION IMPROVEMENT
PROJECT. THEY’RE NOT PROPOSING
SHORELINE PROPOSE PROTECTION.
THEY’RE BUILDING A BULK HEAD.
AS I UNDERSTAND THE PLANS, AND
THE ARMY CORP’S ANALYSIS OF SEA
LEVEL RISE, UNDER THEIR
GUIDANCE, WHICH IS NOT THE SAME
AS THE STATE OF CALIFORNIA
GUIDANCE, IT’S SIMILAR BUT A
LITTLE DIFFERENT, THE PROJECT IS
RESILIENT TO FLOODING THROUGH
ALL PHASES OF THEIR PROJECT, I
BELIEVE, TO 2090. AND I’M
TALKING ABOUT THAT OFF THE TOP
OF MY HEAD RIGHT NOW. SO DON’T
QUOTE ME ON THAT, AND THERE IS
ONLY ONE AREA THAT IS NOT
RESILIENT. SO, THE WAY THEY
PROPOSED TO CONSTRUCT IT, IT’S
AT OR ABOVE THE EXISTING
ELEVATION. THEY DON’T
ANTICIPATE FLOODING IN THAT
REGION. THE OTHER ANSWER, WHICH
CAME UP DURING THE ENGINEERING
CRITERIA REVIEW BOARD — AND I
BELIEVE BARNEY IN THE ROOM, SO
HE MAY WANT TO SPEAK TO THIS
FROM THE ARMY CORP — THE
QUESTION WAS DID YOU INCORPORATE
SEA LEVEL RISE RESILIENCE IN
THIS PROJECT; AND HIS ANSWER
WAS, UNDER THIS FEASIBILITY
STUDY, BECAUSE OF THE NATURE, IT
DOES NOT INCLUDE SHORELINE
PROTECTION. THAT WOULD BE A
DIFFERENT AUTHORITY AND A
DIFFERENT FEASIBILITY FOR THE
CITY OF ALAMEDA. AND THEY COULD
REQUEST THAT OF THE CORP, BUT
THE CORP WOULD HAVE TO FIND A
NATIONAL ECONOMIC INTEREST AND
HAVE THAT AS A SEPARATE KIND OF
PROJECT. IT’S BULKHEAD, NOT
SHORELINE PROTECTION. YES THERE
IS FLOODING ON ALAMEDA FROM OUR
LOOK AT IT COMES FROM A NUMBER
OF OTHER SOURCES NOT
SPECIFICALLY THIS AREA EXCEPT
FOR THE LIMITED HIGH ELEVATION
ISSUE HIGH SEA LEVEL ELEVATION
ISSUE. THAT’S THE WAY THE
COMMISSION STAFF HAS ADDRESSED
IT AT THIS POINT.
>>ANDREW GUNTHER: SO YOU’RE
SAYING BRENDA THAT AS IMAGINED
CURRENTLY, OBVIOUSLY THERE IS
GOING TO BE MUCH MORE WORK DONE
ON THE SPECIFICS OF A PROJECT.
THE PROJECT WILL — WHEN THE
PROJECT IS COMPLETED, THE
SHORELINE IN THAT AREA WILL BE
RESILIENT TO A SEA LEVEL RISE AT
A CERTAIN AMOUNT. I JUST WANT
TO MAKE SURE WE’RE NOT PROPOSING
TO SPEND $500 MILLION IN AN AREA
AND NOT HAVE THAT PRODUCE A
RESILIENT SHORELINE.
>>BRENDA GOEDEN: I UNDERSTAND
WHAT YOU’RE SAYING, AND
APPRECIATE IT. I MEAN BASICALLY
A BULK IS CREATING A NEW
SHORELINE BUT NOT YOU KNOW,
INCREASING THE HEIGHTS OF THE
SHORELINE IT’S SIMPLY INCREASING
THE NEW SHORELINE THERE IS NO
PROPOSED PROJECT THAT RAISES THE
ELEVATION OR PROTECTS THE
SHORELINE FROM SEA LEVEL RISE AT
THIS TIME AND FROM WHAT I
UNDERSTAND FROM THE CORP THAT
WOULD BE A DIFFERENT PROJECT
THAN WHAT IS AUTHORIZED THROUGH
THEIR PROGRAM SO MAYBE THE CORP
OR PORT WANT TO STEP IN AT THIS
POINT AND HELP ME OUT?
>>STEVEN GOLDBECK: I WOULD ADD
THAT POLICIES ON RISING SEA
LEVEL REQUIRE LARGER PROJECTS TO
BE RESILIENT TO MID-CENTURY AND
HAVE AN ADAPTIVE MANAGEMENT PLAN
TO END THE CENTURY. BUT THAT’S
FOR THE PROJECT, AND THE PROJECT
IS A TURNING BASIN. SO, YOUR
POLICIES WOULD REQUIRE THAT
PROJECT ITSELF THAT BEING THE
TURNING BASIN BE RESILIENT NOT
NECESSARILY PROVIDE PROTECTION
FOR ALL THE SURROUNDING AREAS.
>>BRENDA GOEDEN: THANK YOU,
STEVE. ALSO WE CAN DIRECT YOU
TO POLICY SEVEN WHICH SAYS WHEN
WE’RE IN THIS SITUATION WE DON’T
HAVE A REGIONAL SEA LEVEL RISE
ADAPTATION PLAN PROJECT THAT ARE
REGIONAL BENEFITS INCLUDING
TRANSITION TRANSPORTATION AND
THEN THIS IS THE MARINE
TRANSPORTATION ISSUE.
>>STEVEN GOLDBECK: THAT’S NO
OPINION FROM STAFF ON WHETHER IT
WOULD BE GOOD TO HAVE GREATER
PROTECTION OF THE SHORELINE BUT
SIMPLY YOUR POLICIES CALL FOR
THAT.
>>SPEAKER: THANK YOU, STEVE.
>>CHAIR, ZACHARY WASSERMAN:
COMMISSIONER SHOWALTER.
>>PATRICIA SHOWALTER: I WOULD
LIKE ANOTHER BRIEF UNDERSTANDING
OF A CHIEF’S REPORT. SORT OF,
FROM A HIGH-LEVEL MY
UNDERSTANDING OF THE CHIEF’S
REPORT IS BASICALLY IF IT GIVES
ENOUGH SPECIFICITY THAT THE
HEADQUARTERS OF THE CORP OF
ENGINEERS FEELS CONFIDENT TO ASK
CONGRESS FOR AUTHORIZATION
AND/OR FUNDING TO GO FORWARD
WITH THIS PROJECT, IS THAT
CORRECT?
>>SPEAKER: YES. I THINK I CAN
ANSWER THAT WHEN WE SUBMIT IN
JANUARY IS GOING TO BE A FINAL
REPORT WITH OUR RECOMMENDATION
AND THAT GOES TO HEADQUARTERS
AND THEN WE — WE PRODUCE A
CHIEF’S REPORT THAT WOULD MAKE
— THAT WOULD BE DONE BY THE END
OF MAY OF 2024, AND THAT IS A
RECOMMENDATION TO CONGRESS.
CONGRESS CAN DECIDE WHETHER, AT
THEIR DISCRETION, WHETHER
THEY’RE GOING TO AUTHORIZE IT SO
IT CAN GET INTO [INDISCERNIBLE]
2024 AND AT THEIR DISCRETION
WHETHER THEY WANT TO APPROPRIATE
FUND AS WELL. THOSE ARE TWO
SEPARATE DECISIONS THAT THEY
NEED TO MAKE AND THEY CAN DECIDE
TO SAY NO TO BOTH, SAY YES TO
BOTH, OR THEY CAN AUTHORIZE AND
THEN AT A LATER TIME
APPROPRIATE.
>>PATRICIA SHOWALTER: THANK YOU
ERICA. THAT’S WHAT I THOUGHT I
REMEMBERED. BUT I WANTED TO
MAKE SURE. SO, I GUESS WHAT MY
FEELING IS THAT BECAUSE THIS IS
THE PHASE WE’RE AT, IT’S
APPROPRIATE, I FEEL LIKE, FOR US
TO SUPPORT THIS GOING FORWARD AT
THIS PHASE. I MEAN, GRANTED,
WHEN WE GET MORE DETAILS, WE
WILL HAVE A LOT MORE QUESTIONS
AND THERE WILL BE THINGS WE WANT
TO MAKE SURE ARE TAKEN CARE OF.
BUT AT THIS POINT, TO GET — YOU
KNOW, TO GET — MAKE SURE THAT
THIS PROCESS GOING FORWARD IN A
TIMELY MANNER, I’M VERY
SUPPORTIVE OF IT. AND
PARTICULARLY, THE REUSE OF THE
DREDGE SEDIMENT. THAT IS A
WONDERFUL FEATURE. AND
SOMETHING THAT IS VERY, VERY
IMPORTANT FOR OUR OTHER SEA
LEVEL RISE PROTECTION EFFORTS,
PARTICULARLY MARSH RESTORATION
THROUGHOUT THE BAY. SO, I’M
REALLY GLAD TO SEE THIS. AND I
LOOK FORWARD TO WORKING ON IT
FOR QUITE A WHILE. THANK YOU.
>>SPEAKER: THANK YOU
COMMISSIONER.
>>CHAIR, ZACHARY WASSERMAN: WE
HAVE A HAND, COMMISSIONER
NELSON?
>>BARRY NELSON: [LAUGHTER]
IT KEEPS DROPPING AWAY. TWO
ISSUES FOR STAFF. QUESTIONS
ABOUT — FIRST IS ABOUT HOWARD
TERMINAL. IF I AM REMEMBERING
CORRECTLY, WHEN WE DELETED THE
SEAPORT PLAN DESIGNATION FOR
HOWARD TERMINAL, IT CAME WITH
THE CONDITION THAT IF AS DID NOT
CONSTRUCT A BALLPARK AT HOWARD
TERMINAL, THAT SEAPORT WOULD
REVERT BACK TO PLAN
JURISDICTION.
>>BRENDA GOEDEN: ALMOST. IT
REVERTS BACK TO PORT PRIORITY
USE.
>>BARRY NELSON: IF THAT HAD
HAPPENED LAST MONTH, AND THE AS
MOVED TO LAS VEGAS, AND THEY’RE
NOT BUILDING A TERMINAL THEN THE
PORT PRIORITY DESIGNATION WOULD
BE ON THE SITE AND I ASSUME THE
STAFF WOULD INCLUDE ANALYSIS OF
WHAT THIS MEANS FOR HOWARD
TERMINAL. SOME OF THIS WOULD BE
EXCAVATED, HOWARD TERMINAL WOULD
BE SHORTER, ONLY ACCOMMODATE
CERTAIN SHIPS AND SO FORTH.
THAT DECISION HASN’T BEEN MADE
BY THE CITY AND THE AS, IT SEEMS
LIKE SHOULD WE BE THINKING ABOUT
THAT ISSUE?
>>BRENDA GOEDEN: I WOULD SAY,
AS I LOOK TO MY ESTEEMED
COLLEAGUES, DEPUTY DIRECTOR,
EXECUTIVE DEPUTY DIRECTOR, IS
WE’RE CURRENTLY BEHOLDEN TO THE
LAWS AND POLICIES THAT WE HAVE,
BECAUSE THE REVERTING ACTION HAS
NOT TAKEN PLACE, AND IT WILL
LIKELY NOT TAKE PLACE BEFORE
DECEMBER 21ST A.M., WE NEED TO
USE THE POLICIES AND THE
PRIORITY USE AREAS THAT WE HAVE
IN FRONT OF US AT THAT TIME. IF
THE PRIORITY USE AREA REVERTS TO
PORT PRIORITY USE BEFORE THE
NEXT PHASE CONSISTENCY
DETERMINATION, WE WOULD CONSIDER
IT DIFFERENTLY AND LOOK FOR
DIFFERENT INFORMATION. BUT, AT
THIS TIME, THE STAFF
RECOMMENDATION EXPLAINS THAT
THERE IS NO PORT PRIORITY USE AT
HOWARD TERMINAL AT THIS TIME.
>>BARRY NELSON: AND THAT LEAVES
THE QUESTION ABOUT PHASING AND
SEGMENTATION. WHAT HAPPENS IF
WE LOOK AT IT NOW AND SAY
TOTALLY INCONSISTENT WITH OUR
PLAN, AND THEN WE LOOK AT IT IN
A YEAR OR WHENEVER IT COMES BACK
TO US FOR THE NEXT PHASE, AND
THE AS HAVE MADE THEIR DECISION,
PORT PRIORITY USE DESIGNATION IS
BACK ON THE SITE, AT THAT POINT
WE DO AN ANALYSIS ABOUT IMPACTS
ON THE PORT PRIORITY USE. WHAT
HAPPENS IF WE REACH A DIFFERENT
CONCLUSION ON THE SECOND PHASE
BECAUSE THE PORT PRIORITY USE
ISSUE GIVEN THAT WE FOUND
CONSISTENCY OAT FIRST PHASE WITH
DIFFERENT CONSISTENCY — WITH
DIFFERENT DESIGNATION FOR THE
SITE?
>>SPEAKER: I CAN ADD A LITTLE
BIT TO THE CONVERSATION MICHAEL
NG G STAFF ATTORNEY. WE LOOK AT
WHETHER THE CONTINUED PLACEMENT
OR REMOVAL OF PORT PRIORITY USE
AREA DESIGNATION AT HOWARD
TERMINAL HAD ANY PARTICULAR
SIGNIFICANCE OR CONSEQUENCE WITH
THE RESPECT TO REALIZATION OF
OAKLAND TURNING BASIN PROJECT IF
WE PROCEED WE ANALYZED THAT AT
THE TIME OF THE BPA 2/19 WHEN
THAT DESIGN DESIGNATION WAS
REMOVED, AND I BELIEVE OUR VIEW
AT THAT TIME WHICH I THINK IS
STILL OUR VIEW IS THAT IT IS NOT
WHETHER IT’S THERE OR NOT IS NOT
A HINDRANCE TO THE REALIZATION
OF THE TURNING BASIN’S PROJECT I
THINK WHAT YOU’RE REFERRING TO
IS THE A.B. 1191 WHICH WAS THE
SPECIAL HOWARD TERMINAL BALLPARK
PROJECT THAT DOES HAVE THIS,
SORT OF, AUTOMATIC REVERSION
CLAUSE THAT IF THERE’S NO
DEVELOPMENT AGREEMENT BETWEEN
THE CITY AND THE AS BY 2025 THAT
THE DESIGNATION WILL BE
REINSTATED AS IF IT HAD NEVER
BEEN REMOVED BUT AGAIN WHETHER
IT’S THERE OR NOT GIVEN THE
PURPOSE OF WHAT THE PA
DESIGNATION IS FOR WHICH IS
MINIMIZE MITIGATE PRESSURE FOR
THE INCREASED FILL FOR PORT
PURPOSES I DON’T THINK THAT THIS
PROJECT IMPLICATES THAT POLICY
ISSUE.
>>BARRY NELSON: SECOND
QUESTION. ALAMEDA AND THE
SPEAKER FROM EARTH JUSTICE ON
BEHALF OF WEST OAKLAND
INDICATORS RAISED A NUMBER OF
QUESTIONS ABOUT THE PROJECT,
LAND USE, OPERATIONS
CONSISTENCY, WITH FEDERAL
POLICIES AND A NUMBER OF OTHER
THINGS. WE HAVE SOME OF THOSE
CONCERNS, SOME ARE OUTSIDE OUR
JURISDICTION, WE HAVE OUR OWN
EQUITY POLICIES THAT MAY OVERLAP
BUT ARE NOT THE SAME AS THE
FEDERAL POLICIES. I DON’T KNOW
IF BRENDA YOU’RE READY TO
DISCUSS THIS NOW OR SOMETHING
STAFF WANTS TO THINK ABOUT
PREPARING FOR THE STAFF
RECOMMENDATION. BUT I WOULD
LIKE TO UNDERSTAND WHERE THOSE
CONCERNS RAISED BY ALAMEDA AND
EARTH JUSTICE IN PARTICULAR,
OVERLAP WITH THE COMMISSION’S
POLICIES AND THEIR ISSUES THAT
WE SHOULD BE DISCUSSING AND
CONSIDERING IN MAKING THIS
DECISION OR WHETHER THEY’RE JUST
OUTSIDE OUR AUTHORITY AND
THEY’RE NOT GOING TO BE A PART
OF OUR CONSIDERATION OF THE
PROJECT?
>>BRENDA GOEDEN: I GUESS I
COULD MENTION THEM IN BRIEF.
SO, AS MICHAEL SPOKE TO OR
ACTING UNDER COASTAL MANAGEMENT
ACT, AND AROUND THAT ACT WE ARE
DIRECT TO LOOK AT THE EFFECTS TO
THE COASTAL ZONE, WHICH IN THIS
CASE IS SAN FRANCISCO BAY. AND
WE INVESTIGATED ACTUALLY VERY
THOROUGHLY OVER THE LAST TWO
YEARS WHETHER OR NOT AIR QUALITY
IMPACTS WERE SOMETHING THAT THE
COMMISSION COULD ADDRESS UNDER
CZMA, AND I THINK WE DETERMINED,
MICHAEL, STEVE, CORRECT ME IF I
AM WRONG, DETERMINED THAT WE DID
NOT HAVE NEXUS THAT THE AIR
QUALITY THAT ARMY CORP HAS TO BE
RESPONSIBLE TO THE FEDERAL CLEAN
AIR ACT AND AS I UNDERSTAND IT
THEY INCLUDE THAT INFORMATION AS
PART OF THEIR ENVIRONMENTAL
REVIEW AND CONSIDERATION OF THIS
PROJECT. SO WE DON’T HAVE THAT
NEXUS. WHERE WE HAVE A BIT OF
NEXUS ON AIR QUALITY IN MY
HUMBLE OPINION, AND I’M WAITING
TO FIGURE OUT IF I’M RIGHT IS
THAT PARTICULATE MATTER FROM
EMISSIONS FROM TRUCKS AND SHIPS
ACTUALLY DO IMPACT WATER
QUALITY. AND SO WE’RE DO HAVE A
BRIEF REQUIREMENT LOOKING AT
TRUCK ENGINES FOR REDUCTION OF
PARTICULATE MATTER BECAUSE OF
THE CONNECTION TO WATER QUALITY.
IN THE STAFF RECOMMENDATION
WE’LL SEE IF YOU AGREE WITH THAT
CONSIDERATION. THE CORP IS
RESPONSIBLE TO THE FEDERAL LAWS.
WE ARE RESPONSIBLE TO CZMA. WE
DO NOT INVESTIGATE VESSEL
TRAFFIC OR REGULATE VESSEL
EMISSIONS WE DO NOT REGULATE
TRUCK TRAFFIC. WE DO NOT
REGULATE CONSTRUCTION EQUIPMENT
BUT WE CAN MAKE REQUIREMENTS
AROUND IMPACTS TO WATER QUALITY,
FIDUCIARY AND WILDLIFE,
CONTAMINANT ISSUES. AND SO
WHETHER THERE IS A NEXUS TO
THOSE ITEMS PER THE POLICIES
THAT WE LAID OUT FOR YOU TODAY,
WE CAN MAKE REQUIREMENTS, BUT
WHERE WE DON’T HAVE POLICIES OR
AUTHORITY, WE DON’T — WE CANNOT
MAKE THOSE REQUIREMENTS. AND
REGARDING ENVIRONMENTAL JUSTICE
AS PHOENIX LAID OUT, THE WAY OUR
POLICIES ARE WRITTEN — AND I
THINK I’M FROZEN IN SOME
SCREENS, WE HAVE TO ENSURE THAT
PUBLIC ENGAGEMENT IS APPROPRIATE
AND CULTURALLY RELEVANT. AND WE
CAN WORK WITH THE FEDERAL AND
LOCAL PROJECT SPONSOR TO
CONTINUE PUBLIC ENGAGEMENT AND
TRY TO WORK HARDER TO MAKE IT,
ENSURE THAT THEY DO CULTURALLY
RELATIVE PUBLIC ENGAGEMENT AND
THAT THEY WORK WITH THE
COMMUNITY TO IDENTIFY MITIGATION
MEASURES WHERE WE HAVE
AUTHORITY. AND, AGAIN, OUR
AUTHORITY IT LIMITED IN THAT
REGARD. AND THEN REGARDING MED
NEED LANDING, I THINK I
MENTIONED EARLIER THAT THE PORT
IS RESPONSIBLE FOR GETTING
PROPERTY RIGHTS AND IF THEY
CAN’T GET PROPERTY RIGHTS THEY
CANNOT GET A PERMIT FROM BCDC.
AND REGARDING THEIR CONCERNS
ABOUT PUBLIC ACCESS. CERTAINLY
THE ALAMEDA LANDING AREA IS AN
AREA THAT BCDC STAFF HAS
IDENTIFIED AND ALREADY TALKED TO
THE PORT AND CORP ABOUT A
POTENTIAL PUBLIC ACCESS AMENITY
AT THAT SITE BECAUSE THEY WILL
BE CHANGING THE CONFIGURATION
SITE VIA REMOVING SOME OF THE
WATERFRONT WHARF AND DEM OCEAN
PORTIONS OF THE TWO WAREHOUSES
WHICH SHOULD OPEN UP VIEWS AND
PROVIDE OPPORTUNITIES FOR PUBLIC
ACCESS. AND THEN WE HAVE ALSO
TALKED TO THEM ABOUT THE
POTENTIAL FOR IN LIEU PUBLIC
ACCESS NEARBY. AND POTENTIALLY
PROVIDING PUBLIC ACCESS TO AN EJ
OR DISPROPORTIONATELY IMPACTED
COMMUNITY, BECAUSE THAT ALSO
PART OF OUR PUBLIC ACCESS
POLICIES. I AM HOPING THAT’S
HELPFUL.
>>BARRY NELSON: YES. THAT’S
ALL OF THOSE THAT WILL BE
ADDRESSED IN THE STAFF
RECOMMENDATIONS WHEN IT COMES
BACK TO US.
>>BRENDA GOEDEN: YES.
>>CHAIR, ZACHARY WASSERMAN:
COMMISSIONER GILMORE?
>>MARIE GILMORE: THANK YOU,
CHAIR WASSERMAN.
I WANT THANK BARRY AND BRENDA
BECAUSE YOU ANSWERED QUESTIONS I
WAS ABOUT TO ASK. I WAS, SORT
OF, DISTURBED BY THE OPPOSING
ENVIRONMENTAL DOCUMENTS THEY
SEEM TO COME OUT AT EITHER ENDS
OF THE SPECTRUM. BUT THANKS TO
YOUR EXPLANATION, BRENDA I FEEL
BETTER ABOUT IT. I’M ASSUMING
THAT EVERYTHING THAT YOU JUST
DISCUSSED DOES NOT HAVE TO BE
DETERMINED BY THE 21st. WE’RE
GOING TO GET ADDITIONAL BITES AT
PUBLIC MEETINGS, ENVIRONMENTAL
JUSTICE AND ALL OF THOSE THINGS
THAT YOU JUST, SORT OF, LISTED
OFF AND EXPLAINED. RIGHT?
>>BRENDA GOEDEN: YEAH. THAT IS
THE PLAN. RIGHT NOW, I THINK WE
HAVE EIGHT OR NINE REQUIREMENTS,
WHICH ARE GENERAL, IN THE STAFF
RECOMMENDATION WHICH ADDRESS
THESE ISSUES THAT ARE
OUTSTANDING. PARTICULARLY THE
PUBLIC ACCESS ENGAGEMENT, I
THINK IS ONE THAT YOU WILL BE
HEARTENED TO SEE IN SOME
ADDITIONAL INFORMATION ABOUT THE
CONTAMINANTS ASSOCIATED WITH
BOTH THE CONSTRUCTION SITE AND
THE DREDGING. AND I’M NOT
REMEMBERING THE REST OF THEM OFF
THE TOP OF MY HEAD, BUT, YOU
KNOW, THE SILT CURTAINS AND THE
PROTECTIONS FOR THE FISH AND
WILDLIFE AND WATER QUALITY.
>>MARIE GILMORE: OKAY. AND SO
AS WE, ASSUMING THIS PROJECT
MOVES FORWARD, WE WILL — AND WE
FIND OUT MORE ABOUT EXACTLY
WHAT’S BEING PROPOSED, WE CAN
ADD ADDITIONAL CONDITIONS OR
TIGHT END UP CERTAIN CONDITIONS.
SO WE’RE LOOKING AT THIS WHOLE
PROJECT ABOUT THE 300 FOOT
LEVEL, AND AS TIME GOES BY WE’RE
GETTING CLOSER AND CLOSER TO
GROUND LEVEL KIND OF THE WAY I
LOOK AT IT.
>>BRENDA GOEDEN: YES.
>>MARIE GILMORE: THANK YOU VERY
MUCH.
>>CHAIR, ZACHARY WASSERMAN: ANY
OTHER QUESTIONS FROM
COMMISSIONERS? I WOULD HAVE
EXPECTED TO YOU HAVE A LOT.
I JUST HAVE A COUPLE OF QUICK
ONES.
I HAVE A LITTLE FAMILIARITY WITH
DREDGING IN THE OAKLAND ESTUARY.
I HAVE BEEN WORKING ON IT SINCE
1978. I, IN PARTICULAR,
REMEMBER A HELICOPTER RIDE WITH
MAYOR LIONEL WILSON AND
CONGRESSMAN RON DELLUMS WHEN WE
WERE FIGHTING FOR FUNDS TO
DREDGE TO THINK IT WAS 38 FEET,
AND THERE WERE MANY PEOPLE WHO
DID NOT BELIEVE THAT WAS
NECESSARY THAT THESE BIG SHIPS
THAT EVERYBODY WAS TALKING ABOUT
WERE SIMPLY NOT ACKNOWLEDGE,
THEY WERE PIE IN THE SKY. OR I
GUESS, IN THE WATER. CLEARLY
THEY ARE INCREASE THEY CAME,
THEY ARE INCREASING IN SIZE.
AND I DO THINK THAT SOME
ADDITIONAL ATTENTION — NOT BY
THE 21st; I’LL ADDRESS IN THAT
MOMENT — BUT AS THIS COMES BACK
TO US IN THE FUTURE ITERATIONS
THAT NEEDS SOME MORE FACTS AND
ATTENTION, AS VICE CHAIR EISEN
INDICATED. I ALSO THINK, AS WE
MOVE FORWARD, WE NEED AS A
COMMISSION TO BE VERY CAREFUL
AND THOUGHTFUL — AND MICHAEL
TOOK US THROUGH A LONG TUTORIAL
EARLIER THIS AFTERNOON, BUT IT
WAS APPROPRIATE, BECAUSE WE HAVE
NOT DONE THIS IN A WHILE, AND
THERE ARE NEW COMMISSIONERS. WE
HAVE GOT FAIRLY LIMITED
JURISDICTION IN A LOT OF THESE
THINGS AND IT’S NOT THAT WE
SHOULDN’T VOICE OUR CONCERNS,
BUT WHEN IT COMES TO DIRECTOR
STAFF AND VOIDING AND VOTING, WE
NEED TO RECOGNIZE THAT AND HERE
WE DO IN TERMS OF RECOMMENDING
OR NOT CONFORMANCE IS QUITE
DIFFERENT FROM WHAT WE CAN DO
AND SHOULD DO WHEN IT COMES
BUDGET US FOR A PERMIT AND I
THINK UNDERSTANDING THOSE
DIFFERENCES BUT I WANT TO BE
CLEAR THAT IT’S AN ONGOING
PROCESS AND THAT MEANS THAT THE
PUBLIC OUTREACH AND IN
PARTICULAR THE OUTREACH TO EJ
THAT’S PART OF OUR POLICY
ONGOING PROCESS I’M NOT SAYING
ANYBODY HAS SUGGESTED THAT BUT
THE DIALOGUE IS NOT OVER IT WILL
CONTINUE AS THIS PROJECT GETS
FLESHED OUT AND MORE DETAILS
EMERGE. COMMISSIONER ECKLUND
HAS HER HAND UP.
>>PAT EKLUND: I’M SORRY FOR A
SECOND BITE AT THE APPLE. BUT
YOU TRIGGERED ME TO ASK A
QUESTION. IS THERE A
POSSIBILITY WE COULD GET A
ROADMAP OF WHERE BCDC IS GOING
TO HAVE INPUT ON THIS ISSUE
FIDUCIARY THE NEXT 5, 6 YEARS,
OR WHATEVER? JUST SO WE HAVE A
BETTER UNDERSTANDING OF WHERE WE
MIGHT BE ABLE TO BRING DIFFERENT
ISSUES?
THAT WOULD BE HELPFUL.
>>CHAIR, ZACHARY WASSERMAN: I
AGREE. THAT’S A VERY GOOD
SUGGESTION.
>>SPEAKER: WE CAN BRING THAT TO
THE NEXT MEETING ON.
>>CHAIR, ZACHARY WASSERMAN: ON
THIS WILL COME BACK ON THE 21st
FOR A VOTE ON THE CONFORMANCE
ISSUE FOR THE FIRST PHASE. AND
WITH THAT, I WOULD ENTERTAIN —
I’M SORRY. YOU WANT A LAST
WORD. SURE.
>>SPEAKER: YES. I DID. THANK
YOU SO MUCH. THROUGH THE CHAIR,
WE WANTED TO ADD A COUPLE OF
THINGS FOR THE RECORD, AND ONE
IS GOING TO BE RELATED TO
ELECTRIC DREDGING, AND SINCE THE
PORT IS PAYING FOR THAT 100%,
I’M GOING TO ASK JUSTIN TO COME
UP HERE IN A MINUTE. WE WILL
PROVIDE RESPONSES TO ALL THE
QUESTIONS WE HEARD TODAY TO
BRENDA FOR HER STAFF, TO MAKE IT
EASIER FOR HER STAFF REPORT. TO
ALL THE QUESTIONS WE HEARD TODAY
IT’S NOTHING NEW IT’S ALL IN THE
REPORT AND WE’LL POINT TO WHERE
THEY CAN BE FOUND. SPECIFICALLY
FOR COMMISSIONER EISEN, THE
ECONOMIC APPENDIX HAS REALLY
GOOD INFORMATION. THERE IS AN
ECONOMIC MODEL WE CALL THE
HARBOR SIM MODEL THAT’S USED TO
DETERMINE, LOOK AT PROJECTIONS,
CONSEQUENCES, A FUTURE WITHOUT
THE PROJECT. SO THAT IS A
REALLY GOOD DOCUMENT. AND WE’LL
ALSO PROVIDE SLIDES THAT WILL
HAVE CORRECTIONS IN THERE TO
MAKE IT CLARIFY.
AND I THINK THIS’S ALL I HAVE.
SO, WE WILL PROVIDE
CLARIFICATION DIRECTLY TO BRENDA
AS SOON AS POSSIBLE. AND ONE
LAST THING. ELECTRIC DREDGING
AND BENEFICIAL USE THAT WAS NOT
REQUIRED IS MITIGATION, THIS IS
THE FIRST TIME A CORP OF
ENGINEERS PROJECT HAS SUBMITTED
TO HEADQUARTERS A REQUEST TO
ASSISTANT SECRETARY OF THE ARMY
TO COST SHARE THAT WITHOUT BEING
REQUIRED TO DO IT. THIS IS
CALLED COMPREHENSIVE BENEFITS.
IT’S A NEW POLICY. WE WERE THE
FIRST TO DO THAT, FROM WHAT I
UNDERSTAND.
SO, THANK YOU FOR YOUR TIME. WE
REALLY APPRECIATE IT. JUSTIN?
>>SPEAKER: JUSTIN. PORT OF
OAKLAND. DIDN’T WANT TO LEAVE
THAT HANGING. ELECTRIC
DREDGING, THE INFRASTRUCTURE
PROPOSED TO BE INSTALLED
PURSUANT TO THE PROPOSED PROJECT
IS DISCRETE AND SPECIALIZED FOR
THE ELECTRIC DREDGERS. BUT REST
ASSURED THAT THE ELECTRICAL
POWER THAT WOULD BE MADE
AVAILABLE FOR THOSE UNITS DURING
CONSTRUCTION WOULD CERTAINLY BE
VALUABLE AS WE ALL STRIVE AND
MOVE FORWARD TO DECARBONIZE THE
PORTS. SO THE DEMANDS FOR
ELECTRICITY WILL ONLY INCREASE
OVER TIME AND REST ASSURED THAT
POWER THAT WILL BE MADE
AVAILABLE FOR THIS PROJECT WILL
BE UTILIZED FOR OTHER THINGS IN
THE FUTURE. THANK YOU.
>>CHAIR, ZACHARY WASSERMAN:
THAT TRIGGERED IN ME TWO QUICK
THINGS. ONE, THANK YOU FOR
EMPHASIZING THE IMPORTANCE IN
PIONEERING EFFORT OF THE
BENEFICIAL REUSE IN THIS
PROJECT. IT IS SOMETHING THIS
COMMISSION HAS CERTAINLY BEEN
STRIVING FOR SOMETIME, AND WE
ARE VERY HAPPY TO HAVE THE CORP
FULLY ON BOARD FOR THIS.
SECOND, WELL, IT MAY OR MAY NOT
BE DIRECTLY RELATED TO THIS
PROJECT — CERTAINLY RELATED TO
CONCERNS, THE PORT OF OAKLAND IS
UNDERTAKING A VERY MAJOR PROJECT
TO REDUCE EMISSIONS, BOTH IN THE
MODERATELY SHORT-TERM AND IN THE
LONGER TERM, REALLY WITH A
ZERO-EMISSION EMPHASIS TO WHICH
POINT THEY HAVE REDESIGNED THEIR
PORT LOGO TO EMPHASIZE THAT.
SO, THIS IS NOT — THE WORDS
THAT HAVE BEEN HEARD HERE BEFORE
ARE BEING LISTENED TO. I THANK
YOU VERY MUCH. I WILL ENTERTAIN
A MOTION TO ADJOURN.
COMMISSIONER MOULTON-PETERS
MOVES TO ADJOURN. COMMISSIONER
ADDIEGO SECONDS. SEEING NO
OPPOSITION THIS MEETING
ADJOURNS. WE’LL SEE OUT 21st
ENJOY HANUKKAH, ENJOY YOUR TIME.
BE SAFE.
[ADJOURNED]
Learn How to Participate
Bagley-Keene Open Meeting Act
As a state agency, the Commission is governed by the Bagley-Keene Open Meeting Act which requires the Commission to: (1) publish an agenda at least ten days in advance of any meeting; and (2) describe specifically in that agenda the items to be transacted or discussed. Public notices of Commission meetings and staff reports (as applicable) dealing with matters on the meeting agendas can be found on BCDC’s website. Simply access Commission Meetings under the “Public Meetings” tab on the website and select the date of the meeting.
How to Provide Comments and Comment Time Limits
Pursuant to state law, the Commission is currently conducting its public meetings in a “hybrid” fashion. Each meeting notice will specify (1) where the meeting is being primarily held physically, (2) all teleconference locations, which will be publicly-accessible, and (3) the ZOOM virtual meeting link. If you would like to comment at the beginning of the meeting or on an item scheduled for public discussion, you may do so in one of three ways: (1) being present at the primary physical or a teleconference meeting location; (2) emailing comments in advance to public comment until 10 a.m. on the day of the meeting; and (3) participating via ZOOM during the meeting.
If you plan to participate through ZOOM, please use your ZOOM-enabled device and click on the “raise your hand” button, and then wait to speak until called upon. If you are using a telephone to call into the meeting, select *6 to unmute your phone and you will then be able to speak. We ask that everyone use the mute button when not speaking. It is also important that you not put your phone on hold. Each speaker may be limited to a maximum of three minutes or less at the discretion of the Chair during the public comment period depending on the volume of persons intending to provide public comment. Any speakers who exceed the time limits or interfere with the meeting may be muted by the Chair. It is strongly recommended that public comments be submitted in writing so they can be distributed to all Commission members in advance of the meeting for review. You are encouraged to submit written comments of any length and detailed information to the staff prior to the meeting at the email address above, which will be distributed to the Commission members.
Questions and Staff Reports
If you have any questions concerning an item on the agenda, would like to receive notice of future hearings, or access staff reports related to the item, please contact the staff member whose name, email address and direct phone number are indicated in parenthesis at the end of the agenda item.
Campaign Contributions
State law requires Commissioners to disqualify themselves from voting on any matter if they have received a campaign contribution from an interested party within the past 12 months. If you intend to speak on any hearing item, please indicate in your testimony if you have made campaign contributions in excess of $250 to any Commissioner within the last year, and if so, to which Commissioner(s) you have contributed. Other legal requirements govern contributions by applicants and other interested parties and establish criteria for Commissioner conflicts of interest. Please consult with the staff counsel if you have any questions about the rules that pertain to campaign contributions or conflicts of interest.
Access to Meetings
Meetings are physically held in venues that are accessible to persons with disabilities. If you require special assistance or have technical questions, please contact staff at least three days prior to the meeting via email. We will attempt to make the virtual meeting accessible via ZOOM accessibility capabilities, as well.
